2019-10-28 Special Meeting Agenda - Item 1 - Attachment 4 - RAL18-0023 - Master Plan Stage 2

of 32

Page text shows just the words. Original shows the document exactly as it was published.

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
CHOOSING FUTURES: Shire Business Centre Master Plan - Stage 2                                                           18

           Walter Hay Drive and Eenie Creek Road are the principal frontage roads to the site. They also serve high order
           functions in the transport network. No development is to have direct access to those roads. In addition it is
           desirable to screen development from those roads so as to ensure development has an internal focus. (See
           Strategic Plan 19.3.1.8) The design workshop of 5 September 2002 discussed the extent of this landscape and
           concluded a complete screening of all development was not desirable, as it is important that the site be
           identifiable because of its prominent role. Nevertheless a minimum width of 5 metres of existing vegetation is to
           be retained near the entry roads and this width may expand to 10 metres in between those access points.
           To maintain the vegetation in a natural state in the long term, Council requires that part of OS3 containing
           vegetation to be protected is to be contained in a park reserve or otherwise secured for open space purposes in
           the long term (eg. environmental covenant).

           Sub-precincts B1-3, E1-7 and RES are required to provide a minimum area of open space. The intent of those
           open space areas is to provide a vegetated setting for development but also to give consideration to potential
           habitat and fauna corridor functions linking to Open Space Precincts and the open space areas within each of the
           adjacent development sub-precincts. It is acknowledged that substantial parts of the open space within the sub-
           precincts will be re-planted for landscaping effect.

           The location of Walter Hay Drive creates a small precinct in the northeastern sector of the site. This land is
           constrained by -

                      Shape

                      Access

                      Proximity to National Park (buffering on site will be required)

                      Separation from other development precincts

           This area has been determined to have limited development potential and would most usefully serve as an
           addition to the National Park. It can alternatively be considered for a small-scale recreation use or mixed use
           development, upon Council being satisfied the above constraints are satisfactorily accommodated and the values
           of the National Park are not impacted to any measurable degree. A recreation use could be beneficial to the
           functions of the balance of the Shire Business Centre. In reflection of this the land has been designated
           Recreation/Mixed Use, but with buffer areas adjacent to the national park included in Sub-Precinct OS1.

           This master plan also carries forward the intent of MP1 concerning the retention of existing defined drainage
           paths. Additional survey work has demonstrated the open space area shown as Precincts OS5 and OS6 on MP1
           do not contain a well defined drainage corridor. MP2 proposes a different approach in this area and seeks the
           retention of a lesser extent of open space land that is to perform a role of a character element - separating
           differing land use types. Landscaping treatment of the drainage corridors and other parts are to be designed with
           water quality objectives in mind. Landscape treatments in the more urbanised parts of the site may include water
           elements.

           The three entry roads into the site are to be distinguished by landscape treatment. This treatment as with all
           landscaped areas shall be consistent with the adopted landscaping policies of Council. Landscaping should retain
           existing vegetation where practicable.




\\stratplan\psreview\Planning Scheme\Planning Studies\Shire Business Centre\Masterplan-FinalApr03.doc
Log in to download the original file

2019-10-28 Special Meeting Agenda - Item 1 - Attachment 4 - RAL18-0023 - Master Plan Stage 2(PDF, 745KB).pdf · 763 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.