Skip to the record
Search everything, all in one place.

Council archive · source document

Part 8 of 37 Appendix 6 - Flood Study MCU12/0208

of 115

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Very large file (93.6 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.

Noosa on Weyba
Flood Study
                                                                                         ~,.,CardnO.

7                    Proposed Development

7.1       Proposed Development
The proposed development plan is shown in Figure 13. The roughness values were not altered in the

developed case, as proposed urban areas will be filled, where necessary, to above the 100 year ARI
developed case peak flood level (with climate change).
J&K Hofmann Site

The proposed development of the J&K Hofmann site is predominantly outside of the 100 year ARI inundation
extent.      Minor sections of filling are required for three lots within Precinct I.   The 100 year ARI developed
case    peak flood level (with climate change) is 3.45 mAHD in this area. Therefore the minimum floor levels
will be set above 3.95 mAHD to provide sufficient flood immunity in accordance with SCRC requirements.

Compensatory excavation in this area is not proposed.                However, if required by Council, this could be
conducted in the asset protection zone adjacent to the filled lots.

To provide attenuation of peak flows, a culvert crossing of the Eenie Creek tributary will be located within the
easement at the northern end of the site. Detention basins will also be required for the northern section of
Precinct I as well as Precinct L. Sizing of these detention basins will be conducted during detailed design.

It is proposed that Hollett Road West should be     upgraded by council, as a cost to the Noosa on Weyba
project, to ensure that 10 year ARI flood immunity is provided. This road will also be trafficable during a PMF
event to allow for emergency access to Precincts L, K and J. Precincts H and I will be able to access the site
from Walter Hay Drive.

Northbrook Site

It is proposed that a large area will be filled to levels above the 100 year ARI flood level (with climate

change). A waterway corridor of a minimum 120 metre width will be maintained in this area. At the southern
boundary of the site, the waterway corridor increases to around 190 metres so that existing overland flow
paths are maintained. No excavation within the waterway corridor is proposed so as to maintain existing
vegetation. The 100 year ARI developed case peak flood level (with climate change) is 2.90 mAHD in these
areas. Therefore the minimum floor levels will be set above 3.40 mAHD to provide sufficient flood immunity

in accordance with SCRC requirements. The entire area will be filled to levels above the 100 year ARI flood
level (with climate change).

Road crossings of Keyser Creek and one of its tributaries are also proposed. These crossings will have 100

year ARI flood immunity. Site access along the northern crossing of Keyser Creek (i.e. Hollett Road East)
will also be trafficable during a PMF event.        The road crossings will also provide attenuation of peak flows.
A secondary access route along Tidswell Road is also proposed, and so this road needed to be upgraded in
the modelling to provide sufficient flood immunity.


7.2       Proposed Structures
The proposed culvert crossings are shown in Figure 11. The details of the proposed structures are shown
below. The evacuation routes are shown in Figure 12. To be considered trafficable, the roads were

designed to have a maximum flow depth of 250mm and a depth-velocity (dV)product of less than 0.4 m2/s.

During PMF events, access for emergency vehicles would be required. These vehicles are typically larger
than standard vehicles and so can handle greater flow depths across roads. Based on Project 10 of
Australian Rainfall and Runoff (AR&R): Appropriate Safety Criteria for Vehicles (2011), large 4WDs can
cross roads with maximum depths of 500mm, with a limiting dV product of 0.6 m2/s.      Large passenger cars
can cross roads with maximum depths of 400mm, with a limiting dV product of 0.45 m2/s.      For PMF events

trafficability was assumed if the depth was less than 400mm with a dV product of 0.45 m2/s.

Typical entry and exit losses of 0.5 and 1.0 were assumed unless specified otherwise.




Northbrook Corporation Pty Ltd                           Version 1                                    23 October 2012
Flood Study v1.doc                               Commercial in Confidence                                    Page 19

Used in these records

About this file

File size
93.6 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Part 8 of 37 Appendix 6 - Flood Study MCU12_0208.pdf · 93.6 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.