Information Response MCU12/0208

of 64

Text shows just the words. Original shows the document exactly as it was published.

Section 8.3 of the Stormwater Management Plan amended addresses this item.

The MUSIC analysis was re-run to determine the increase in bio-retention treatment size that would be
required to compensate for the loss of the rainwater tanks and still meet the stormwater quality
objectives. As the proposed development has targeted a higher level of treatment than typically required,
the increase required was not as significant as that necessary for similar developments. It was found that if
the bio- retention filter media area in the basins and swales was increased by 25 percent then the WQOs
could be met. The exception was for areas F and G, where a 50 percent increase in the bio-retention
gardens was required. It would also be necessary to drain the roof areas to the road, rather than directly to
underground drainage. The resultant load removal for the combined site was 83% for TSS, 60% for TP and
48% for TN.

 While the water quality objectives can be met if the bio-retention areas are increased, it is still
recommended that rainwater tanks be adopted on site. The proposed development aims to promote the
use of ecologically sensitive design and the use of rainwater tanks plays an important role in this regard. As
this will be a Body Corporate development there will be more control available on the development
conditions for each lot. The use of rainwater tanks will significantly reduce the water demand of the site
(by up to 53%), reduce stormwater flows being discharged off-site and allow the remaining treatment
devices to be better target utilised treating ground and road runoff, rather than relatively clean roof runoff.



       It is proposed to combine a detention function within several bio-retention devices. Whilst it is
        claimed that more information about these devices will be provided at the detailed design phase,
        the main concerns with this approach is the viability of combining detention with bio-retention
        where vegetation could be drowned by prolonged periods of rainfall.

Response:

The use of bio-retention within detention basins is standard practice. The extended detention zone will
not be different to that of bio-retention basins, and the area will be planted with suitable plants that can
tolerate prolonged periods of ponding. Only the bio-retention zone within the basin will experience
prolonged periods of ponding. The remainder of the basin will be located at a higher level and function
similar to a traditional detention basin.

The outlets of the basins will be suitably sized using a program such as XP-SWMM to show that sufficient
attenuation of peak flows can be provided for all storm events. The bio-retention extended detention
zone will be assumed to be full, as antecedent rainfall may fill this storage volume prior to the peak storm
event occurring.

 The Healthy Waterways MUSIC Modelling Guidelines (2010) state that when bio-retention is incorporated
into the base of a retarding basin, that the volume above the top of the extended detention depth should
not be included in the model for water quality assessment. Flood storage was not included in the
stormwater quality modelling. BCC practice notes for bio-retention basins also state that they can be
incorporated into retarding basins.

Off-line detention basins have only been proposed for catchments E3, F7 and F8. These are the
catchments that drain directly to Eenie Creek and its tributaries. The other catchments that drain to
Keyser Creek or Eenie Creek will have “on-line” attenuation of peak flows for all storm events provided by
the proposed culvert crossings. The results of this assessment are summarised in Section 8.2 and
Appendix G of the amended Flood Study (see Attachment 13). Refer to comparison points Q3, Q5 and EC4
in Table G3 to compare the existing and developed case peak flows. The flood modelling that was
conducted for the developed case assumed that all of the site had developed case inflows (i.e. increased
due to the greater impervious areas), except for catchments E3, F7 and F8, as these flows will be reduced
to existing case levels by the proposed detention basins. The details of these basins will be determined at
the detailed design stage. Although Precinct H drains to a point in Keyser Creek downstream of the
proposed culvert crossings, the over-attenuation provided by these crossings is sufficient to ensure that

                                                 59

Used in these records

About this file

File size
1.6 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Information Response MCU12_0208.pdf · 1.6 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.