Council Resolution
Moved: Cr Jurisevic
Seconded: Cr Bolton
The General Committee recommendations dated 12 January 2015 be adopted except where
dealt with or held over by separate resolution.
Carried.
2 OPERATIONAL WORKS FOR PRESCRIBED TIDAL WORKS JETTY SITUATED AT 256
GYMPIE TERRACE, NOOSAVILLE OPW14/0307
That Council note the report by the Development Engineer to the General Committee
Meeting dated 12 January 2015 regarding Application No. OPW14/0307 for a Development
Permit for Operational Works for Prescribed Tidal Works – Commercial Jetty situated at
256 Gympie Terrace, Noosaville and approve the application in accordance with the
following conditions:
1. Development undertaken in accordance with this approval must generally comply
with the approved plans of development. The approved plans are listed in the table
below and as may be amended by these conditions.
Plan No. Rev. Plan/Document Name Date
4656-100 - General Notes & Locality Plan, prepared by 29 May 2014
International Marina Consultants Pty Ltd
4656-101 - Demolition Plan, prepared by International 28 May 2014
Marina Consultants Pty Ltd
4656-102/A A General Arrangement, prepared by International 16 October 2014
Marina Consultants Pty Ltd
4656-103/A A Elevation, prepared by International Marina 16 October 2014
Consultants Pty Ltd
4656-104/A A Pile Layout, Profile and Schedule, prepared by 16 October 2014
International Marina Consultants Pty Ltd
4656-105/A A Pontoon Setout, prepared by International 16 October 2014
Marina Consultants Pty Ltd
4656-106 - 1.2m Overall Width x 7.5 Long Gangway, 30 May 2014
prepared by International Marina Consultants
Pty Ltd
4656-109 A Pontoon Setout, prepared by International 30 May 2014
Marina Consultants Pty Ltd
2. All structures associated with the use (jetty and pontoons) must be constructed
wholly within the lease area as shown on SP146043 dated 4 December 2013.
3. To ensure the safety of persons accessing the approved works and to prevent
environmental harm, a safety audit of the on-site fuel storage tanks, bowsers and
associated pipework, valves, vents and systems shall be conducted by a suitably
qualified professional and submitted to Council for approval. The audit shall
demonstrate that the fuel systems are in a safe and serviceable condition or, where
necessary, identify repair and rectification requirements to meet the relevant
Australian Standards and industry best practice environmental management. Any
repair works must be completed, with certification submitted by the auditor to Council,
prior to the use of the new works (pontoon/jetty extensions).
Page 6 of 21
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.