Minor Change Request

of 3

Page text shows just the words. Original shows the document exactly as it was published.

Friday, 2 August 2024

Our Ref: 12211
Council Ref: MCU18/0009.04


        NOOSA COUNCIL
        PO BOX 141
        TEWANTIN QLD 4565

        ATTENTION: Development Assessment

Dear Sir/Madam


MINOR CHANGE APPLICATION

DEVELOPMENT PERMIT FOR MATERIAL CHANGE OF USE - MULTIPLE HOUSING TYPE 3
RETIREMENT & SPECIAL NEEDS

186 COOROY NOOSA RD & 4 CARRAMAR ST TEWANTIN

In relation to the abovementioned Development Approval, MCU18/0009.04, originally granted Noosa Council
on 15 November 2018 and changed on 21 October 2021, on behalf of Noosacare Inc, we hereby make a
change application pursuant to Section 78 of the Planning Act 2016.

Please find attached Planning Act Form 5 to facilitate Council’s assessment of the request.

PROPOSED CHANGE
The proposed change relates to conditions of approval 2.5 and 32 a.

2.5.    A minimum landscape setback of 6.0 metres must be provided to all boundaries, apart from existing
development, with existing vegetation retained and reinforced in the setbacks to maintain the amenity of
adjoining residents and a visual screen to Cooroy Noosa Road.

32 a. Provide landscaping plans that provide detailed sections and plan of a 6.0 metre landscaped buffer
adjacent to the northern boundary to buffer the adjacent residential uses from the development.

Both of these conditions require a 6m landscaped buffer adjacent to the northern boundary and which
conflict with approved MCU plans and the operational works approval.

An extract of approved plan 1810-103B is below, showing a 3m wide access and clearance zone adjacent to
the boundary and with 3m of landscaping.
Log in to download the original file

Minor Change Request.pdf · 559 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 2 pages

Page 2

There are several reasons that the 3m access and clearance zone is required, including:
• Not having planting over the major Council 600mm diam stormwater pipe that runs along the boundary;
• Providing access to maintain the bio basin and BAL zone to the east of the development;
• Providing required access for QFES from the new hardstand (12.0m x 6.0m) to service hydrants at the
  east end on the building;
• Providing access to the Council park area as required.

Subsequent operational works approval, OPW20/0007, reflects this outcome providing the hardstand which
was required by QFES over the 3m access along the north boundary and 3m of landscaping.’

This outcome has been constructed, with certificates of completion for both MCU18/0009 and OPW20/0007
issued.

Release of the development bond is however still being held by Council due to the conflict with these
conditions.

Accordingly, it is requested that condition 2.5 be amended to exclude the northern boundary and that
condition 32 a. be deleted.

MINOR CHANGE ASSESSMENT
The Planning Act 2016 defines a minor change for a development approval as a change to the approval that
would not result in a substantially different development.

The DA Rules state:

In determining whether the proposed change would result in substantially different development, the
assessment manager or referral agency must consider the individual circumstances of the development, in
the context of the change proposed.

    Description / Provisions                       Comment / Response
    A change may be considered to result in a substantially different development if the proposed
    change:

    •   Involves a new use; or                          No new use is proposed.
    •   Results in the application applying to a        No new land is included as part of the
        new parcel of land; or                          application.
    •   Dramatically changes the built form in          The proposed change does not dramatically
        terms of scale, bulk and appearance; or         change the built form in terms of scale, bulk
                                                        and appearance.
    •   Changes the ability of the proposed             No change is made to the proposed
        development to operate as intended (for         development to impede its operations.
        example, reducing the size of a retail
        complex may reduce the capacity of the
        complex to service the intended
        catchment); or
    •   Removes a component that is integral to         The proposed change does not involve
        the operation of the development; or            removal of a component that is integral to
                                                        the operational of the development.
    •   Significantly impacts on traffic flow and the   The proposed change will not significantly
        transport network, such as increasing           impact on traffic flow and the transport
        traffic to the site; or                         network, such as increasing traffic to the site.
    •   Introduces new impacts or increases the         The proposed change does not introduce
        severity of known impacts; or                   any new impacts, nor will it increase the
                                                        severity of known impacts.

Page 3

    •   Removes      an    incentive    or    offset   No    incentive   or   offset   components
        component that would have balanced the         incorporated.
        negative impact of the development; or
    •   Impacts on infrastructure provisions.          The proposed change does not impact upon
                                                       infrastructure provisions.

The original application did not trigger any referral agency assessment and no referral agency assessment is
now triggered with the changes.


CONSISTENCY ASSESSMENT
Pursuant to Clause 81 (4) & (5) the responsible entity must consider the statutory instrument, or
other document, as in effect when the development application for the development approval was
properly made.

However, the responsible entity may give the weight the responsible entity considers is appropriate,
in the circumstances, to—
    (a)     the statutory instrument or other document as in effect when the change application was
            made; or
    (b)     if the statutory instrument or other document is amended or replaced after the change
            application is made but before it is decided—the amended or replacement instrument or
            document; or
    (c)     another statutory instrument—
            (i)     that comes into effect after the change application is made but before it is
                    decided; and
            (ii)    that the responsible entity would have been required to consider if the instrument
                    had been in effect when the development application for the development
                    approval was properly made.

Comment: The original application was lodged and approved under the superseded Noosa Plan 2006. The
proposed condition changes remains consistent with the intended outcome of superseded Noosa Plan 2006.

There has been no change to the development intent for the site under the current Noosa Plan 2020.

CONCLUSION
The proposed change does not compromise the intent of the original approval.

Approval of the minor change is warranted.


Should you have any questions with respect to the above, please do not hesitate to contact me direct.

Yours faithfully
PROJECT URBAN




Scott Sobey
DIRECTOR
Email: [email protected]

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.