               46.    The development must be undertaken and operated in a manner that causes no detrimental
                      effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
                      lighting, air-borne hazards, atmospheric pollutants (including dust or odours) nuisance or any
                      other emissions in accordance with the nuisance provisions of the Environmental Protection
                      Act 1994.
               47.    All mechanical equipment on site must be in accordance with the Environmental Noise
                      Assessment, prepared by Acoustics RB Pty Ltd dated October 2018.
                      Noise Nuisance
               48.    Noise emission from mechanical equipment must comply with the following requirements:
                      a.      Air-conditioning, refrigeration, fans including mechanical exhaust fans/ventilation, plant
                              rooms and refuse compactors:
                               •       7am to 10pm: Maximum background + 5dB(A)
                               •       10pm to 7am: Maximum background + 3dB(A)
               49.    Submission of written certification from a suitably qualified person confirming that the noise
                      levels from all mechanical equipment comply with the noise requirements of this Decision
                      Notice when measured at either the residential boundary or outside the most exposed part
                      of an affected building, whichever is the closest to the equipment.
                      Easements
               50.    Unless otherwise agreed in writing by the relevant service provider, any public or third party
                      infrastructure located on the subject site must be placed within an easement registered
                      against the title of the property.
               51.    Where required, all easements must be designed in accordance with the planning scheme
                      and granted at no cost to the Grantee. Where the Grantee is Council or a service authority,
                      the easement documentation must be in accordance with the Grantee’s standard easement
                      terms. Draft easement documentation must be submitted to Council for endorsement.
               52.    All works must be kept clear of any existing or proposed easements on the subject land,
                      unless agreed otherwise in writing by the Grantee.
                      Stormwater
               53.    The site must be provided with a stormwater drainage system connecting to a lawful point of
                      discharge. The works must be undertaken in accordance with an Operational Works
                      approval.
               54.    A stormwater quality treatment system must be provided for the development. The works
                      must be undertaken in accordance with an Operational Works approval and the Water by
                      Design Bioretention Technical Design Guidelines, or more current Water by Design
                      document, and must include in particular detailed design of Stormwater quality treatment
                      devices of a size generally in accordance with those shown in Section 6 and Appendix C of
                      the of the Stormwater Management Plan for Eden Private Hospital Expansion 46-50 Maple
                      Street, Cooroy by ADG Engineers (Aust) Pty Ltd dated 03 September 2019.
               55.    All stormwater quality treatment devices must be maintained in accordance with the Water
                      by Design (2009) Maintaining Vegetated Stormwater Assets (Version 1). Records of all
                      maintenance activities undertaken must be kept and made available to Council upon request.
               56.    In accordance The Noosa Plan, permanent educational signage must be erected to educate
                      the public about the function of the bioretention device(s). The dimensions, standard,
                      presentation and location of the educational signage must be in accordance with an
                      Operational Works approval.




                                                                                                         Page 8 of 16
Document Set ID: 24873125
Version: 4, Version Date: 18/06/2026

Used in these records

About this file

File size
211 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval - MCU19 0049 01 (As Published).pdf · 211 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.