                                                                                       2008/66



15.   Copies of the approved plans (incorporating any modifications required due to conditions
      contained herein) duly signed by the consultant Registered Professional Engineer of
      Queensland (RPEQ) shall be provided to Council’s Construction Technical Officer at the “pre
      start” meeting.
16.   The filling of the site and construction of the proposed building and fencing shall not create
      additional ponding of stormwater on any adjoining property.
17.   Roof and surface runoff connection to Council’s kerb and channel shall be as shown on Spice
      Consulting’s Drawing No. 686-01, A. Kerb adaptors shall be used in the kerb.
18.   A 1.5 metre wide concrete footpath shall be constructed across the full frontage of the
      development. The alignment shall be determined on site with Council’s Construction Technical
      Officer. The footpath shall have a slip resistant surface. The expansion joints in any
      bikeway/footpath shall be “saw cut”, not trowel jointed.
19.   The vehicular access driveway serving the development shall be constructed with a maximum
      width of 4.5m.
20.   The driveway and any associated fencing or vegetation shall comply with the minimum sight
      line requirements as defined in AS2890.1, sec 3.2.4.
21.   Council’s Construction Technical Officer (ph 0410 512 505) shall be given seven (7) days’
      notice of intention to commence works to arrange a “pre start” meeting prior to the
      commencement of works.
22.   The principal contractor must have all the appropriate insurance and public liability
      documentation to carry out the works. The principal contractor is also responsible to ensure
      that any sub contractors also have the appropriate insurance and public liability
      documentation.
23.   Prior to the “pre start” meeting, the principal contractor must be provided with a copy
      of Council’s signed approved drawings and conditions by the applicant.
24.   The Consulting Engineers for the project shall be currently Registered Professional Engineers
      of Queensland (RPEQ).          The consulting engineers are responsible for arranging all
      inspections with Council’s Construction Technical Officer or nominated staff. Council’s
      Construction Technical Officer shall provide an inspection form for signing off by the Engineer
      at appropriate stages of construction, during on-site meetings. Construction Technical Officer
      will also sign the form at each stage when requested conditions have been satisfied.
25.   Prior to works commencing, Council is to be advised of the Engineer (RPEQ) supervising the
      project. (This person will be the contact for the project).
26.   Council standards shall apply to these works unless otherwise modified herein.
27.   The person acting on this permit shall ensure that its consultants and contractors take all
      reasonable care during the construction of the engineering works to ensure that Council
      property, road pavements or facilities (such as underground drainage, water supply,
      sewerage, footpaths, kerbing, landscaping, street furniture, etc.) are protected against any
      damage or interference whatsoever.
      If any Council property or facilities should be damaged by the Applicant or any of its
      Consultants or Contractors through any cause whatsoever in the course of, directly or
      indirectly, carrying out the engineering works, the Applicant and/or its Contractors shall
      forthwith notify the Manager Land Development and shall forthwith rectify the damage to that
      property or facility at its cost and to the satisfaction of the Manager Land Development.
      All rectification works are to be completed prior to the commencement of the use or,
      alternatively, the Applicant may request Council to carry out the rectification work at the
      Applicant’s cost, such cost being paid by the Applicant to Council prior to the commencement
      of the use.

                                                                                         3 of 8

Used in these records

About this file

File size
62 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

SUPERSEDED - Negotiated Decision Notice - 010.2008.00000066.001 [As Published].pdf · 62 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.