46. The development must be undertaken and operated in a manner that causes no detrimental
effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
lighting, air-borne hazards, atmospheric pollutants (including dust or odours) nuisance or any
other emissions in accordance with the nuisance provisions of the Environmental Protection
Act 1994.
47. All mechanical equipment on site must be in accordance with the Environmental Noise
Assessment, prepared by Acoustics RB Pty Ltd dated October 2018.
Noise Nuisance
48. Noise emission from mechanical equipment must comply with the following requirements:
a. Air-conditioning, refrigeration, fans including mechanical exhaust fans/ventilation, plant
rooms and refuse compactors:
• 7am to 10pm: Maximum background + 5dB(A)
• 10pm to 7am: Maximum background + 3dB(A)
49. Submission of written certification from a suitably qualified person confirming that the noise
levels from all mechanical equipment comply with the noise requirements of this Decision
Notice when measured at either the residential boundary or outside the most exposed part
of an affected building, whichever is the closest to the equipment.
Easements
50. Unless otherwise agreed in writing by the relevant service provider, any public or third party
infrastructure located on the subject site must be placed within an easement registered
against the title of the property.
51. Where required, all easements must be designed in accordance with the planning scheme
and granted at no cost to the Grantee. Where the Grantee is Council or a service authority,
the easement documentation must be in accordance with the Grantee’s standard easement
terms. Draft easement documentation must be submitted to Council for endorsement.
52. All works must be kept clear of any existing or proposed easements on the subject land,
unless agreed otherwise in writing by the Grantee.
Stormwater
53. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge. The works must be undertaken in accordance with an Operational Works
approval.
54. A stormwater quality treatment system must be provided for the development. The works
must be undertaken in accordance with an Operational Works approval and the Water by
Design Bioretention Technical Design Guidelines, or more current Water by Design
document, and must include in particular detailed design of Stormwater quality treatment
devices of a size generally in accordance with those shown in Section 6 and Appendix C of
the of the Stormwater Management Plan for Eden Private Hospital Expansion 46-50 Maple
Street, Cooroy by ADG Engineers (Aust) Pty Ltd dated 03 September 2019.
55. All stormwater quality treatment devices must be maintained in accordance with the Water
by Design (2009) Maintaining Vegetated Stormwater Assets (Version 1). Records of all
maintenance activities undertaken must be kept and made available to Council upon request.
56. In accordance The Noosa Plan, permanent educational signage must be erected to educate
the public about the function of the bioretention device(s). The dimensions, standard,
presentation and location of the educational signage must be in accordance with an
Operational Works approval.
Page 8 of 16
Document Set ID: 24873125
Version: 4, Version Date: 18/06/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Existing Approval - MCU19 0049 01 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 211 KB (small file)
- File type
No other editions are linked here.