8.2. The detailed topography of the rear of the site showing both sides of the
existing gully.
8.3. Survey of the frontage of the site in order to ascertain the differential levels
between the kerb line of Eumundi Noosa Road and the topography of site
and the existing batter within the property.
8.4. The actual locations of the existing public services within and outside the
property including the existing storwater inlets and culvert in Gateway
Drive, and any existing stormwater service discharging from the adjoining
properties eg stormwater pipe discharging from the rear into the existing
gully.
8.5. The location of the existing sewer main on the site.
9. Revised plans of the development to dedicate:-
9.1. A road reserve along Eumundi Noosa Road to achieve a minimum 8m wide
footpath verge between the existing kerb line and boundary line of the site.
This is to be adjusted to accommodate the new kerb line for the modified
roundabout.
9.2. Where required, a road reserve along Gateway Drive to achieve a minimum
6m wide footpath verges between the existing kerb line and boundary line
of the site.
9.3. Additional to the road reserve widening an appropriate truncation on the
corner of Gateway Drive and Eumundi Noosa Road is required.
10. Plans and cross sections showing the depth of the proposed earthworks (filling
and cuts) on the site including batters and any retaining walls.
11. Cross section/s to show the design levels, batters, accesses and services in
relation to Eumundi Noosa Road and Gateway Drive.
12. Detailed cross section/s of any proposed filling and retaining works along the
gully near the northern boundary of the proposed development.
13. Provide stormwater drainage layout plan/s for the site, and demonstrate that the
proposed development will not caused additional stormwater ponding or have
adverse impact on the drainage conditions on the adjoining properties i.e. how is
discharge from the upstream properties dealt with.
14. Provide Figure 4 from the Water Quantity Section of the Cardno Surface Water
Management Plan.
15. A1 (to scale) plan showing the carparking layout including dimensions of the
spaces and aisles.
16. Details of the loading bay/receiving area showing trucks’ maneuvering and
specifying the types and sizes of delivery trucks using the site and demonstrating
compliance with Australian Standards.
Award Winner - Australian Clean Beach
Challenge 2004 Litter Prevention
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
0015E253.001.pdfRelated documentPublic source context ↗
Request for Further Information - 010.2007.00000256.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 19 KB (small file)
- File type
No other editions are linked here.