Performance Outcomes Acceptable Outcomes Response
maintenance of existing
infrastructure.
Environmental protection No acceptable outcome Complies
provided
PO11 The development will ensure
that earthworks minimise any
Earthworks minimise any
adverse impact upon
adverse impact upon
groundwater, watercourses,
groundwater, watercourses,
drainage lines, wetlands, and
drainage lines, wetlands, and
native vegetation.
native vegetation.
Dams AO12.1 Not Applicable
PO12 Where the site is in the Rural The development site is not
zone— located within a Rural zone.
Dam location and construction
does not impact upon a) the land has a slope of
neighbouring properties or less than 25% (1:4);
road reserves, in terms of—
b) the earthworks including
a) hydrology; cut and fill batters and
retaining walls are
b) alteration of existing
setback a minimum of
overland flow paths
50 metres from the
and patterns;
property boundary; and
c) landslide or failure of
c) the size of the lot is
dam wall; and
greater than 5 hectares.
d) effluent disposal areas.
AO12.2 Not Applicable
Where the site is in the Rural The development site is not
residential zone or the Rural located within a Rural
zone and the lot is less than 5 residential zone or a Rural
hectares: zone.
a) the land has a slope of
less than 1:6;
b) the earthworks
including cut and fill
batters and retaining
walls are setback a
minimum of 20 metres
110
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Appendix E - Noosa Plan 2020 Assessment.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.