NOOSA COUNCIL IDAS Development Application Decision Notice                                                  5 of 8


23.   The Consulting Engineers for the project shall be currently Registered Professional Engineers of
      Queensland (RPEQ). The consulting engineers are responsible for arranging all inspections, with
      Council’s Construction Technical Officer or nominated staff.

24.   Prior to works commencing, Council is to be advised of the Engineer (RPEQ) supervising the project.
      (This person will be the contact for the project).

25.   Council standards shall apply to these works unless otherwise modified herein.

26.   The person acting on this permit shall ensure that its consultants and contractors take all reasonable care
      during the construction of the engineering works to ensure that Council property, road pavements or
      facilities (such as underground drainage, water supply, sewerage, footpaths, kerbing, landscaping, street
      furniture etc.) are protected against any damage or interference whatsoever.

      If any Council property or facilities should be damaged by the Applicant or any of its Consultants or
      Contractors through any cause whatsoever in the course of, directly or indirectly, carrying out the
      engineering works, the Applicant and/or its Contractors shall forthwith notify the Manager Land
      Development and shall forthwith rectify the damage to that property or facility at its cost and to the
      satisfaction of the Manager Land Development.

      All rectification works are to be completed prior to the commencement of the use or, alternatively, the
      Applicant may request the Council to carry out the rectification work at the Applicant’s cost, such cost
      being paid by the Applicant to the Council prior to the commencement of the use.

      In the case of any emergency the Council shall be entitled to rectify such damage at the cost of the
      Applicant, such cost being paid prior to the commencement of the use.

27.   The development of the site shall be carried out in such a manner as to prevent dust and/or sand
      nuisance to residents and/or tenants in the vicinity of the development.

28.   Construction work and other associated activities are permitted only during the hours of 7.00 am and 6.00
      pm Monday to Saturday. No work is permitted on Sundays or public holidays, except where extended
      hours are approved by the Manager-Land Development or his nominee.

29.   All signage, including that for safety during construction shall be in accordance with the Manual of Uniform
      Traffic Control Devices and Traffic Infrastructure (Roads) Act.

30.   Safe pedestrian access on Ventura Street shall be maintained at all times. Should footpath / road
      closures be necessary to carry out construction works, Council’s Construction Technical Officer (ph 0410
      512 505) must be notified prior to the proposed closure.

31.   Sediment and erosion control measures must be in place prior to works commencing. If such measures
      are not in place or are not satisfactory, “on the spot“ fines may be issued. Such fines can be issued if
      sediments from the site are found to enter or have the potential to enter Council’s stormwater system or
      natural waterways. Although the sediment and erosion control measures have been approved on drawing
      No. F06-012 2 of 21 Rev E dated 28 May 2007 by F3 Design and Architecture, Council’s Manager –
      Land Development may request further controls to be installed should approved measures be inefficient.

32.   The Design Engineer shall supervise the construction of the infiltration system and at the completion of
      the works submit to Council certification stating that the works have been undertaken in accordance with
      the approved design and that the infiltration system has the capacity to cater for the runoff from the site
      without adversely affecting adjoining properties or any Council services or structures.

33.   A 5% cost of works to become Council assets or $1,500 bond (whichever is the greater) will be imposed
      on construction works during the maintenance period, which is a minimum period of 12 months duration.
      Such bond must be lodged by, and shall only be accepted from the Developer for the works.

34.   The works to become Council assets will not be accepted "On Maintenance" until the landscaping is
      completed.

35.   Notwithstanding that Council has checked the plans with due care, where it is found during construction
      that variations from Council's standards exist, then Council standards shall apply




AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@5404378a\@[email protected]

Used in these records

About this file

File size
38 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

0015A7CC.001.pdf · 38 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.