Site Access, Car Park and Driveways
17. The existing driveway must be removed and a sealed access driveway must be provided
from Swan Street (approximately in the same location as the existing) to all parking and
manoeuvring areas of the development. The works must be undertaken in accordance with
an Operational Works approval and must include in particular:
a. a driveway crossover in accordance with Council’s standard drawing RS-051and
respective addendum; and
b. reinstatement of damaged kerb and footpath contiguous to the driveway.
18. All car parking areas, motorcycle parking areas and access driveways must be maintained
exclusively for vehicle parking and manoeuvring and kept in a tidy and safe condition at all
times.
19. The car park area is to be sealed and parking spaces must be clearly delineated and marked.
20. Directional signage must be provided to direct vehicles to the car parking spaces provided
on site.
Stormwater Drainage
21. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge. The works must be undertaken generally in accordance with Black & More’s
Stormwater Management Plan (SWMP) for the subject site, dated 20/03/2020, File ref: 7465.
22. The site specific SWMP must be approved as part of the subsequent Building Approval.
Electricity and Telecommunication Services
23. Unless otherwise stipulated by telecommunications legislation at the time of construction, the
development must be provided with all necessary conduits, pits and pipes to accommodate
the future connection of optic fibre technology telecommunications.
24. Certification must be submitted to Council from all relevant service providers which certifies
that the development has met the requirements of this Decision Notice and all applicable
legislation at the time of construction.
Easements
25. Unless otherwise agreed in writing by the relevant service provider, any public or third party
infrastructure located on the subject site must be placed within an easement registered
against the title of the property.
26. All easements must be designed in accordance with the planning scheme and granted at no
cost to the Grantee. Where the Grantee is Council or a service authority, the easement
documentation must be in accordance with the Grantee’s standard easement terms. Draft
easement documentation must be submitted to Council for endorsement.
27. All works must be kept clear of any existing or proposed easements on the subject land,
unless agreed otherwise in writing by the Grantee.
Earthworks and Retaining Walls
28. All fill and associated batters must be contained entirely within the subject site unless written
permission from the respective landowner(s) is provided to Council. All earthworks must be
undertaken in accordance with the provisions of Australian Standard AS3798: Guidelines on
Earthworks for Commercial and Residential Developments.
29. Where the development involves excavation or filling over, or adjacent to, drainage, water
supply or sewerage infrastructure, all access chamber surface levels must be adjusted to
provide a freeboard of 100mm above the finished ground surface level.
Page 5 of 8
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.