     –    Sediment contained by the sediment control devices such as sandbags, sediment fences and
          containment bunds must be frequently removed and placed in a controlled area.
     –    Implement an inspection schedule for any spill or leaks of any potential polluting areas or
          activities.

6.4.4 Erosion and Sediment Control Management Goals
•    Licenses, approvals, permits and inspection reports are in order.
•    Sediment or pollution control devices such as sandbags, sediment fences and containment bunds
     are in place, maintained and effective.
•    Spill/ pollution control equipment is readily accessible at designated locations.
•    No accumulated sediment is contained by the sediment control devices such as hay bales, sediment
     fences and containment bunds.
•    No sediment exceeding a depth of 300mm in the pollution control devices (e.g. silt trap).

6.4.5 Erosion and Sediment Control Implementation Program
•    Licenses, permits or approvals for each environmentally relevant activity must be obtained prior to
     the commencement of the particular activity.
•    Appropriate control measures such as sediment fences, temporary construction entry/ exit sediment
     traps, pollution containment devices (e.g. sandbags), stormwater diversion and administrative
     controls must be installed and established prior to commencement of the earthworks and
     construction activities.
•    Pollution control devices such as spill control equipment must be inspected on a regular basis (at
     least weekly).
•    Other sediment and pollution control equipment such as containment bunds, hay bales and
     sediment fences must be inspected on a regular basis (at least daily).
•    Inspection for any leaks, spills or potential contaminating activity must be performed on a regular
     basis (at least daily).
•    Remove accumulated sediment or other contaminants from sediment/ pollution control devices on
     a regular basis.
•    All erosion and sediment control measures must be inspected within 24 hours of expected rain and
     within 18 hours of a rainfall event.

6.4.6 Responsible Person or Organisation

The contractor shall be responsible for the implementation and maintenance of the Erosion and
Sediment Control Measures.




                                                                                                                                         14
Inspired engineering

22 May 2025
https://mpncnetau.sharepoint.com/sites/Administration/Shared Documents/10000-10999/10200-10299/10256/Report/22-05-25 SWMP_Issue A.docx

Log in to download the original (Stormwater Management Plan.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.