Minor Change Existing Approval - MCU22 0097 02 (As Published)
Lighting
10. Lighting of appropriate intensities is provided which satisfies the requirements of Australian
Standard AS1158: Public Lighting Code, unless otherwise specified in this Code.
11. Lighting is directed onto the site and away from neighbouring properties.
Performance Bond
12. Security in the form of a cash bond or trading bank guarantee to the sum of $15,000 must
be submitted to Council, to secure performance of all conditions of this approval, prior to the
issue of a Development Permit for Operational Works. The cash bond or trading bank
guarantee will be returned on performance of the conditions of approval less any costs
incurred by Council in respect of enforcing performance of this permit. Council reserves the
right to call upon the bond or guaranteed sum to effect compliance with conditions.
Street Identification
13. The street address of the development must be clearly visible and discernible from the
primary frontage of the site by the provision of a street number and, where appropriate, the
building name.
Water & Sewer Connections
14. An underground connection to reticulated water and sewerage must be provided to the
development site in accordance with the standards and requirements of Northern SEQ
Distributor–Retailer Authority (Unitywater).
15. A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater)
must be submitted to Council that certifies an underground connection to reticulated water
and sewerage has been provided to the development site.
Landscaping Works
16. The development site must be landscaped. A detailed Landscaping Plan is to be prepared
by a suitably qualified person and provided for approval to the Manager Development
Assessment prior to the commencement of Operational Works. The below items are to be
incorporated into the Landscaping Plan:
a. All species are to be consistent with Noosa Plan, Planning Scheme Policy PSP2 –
Landscaping for that specific area;
b. Provision of at least 1 x 45 litre pot size tree within the outdoor dining area to allow for
a large tree canopy to form the predominant shading of the outdoor dining area;
c. Artificial grass is not to be incorporated into the landscaping in the development and is
to be removed.
d. A minimum of 6 canopy trees (a minimum of 45 litres pot size), treated with porous
surface are to be provided within the car parking area.
e. Existing vegetation on the site is to be retained.
Site Specific Conditions
17. The surface of the existing access handle and internal carpark must be upgraded to ensure
the carpark remains functional throughout the lifespan of the development. The works must
be undertaken in accordance with an Operational Works approval, be generally in
accordance with RECOR’s Roads Layout Plan (20220213-001) dated 21 October 2022, and
must include in particular:
a. pavement patching; and
b. crack sealing.
18. The property owner(s) is(are) wholly responsible for the ongoing maintenance of the access
handle and internal carpark and must ensure the access handle and internal carpark
maintains in their ‘as-constructed’ conditions.
Page 3 of 9
Document Set ID: 25010384
Version: 3, Version Date: 28/07/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original