ORDINARY MEETING MINUTES                                                         15 JANUARY 2015


    4.    Structures shall be designed and constructed such that they are free standing within
          the waterway and are not connected to or behind the revetment wall or rock wall.
    5.    No posts or vertical supports of the proposed structures are to extend vertically above
          the height of the new piles.
    6.    No boatlifting devices are to be attached or moored at the jetty structure for the
          purpose of elevating a vessel above the water without Council approval.
    7.    The jetty shall be constructed in a manner to render the underside area vermin proof.
    8.    The connection point for any electrical reticulation system extending beyond the
          revetment wall must be located above the Q100 flood level.
    9.    Lighting associated with the use shall be designed, installed, operated, and
          maintained in accordance with Section 3 of AS4282 Control of the Obtrusive Effects
          of Outdoor Lighting.
    10.   Boat repair activities will not be permitted on site.
    11.   Wastewater and sullage shall only be disposed of at approved pumpout facilities.
    12.   The mooring facility shall not be utilised for live-aboard purposes.
    13.   Any construction and post construction activity is not to impact on the condition of the
          waterway, and is to be conducted so as not to breach the Environmental Protection
          Act (EPA) 1994 and the Environmental Protection (Water) Policy 1997.
    14.   Certification by a Registered Professional Engineer of Queensland (RPEQ) shall be
          submitted to Council. The certification shall state that the works have been
          constructed in accordance with best practice methods, are in accordance with
          Coastal Protection and Management Act 1995, are structurally sound and will have
          no detrimental effect on the river bed or river bank.
    15.   A final inspection and approval of the structure by Council’s Inspector is required.
          Please contact Council’s Planning Assessment Section to arrange the inspection.
    Advisory Notes
    1.    Council has undertaken an audit check of the Operational Works drawings in relation
          to the proposed works. A detailed design check of the calculations and drawings has
          not been undertaken, as they have been certified by a RPEQ. The RPEQ bears full
          responsibility for all aspects of the engineering design. Council reserves the right to
          require further amendments and/or additions at a later date, should design errors
          become apparent.
    2.    Council reserves the right to call up any performance bond held or levy charges
          against the property, should emergency works be required to be undertaken by
          Council to make the site safe due to inactivity on the development site for extended
          periods of time.
    3.    Should any changes or modifications to the approved plans be required as a result of
          construction constraints, a “Request to change an existing approval” under the
          Sustainable Planning Act 2009 must be made. Amended plans clearly indicating the
          changes must be lodged with this application along with the appropriate fees.
    4.    The Environmental Protection Act 1994 states that a person must not carry out any
          activity that causes, or is likely to cause, environmental harm unless the person takes
          all reasonable and practicable measures to prevent or minimise the harm.
          Environmental harm includes environmental nuisance. In this regard, persons and
          entities involved in the construction and operation of this development are to adhere
          to their ‘general environmental duty’ to minimise the risk of causing environmental
          harm.


                                                                                     Page 7 of 21
Log in to download the original file

2015-01-15 Ordinary Meeting Minutes(PDF, 149KB).pdf · 152 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.