Engineering_Integrated Water Management Plan
Plans and drawings
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawndue to site constraints; however, treatment has been sized such that the overall site
achieves the WQO’s. Table 6 outlines the catchment areas represented within the
MUSIC model. The stormwater quality catchments are provided in Figure 5.
Table 6: Catchment Areas
Catchment Area Roof Road Total
A1 0.72 0.15 0.56 0.72
A2 0.35 0.17 0.18 0.35
B 0.61 0.03 0.58 0.61
C 0.44 0.20 0.24 0.44
D 0.17 0.04 0.13 0.17
E 0.12 0.08 0.04 0.12
F 0.12 0.08 0.04 0.12
TOTAL 2.52 0.76 1.77 2.52
2.3.3 MUSIC Model Layout
As the management of urban stormwater needs to take a holistic approach, a
number of management measures need to be implemented in series to form a
treatment train. The correct utilisation of various devices within the treatment train
is imperative to target the desired pollutants, from the gross solids to the fine
colloidal partials.
Figure 4 shows the MUSIC model layout for the development.
Figure 4: Model Layout
7
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.