Information Response MCU12/0208

of 64

Text shows just the words. Original shows the document exactly as it was published.

         following:

         a) demonstrate that the design, intensity, configuration and establishment of development, is
         compatible with the physical constraints of the site and receiving environment
         b) includes a contoured site plan showing natural features and location of the proposed control
         structures, including sediment basins, ESC treatment train and an overview strategy for the site
         outlining the sequence of development, and temporary and permanent management mechanisms
         with an emphasis on site stabilisation to prevent erosion in the first instance, until commissioning
         of permanent water sensitive urban design features and addresses the following:

                I.       Sediment basins:
                         -         are nominated for treatment of stormwater runoff from all areas which are
                         proposed for clearing, earthworks, stockpiling or otherwise exposed soils.
                         -         are appropriately sized based on a Type D basin (preliminary
                         calculations are provided and based on SCRC Manual or IECA)
                         -         are located:
                                   o         outside of waterways and flood prone areas (at least the 1 in 2
                                             year ARI level)
                                   o         where the basin will not be inundated by groundwater
                                   o         other than in areas of retained vegetation
                                   o         on topography where they are capable of being constructed (eg
                                             not on steep slopes)
         II.    In areas of the site where a sediment basin is not feasible, compensatory erosion and
                                   sediment controls, which are capable of achieving the stormwater release
                                   limit, are nominated.
         III.    The proposed extent of vegetation clearing is limited to that necessary to undertake the
                                   works.
         IV.    Clearly identifies the proposed extent of soil disturbance and provides indicative staging of
                                   the proposed construction activities such that the area of soil exposed at any
                                   one time will be minimised.
         V.                        Proposed clean upslope stormwater diversions around or through the site
                                   are indicated. Alternatively, if it is not feasible to divert clean water around
                                   or through the site, the Plan indicates how the additional volume of
                                   stormwater runoff will be managed.
         VI.                       Proposed concentrated flow paths for conveying contaminated stormwater
                                   are indicated

Response:

Further to Council’s information request, the aim of the Erosion and Sediment Control Plan (ESCP) (Appendix E
of the amended Engineering Report [Attachment 8]) is to provide performance criteria, strategies and
procedures to assist in minimising the impact of construction activities on the physical and social environment.

An ESCP has been prepared with reference to the ‘Best Practice Erosion and Sediment Control (2008)’ guidelines
published by the International Erosion Control Association (IECA) Australasia, and current local best practice
engineering and environmental management.

The objective is to control soil erosion on the site and prevent sediment discharge to downstream local water
courses or road stormwater drainage systems during storm events for the construction phase of the project.

Please refer to section 2.6 and preliminary ESCP in Appendix E of the amended Engineering Report (see
Attachment8) for further information regarding ESCP’s.

Please note that a final ESCP can only be completed upon knowing the lot layout and hence earthworks which
can only be completed as part of future applications.
In this instance it is anticipated Council would impose an appropriately worded condition regarding the
requirement for a final ESCP as part of any approval package.
                                                        62

Used in these records

About this file

File size
1.6 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Information Response MCU12_0208.pdf · 1.6 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗