CSR West Ridge Quarry
Ecological Assessment Report
Column 1 Column 2 Assessment of Impacts and Recommendations
Specific outcomes Probable solutions (if code
assessable)
Conservation (Koala) Conservation Plan 2006 and Management Program 2006 – 2016):
the proposed works take advantage of disturbed areas of the site which provide low habitat values;
the nominated disturbance areas do not include undisturbed areas of the site which offer suitable resources
for Koalas;
the proposed disturbance areas involve clearance to areas adjoining the existing quarry pit and will not result
in fragmentation or isolation of vegetated corridors and linkages on and off-site;
no permanent structures are proposed, and threats to Koalas such as a long term increase in traffic,
residential population, dogs etc will not result;
no new roads are required to be created;
the increase in traffic along Lake Macdonald Drive relating to transport of materials from West Ridge to the
other quarries will be temporary in nature (works to take approximately 24 months), and will occur only over
a short distance (i.e. 1.2km); and
the overall proposed works will enable rehabilitation and vegetation enhancement using native species to
other disturbed quarries nearby.
It would be appropriate for SCRC to condition the following requirements as part of an MCU approval. These
requirements would be incorporated into a CEMP if necessary.
Sequential and directional felling must be employed during vegetation clearance to lesson potential harm to
Koalas and other wildlife.
A spotter-catcher must be employed for the clearance works.
Dogs must not be permitted on site as part of the construction works.
Probable Solution S6.1 and 7.1 therefore applies and the proposed works would achieve Specific Outcomes 06
and 07.
Open space networks & S8.1 Vegetation is enhanced The proposed removal of 2.66ha of non-remnant vegetation is positioned in a manner which avoids:
wildlife corridors through revegetation and remnant and High-value regrowth vegetation, watercourses and ridgelines;
O8 Open space networks vegetation maintenance in areas
indicated in Schedule 5 on Map 4 a Conservation Estate (and its buffer) associated with Yurol State Forest, located on an adjoining property to
and wildlife corridors are
maintained and - Open Space Networks. Lot 3 and at least 800m from the quarry (refer Appendix E); and
embellished to provide for a recognised Open Space corridor as shown on the excerpt below from The Noosa Plan Map 4.
viable connectivity between AND
vegetation by protecting
and replanting vegetation The proposed disturbance areas adjoin the existing quarry and take advantage of cleared areas, thus avoiding
S8.2 Existing wildlife corridors are
CSR Building Products Ltd Version 3 4 December 2012
Ecological Assessment Report V3.docx Commercial in Confidence Page 23
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.