MCU16/0079 Appendix E - Traffic Impact Assessment
Tewantin Noosa RSL – Stage 4, 5 & 6
Traffic Impact Assessment
5.4 DESIGN TRAFFIC VOLUMES
Design traffic volumes have been derived by adding estimated development trips to background traffic
forecasts for both the ‘year of opening’ (assumed to be 2018) and the 10-year design horizon (2028). The
estimated future design volumes are included at Appendix H.
5.5 INTERSECTION ANALYSIS
The adopted layout for the Memorial Avenue/Doonella Street roundabout is illustrated on Figure 5.1. The
assessment results are summarised in Table 5.3. Detailed SIDRA outputs are provided at Appendix I.
Figure 5.1: SIDRA Layout – Intersection of Memorial Avenue/Doonella Street
Table 5.3: SIDRA Results – Intersection of Memorial Avenue/Doonella Street
Average Delay 95th %ile Queue Acceptable
Scenario Demand (vehs/hr) DOS (%)
(secs) (m) Performance
AM Road Network Peak
2016 Baseline 1,807 71 8 54 Yes
2018 BG 1,841 73 8 57 Yes
2028 BG 2,024 81 9 88 Yes
2018 BG + DEV 1,851 73 8 59 Yes
2028 BG + DEV 2,034 82 9 93 Yes
AM Road Network Peak
2016 Baseline 1,705 65 7 51 Yes
2018 BG 1,739 66 7 53 Yes
2028 BG 1,910 73 8 68 Yes
2018 BG + DEV 1,757 67 7 55 Yes
2028 BG + DEV 1,928 74 7 71 Yes
The results suggest that the intersection will operate within the acceptable performance thresholds for a
roundabout (i.e. (DOS < 85%) in all assessed scenarios. Therefore, no upgrades are warranted.
Project No: P2623 Version: 002 Page 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (MCU16_0079 Appendix E - Traffic Impact Assessment.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.