In the case of any emergency, Council shall be entitled to rectify such damage at the cost of
the Applicant, such cost being paid prior to the commencement of the use.
28. The development of the site shall be carried out in such a manner as to prevent dust and/or
sand nuisance to residents and/or tenants in the vicinity of the development.
29. Construction work and other associated activities are permitted only during the hours of 7.00
am and 6.00 pm Monday to Saturday. No work is permitted on Sundays or public holidays,
except where extended hours are approved by the Manager, Land Development, or his
nominee.
30. All signage, including that for safety during construction, shall be in accordance with the
Manual of Uniform Traffic Control Devices and Transport Infrastructure (Roads) Act.
31. Safe pedestrian access on Edward Street in the vicinity of the development shall be
maintained at all times. If footpath / road closures are necessary to carry out construction
works, Council’s Construction Technical Officer (ph 0410 512 505) must be notified prior to the
proposed closure.
32. Sediment and erosion control measures must be in place prior to works commencing. If such
measures are not in place or are not satisfactory, “on the spot “ fines may be issued. Such
fines can be issued if sediments from the site are found to enter or have the potential to enter
Council’s stormwater system or natural waterways. Although the sediment and erosion control
measures have been approved on JTC’s drawing no. 207196 Sheet 018 A and 207196 Sheet
019 A, Council’s Manager, Land Development, may request further controls to be installed
should approved measures be inefficient.
33. These works are also to be in compliance with the relevant conditions of Development
2007/567.
34. Notwithstanding that Council has checked the plans with due care, where it is found during
construction that variations from Council's standards exist, then Council standards shall apply.
Approved Plans
The approved plans for this development approval are listed in the following table:
Plan / Document No. Rev. Plan / Document Name Date
6017 02 D Stormwater Disposal Plan & Site Plan – 06-05-08
Design to Detail
207196 019 A Drop Inlet Protection Detail, Sediment 11/01/08
Fence Detail, Sediment Fence & Spoon
Drain Detail & Section at Entry – JTC
Consulting Engineers
207196 018 A Erosion & Sediment Control – JTC 11/01/08
Consulting Engineers
686-01 A Site & Floor Plans All Services – Spice 20/12/07
Consulting
5 REFERRAL AGENCY CONDITIONS
The referral agencies applicable to this application are:
Referral Trigger Referral Status Referral Agency Referral Address
Nil
4 of 8
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED - Negotiated Decision Notice - 010.2008.00000066.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 62 KB (small file)
- File type
No other editions are linked here.