Original source · versioned page text
Amended Planning Report
O5 Development does not S5.1 Buildings or other structures Not applicable
adversely impact on the Lake within the
Macdonald water supply. Lake Macdonald catchment (indicated
on Figure 14.7) are located above the
98.5m AHD level.
Services and Utilities No sewerage,
O6 The house is provided with S6.1 Where located in an urban stormwater or water
infrastructure, services and utilities zone, or a water or sewerage service infrastructure available.
appropriate to its setting. area, appropriate connection is
provided to reticulated sewerage,
water supply and stormwater drainage.
Electricity supply infrastructure Complies
O7 Uses and works maintain S7.1 Buildings and structures
an adequate safe distance from (including swimming pools, sheds,
electrical infrastructure including tennis courts or outbuildings) are not
substations, overhead constructed under
powerlines, power poles and overhead electricity transmission lines,
transformers. or within electricity easements.
Water Supply Infrastructure Complies
O8 Existing water supply S8.1 Buildings and structures are
infrastructure, including pipeline setback a minimum of 20m from a
corridor, is protected from water supply pipeline as shown on
incompatible development to ensure Overlay Map OM3.5.
the safety and reliability of water
supply network.
Steep Slopes and Landslide Hazard Area on Overlay Maps Not applicable –
hazard areas O9 Detached OM1.3–9.3, or on steep slopes the Outside of overlay
houses, Ancillary dwelling use does not– mapping
units, and associated uses are a) involve the removal of vegetation
sited or constructed to maintain other than grass from use areas;
the safety of people and property or
from the risk of landslide. b) involve excavating or filling of
more than 50m3 of material
(other than placement of
topsoil not exceeding 100mm
in depth relative to natural
ground level; or
c) involve cut or fill with a depth of
more than 2m relative to natural
ground level; or
d) redirect or impede water flows
in an existing watercourse or
stormwater drain; or
e) involve construction of an on-
site effluent disposal system;
OR
S9.2 A site specific geo-technical
report prepared by a registered
professional engineer either—
a) certifies that the site is not at
risk from landslide emanating
from the site or from other
land; or
b) identifies methods of
stabilising all buildings,
10 | P a g e
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.