Minor Change Request
There are several reasons that the 3m access and clearance zone is required, including:
• Not having planting over the major Council 600mm diam stormwater pipe that runs along the boundary;
• Providing access to maintain the bio basin and BAL zone to the east of the development;
• Providing required access for QFES from the new hardstand (12.0m x 6.0m) to service hydrants at the
east end on the building;
• Providing access to the Council park area as required.
Subsequent operational works approval, OPW20/0007, reflects this outcome providing the hardstand which
was required by QFES over the 3m access along the north boundary and 3m of landscaping.’
This outcome has been constructed, with certificates of completion for both MCU18/0009 and OPW20/0007
issued.
Release of the development bond is however still being held by Council due to the conflict with these
conditions.
Accordingly, it is requested that condition 2.5 be amended to exclude the northern boundary and that
condition 32 a. be deleted.
MINOR CHANGE ASSESSMENT
The Planning Act 2016 defines a minor change for a development approval as a change to the approval that
would not result in a substantially different development.
The DA Rules state:
In determining whether the proposed change would result in substantially different development, the
assessment manager or referral agency must consider the individual circumstances of the development, in
the context of the change proposed.
Description / Provisions Comment / Response
A change may be considered to result in a substantially different development if the proposed
change:
• Involves a new use; or No new use is proposed.
• Results in the application applying to a No new land is included as part of the
new parcel of land; or application.
• Dramatically changes the built form in The proposed change does not dramatically
terms of scale, bulk and appearance; or change the built form in terms of scale, bulk
and appearance.
• Changes the ability of the proposed No change is made to the proposed
development to operate as intended (for development to impede its operations.
example, reducing the size of a retail
complex may reduce the capacity of the
complex to service the intended
catchment); or
• Removes a component that is integral to The proposed change does not involve
the operation of the development; or removal of a component that is integral to
the operational of the development.
• Significantly impacts on traffic flow and the The proposed change will not significantly
transport network, such as increasing impact on traffic flow and the transport
traffic to the site; or network, such as increasing traffic to the site.
• Introduces new impacts or increases the The proposed change does not introduce
severity of known impacts; or any new impacts, nor will it increase the
severity of known impacts.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.