46. All frontage works must match neatly with existing road and verge/footpath
features. Additional works beyond the frontage may be required to provide an
acceptable transition to existing road and verge/footpath profiles. In this regard,
any sections of the footpath in the common property frontage of the site that is
either damaged or missing must be replaced as part of these works.
Site Access and Driveways
47. Any existing unnecessary or redundant property accesses must be removed,
and the kerb, footpath and verge area reinstated to match the existing footpath
and/or verge treatments. Grassed verge areas to be reinstated must be
provided with 100 mm topsoil and grass seed or turf, and must be maintained
by the developer until established.
48. The following must be complied with during the construction of the required
crossover/driveway:
a. The driveway must be constructed so as not to concentrate stormwater
runoff onto neighbouring properties or cause ponding of water within the
road reserve
Earthworks
49. The finished surface levels of the site must be graded and shaped to ensure
that all surface runoff is directed to the proposed drainage system and not
directed on to any adjoining property.
50. All earthworks shall be undertaken in accordance with the provisions of AS
3798 Guidelines on Earthworks for Commercial and Residential Development.
Certification must be provided by an RPEQ and submitted to Council the issue
of the Certificate of Classification for the building.
Service Conduits under Existing Road Features
51. Electrical conduits or other services proposed to be installed under existing
sealed carriageways, concrete pathways or concrete/sealed driveways must be
installed by boring. Trenching is not permitted, unless specifically approved by
Council.
Supervision/Certification
52. Upon completion of the work a certificate must be issued by an RPEQ certifying
that the works have been constructed in accordance with the Operational
Works permit.
Landscaping
53. The finished level of all mulch in garden beds must be a minimum of 50mm
below the level of the adjacent top of pavement. All landscaping is to be
constructed in accordance with Council’s Planning Scheme Policy PSP03
Landscaping Plants and Guidelines.
54. All approved landscaping works must be maintained in good condition for the
duration of the approved use.
55. All landscape works must be constructed and work procedure undertaken in
accordance with:
a. The approved plan and conditions detailed in this Decision Notice.
b. All relevant council Planning Scheme Policies, standard drawings,
standard specifications and guidelines.
56. Landscape works must be supervised, constructed and certified by qualified
persons*. (* Refer to Advisory Note)
Page 14 of 21
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.