PEREGIAN BEACH ACTIVE STREET - STAGE 1 PROGRESS UPDATE AND NEXT STEPS (Deferred from the General Committee Meeting dated 16 March 2026) · Report

of 16

Page text shows just the words. Original shows the document exactly as it was published.

ORDINARY MEETING                                                                  19 MARCH 2026


Together, these upgrades will deliver a safer, greener and more attractive active transport
experience for users.

Grant Funding Opportunity

The project's high priority in the State funded corridor study, along with the community concerns
raised regarding speeding and pedestrian safety along and around Lorikeet Drive, made it an
excellent candidate for external funding. The project is 100% Grant funded through the South East
Queensland Liveability Fund and the Active Transport Fund.

The SEQ Liveability fund is Supporting Local Government projects that create liveable, creative,
sustainable and healthy communities. Projects funded will be of a regional or sub-regional scale
that leave a legacy in the community. The funding through the SEQ Liveability grant covers design
and construction works.

The Active Transport Fund (ATF), provides funding for the design and construction of new or
existing bicycle and walking pathways to encourage the use of active transport.
The focus areas for the program are:
   •   road safety
   •   reducing transport emissions
   •   active and liveable communities
The ATF grant funding for this project is specific to construction only.


3. Program

The project program is governed by Council's Annual Capital Works Programs and two separate
external funding agreements as outlined below.

SEQ Liveability
The last possible dates for milestones as listed in the executed SEQ Liveability funding agreement,
are:

Milestone                         Last Possible Date (as per         Status
                                  Program Guidelines)
Completion of                     30 Jun 2027                        At risk
Construction
Final Reporting                   Dec 2027                           Achievable

Active Transport Fund
The last possible dates for milestones as listed in the executed ATF funding agreement, is:
Milestone                         Last Possible Date (as per         Status
                                  Program Guidelines)
Commencement of Construction 25 Mar 2026                             At risk
Completion of                     25 Mar 2028                        Achievable
Construction
Acceptance of                     25 Jun 2028                        Achievable
Post-Completion Report
Log in to download the original file

Report.pdf · 289 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.