                                                  Daniel Smith, 07 5449 5106
                                                  Email: [email protected]
                                                  Application Ref: 1989/112




2 August 2007


Raymond Gerrard Waters
5 Silkwood Drive
NOOSAVILLE QLD 4566




Dear Sir,

Re: Application for a Change to a Development Approval for light Industry –
    refrigeration works and motor repairs situated at 8 Commerce Court
    Noosaville, described as Lot 0 & 3 BUP 12535

I refer to your request to make a change to the above development approval. On 2
August 2007 Council decided to-

A.      Approve the application and delete condition 3.

B.      Change Condition 1 to read as follows:-

        1.    Development undertaken in accordance with this approval must generally
              comply with the approved plans of development. The approved plan is
              titled Site Plan, Elevations, Floor Plan and Section A-A and dated June
              2007 and as may be amended by these conditions.

C.      Add the following Conditions:-

Land Use
1.      A minimum of 6 carparking spaces shall be provided on the site and accessible at
        all times.

2.      To make up the loss of landscaping area from the frontage (due to the two car
        parking spaces), a minimum of 30m² of landscaping shall be provided elsewhere
        on the site. The area shall be landscaped in accordance with Planing Scheme
        Policy 3 – Landscaping Plants and Guidelines.

3.      All goods are to be displayed on site within the property boundaries and/or on the
        premises approved for the use.

4.      Security in the form of a cash bond or trading bank guarantee to the sum of
        $3000 must be submitted, to secure performance of all conditions of this
        approval, prior to the issue of a Development Permit for building works. The cash
        bond or trading bank guarantee will be returned on performance of the conditions
        of approval less any costs incurred by Council in respect of enforcing
        performance of this permit.


     Award Winner - Australian Clean Beach
       Challenge 2004 Litter Prevention
Full text of the other 3 pages

Page 2

5.      Existing trees on the site and within road reserves are to be retained, except
        where required to be removed due to building operations or the conduct of the
        approved use.
Land Development
Roof Water & Stormwater Drainage
6.      Roof runoff from the new roofed areas and any new surface runoff shall be
        directed to the existing stormwater disposal system for the site.
Sewer Mains
7.      To ensure Council’s sewer main is accessible for maintenance purposes and is
        protected from risk of damage no structures requiring a building permit (eg.
        buildings, roof overhangs, raised terraces, etc) shall be constructed within this
        ‘zone of influence’ or within 1.5m of the centreline of the sewer main, whichever
        is the greater. In this regard the existing sewer main that traverses the site at the
        rear and the ‘zone of influence’ (taken as the area within a 45-degree angle
        measured from the invert of the sewer main to the finished surface level) shall be
        accurately located, determined and marked on site by a licensed Surveyor.
Erosion and Sediment Control
8.      Any person acting on this permit shall prevent erosion and sediment export from
        leaving the site. Site control measures such as silt fencing, controlled gravel
        access to the site and controlled disposal of waste, will be necessary.
Contributions Towards Council Infrastructure
9.      Monetary contributions shall be paid to Noosa Council towards the cost of
        providing and/or upgrading various infrastructure at the rates applicable at the
        time of payment. An estimate only of the contribution amounts under the current
        Council policies and requirements is outlined in the table below:

         Contribution Required For:                                              Amount:
         PSP12 – Public Open Space Contributions (Park)                          $340
         PSP16 – Sewerage Headworks Contributions                                $664
         PSP17 – Water Supply Headworks Contributions                            $769
         PSP20 – Pathway Trunk Network Contributions                             $343
         TOTAL Contribution Amount =                                             $ 2,116
         Please note, that these amounts are all subject to variations in the Consumer Price Index,
         All Groups Brisbane from June 2007 until the date of payment.
        All contributions must be paid prior to the commencement of the use.
        Alternatively a trading bank guarantee shall be submitted to Council plus 20%.
        Should the contributions not be paid at the due time, Council shall call upon the
        trading bank guarantee in full.
        Processing of bonds for security where specific Council approval has been given
        for the bonding of contributions will incur an administration fee in accordance with
        Council’s Land Development Commercial & Regulatory Fees at the time of
        lodgement.
        In the event that the Development Permit for Material Change of Use of Premises
        lapses or is cancelled, the trading bank guarantee will be returned.




     Award Winner - Australian Clean Beach
       Challenge 2004 Litter Prevention

Page 3

General
10.     Any damage caused to any public utility during the course of construction shall be
        repaired to Council’s standards and at no cost to Council.

11.     Any alteration of any public utility or other facilities necessitated by the
        development of the land or associated construction works external to the site
        shall be at no cost to Council.

12.     The transportation of all materials to and from the site shall be undertaken in a
        manner such that no particle matter escapes onto a public road. All vehicles
        carrying materials either to or from the site shall be covered to prevent materials
        including dust being windblown from the vehicle.
Further Permits Required
13.     Prior to the commencement of development, the following Development Permits
        must be obtained:-

        13.1. Development Permit for Building Works; and

        13.2. Development Permit for Plumbing & Drainage works in accordance with the
              Plumbing & Drainage Act 2002 (as applicable).
THE FOLLOWING ADVICES ARE FOR INFORMATION PURPOSES ONLY AND DO
NOT FORM CONDITIONS OF APPROVAL
1.      The applicant is advised that development contributions and infrastructure
        charges applicable to this development approval have been based on the
        following Uses Class/ Uses and applicable quantities:-
                                  Approved Development
           Existing Use Class /    Approved Use Class /
                                                            Approved Quantity
                   Use                    Use
                                                              2
         Industrial Business –    Industrial Business –   98m of Additional Use
         Type 2 – Production      Type 2 – Production     Area

2.      The applicant is informed that approval of this development application will trigger
        an Infrastructure Charge in accordance with the Coastal Major Road Network
        Infrastructure Charges Plan for the estimated amount of $3,325 and is subject to
        variations in the Consumer Price Index, All Groups Brisbane from June 2007
        until the date of payment. An Infrastructure Charge Notice will be issued in
        accordance with Chapter 5 of the Integrated Planning Act 1997.

3.      The applicant is informed that payment via credit card transaction will not be an
        acceptable method of payment for development contributions conditioned in this
        permit or for infrastructure charge notices issued separately.

4.      The proposed building works will be located outside of the boundaries of Lot 3
        BUP 12535 and within the Common Property area. It is recommended that the
        applicant undertake amendment of BUP 12535 to include the proposed
        improvements within the boundaries of Lot 3.
D.      Advise the Applicant of Council’s decision.




     Award Winner - Australian Clean Beach
       Challenge 2004 Litter Prevention

Page 4

Please note that an Infrastructure Charge in accordance with the Coastal Major Road
Network Infrastructure Charges Plan has been triggered by the approval of this
development application. An Infrastructure Charge Notice is attached in compliance
with Chapter 5 of the Integrated Planning Act 1997.

Should you wish to obtain more information about Council’s decision, the reports and
staff recommendations regarding this application are available for viewing or purchase
at the Level 2 counter of Council offices. It would assist Council staff if you could bring
this letter with you.

Yours faithfully,



Daniel Smith
TECHNICAL OFFICER - PLANNING


Encl: Compiled Decision Notice
      Infrastructure Charge Notice




  Award Winner - Australian Clean Beach
    Challenge 2004 Litter Prevention

Used in these records

About this file

File size
15 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Council Decision - Changes - old apps - 005.1989.00000112.002 [As Published].pdf · 15 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.