Original source · versioned page text
2019-12-11 SM Agenda - Item 1 - Attachment 7 - Final New Noosa Plan - Part 8-10 Schedule Appendix - Clean version
Plans and drawings: the text below has words only, no drawings.
Very large file (23.3 MB): may take a few minutes to open.
(iii) Stormwater infrastructure shall comply with the relevant IPWEA and TMR standard drawings.
(iv) Kerb entry catchpit without grates are the desired style of pit for cycling safety and to display Council’s
environmental messages in the lids.
(v) Stormwater drainage easements shall be dedicated in favour of Council, excluding inter allotment drainage,
over all drain lines in private property. The width of the easement shall be a minimum of 4.0 metres wide and
increased when the depth of the pipe warrants or for multiple pipes the easement shall be pipe width plus
600 millimetres each side.
(vi) Dissipaters, silt traps, oil arrestors and wetland basins shall be required as appropriate to reduce the impact
of development on the natural environment.
(vii) Catchpit to catchpit connections are permitted in the head of catchments to avoid manhole lids in the driving
lane.
(viii) Deflections in pipelines to be desirably less than 45 degrees.
(ix) Saltwater cover class pipes are to be used in all tidal areas.
(x) Pipe classes shall comply with Australian Standards in terms of cover.
(xi) All pipes are to be rubber ring jointed.
(xii) Bolt down lids are required when the clearance from design water level to pit lid is less than 300 millimetres.
(xiii) Headwalls and childproof grates are required on all pipe culvert inlets and outlets over 600 millimetres.
Velocity dissipaters and rock gabions are required on all pipe outlets to reduce erosion.
(j) Downstream Drainage
(i) The developer’s consultant is required to investigate the effect that the development may have on capacity of
the downstream drainage. If the downstream system or any property downstream will be adversely affected,
the consultant is to analyse the required mitigation works.
(ii) If the existing drainage system will be undersized according to current standards as a result of the
development, the developer shall be responsible for augmenting or replacing the drainage system. The
drainage system must be capable of handling the designated design frequency up to and including the 1 in
100 year Average Recurrence Interval (ARI) storm event including the overland flow situation
(k) Roof downpipe drainage outlets
(i) For each residential allotment, two approved kerb and channel adaptors are to be installed in the kerb 1.0
metre away from the side boundaries.
(ii) For commercial development unless a direct connection to the underground system can be achieved, a
special conduit capable of providing the required capacity shall be fabricated from stainless steel so that it
grades to the invert of the kerb and channel and yet is shallow enough to accommodate the footpath surface
treatment without becoming a trip hazard.
(l) Earthworks
(i) Where a development site requires cut/fill operations to enable the site to properly drain or keep the site
above flood levels, this work is to be completed prior to the construction of roads and other services.
(ii) Filling works must be undertaken so that there is an acceptable development area above the 1 in 100 year
ARI flood level or where modelling is not available, the highest recorded flood level plus 300 millimetres.
(iii) Excavation or filling works require an Operational Works development permit. The following information is
required as part of the application:
(A) A drainage plan for the site indicating proposed drainage patterns, extent and depth of filling works and
finished site levels;
(B) A detailed engineering study of the implication of the filling works in relation to the drainage pattern of
adjoining allotments and road reserves and an assessment of the increase, if any, of the flood heights
upstream of the subject site.
(C) The study should include sufficient survey information external to the site to determine existing
drainage flows, in addition to recommended drainage works on the perimeter of the site, to prevent
possible drainage problems on adjoining land;
(D) An Erosion and Sediment Control Plan prepared by an appropriately qualified consultant in accordance
with the Institution of Engineers Australia (Queensland Division) Soil Erosion and Sediment Control
Guidelines for Queensland Construction Sites.
**FINAL DRAFT Post Consultation 2019**
Page 7 of 9
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.