Information Request RAL23 0021
Issue – Preliminary Construction Management Plan
Advisory Note 12 of Attachment A of the P&E Court Appeal dated 28 September 2023 states:
“Preparation of a Preliminary Construction Management Plan
12. A preliminary Construction Management Plan must be submitted with the Operational
Works application and must address the following:
a. Traffic management during all aspects of the construction phase including:
i. A Traffic Management Control Plan in accordance with the Manual of
Uniform Traffic Control Devices (MUTCD) detailing all temporary signage
and traffic control measures prior to construction
ii. Maintenance of safe vehicle and pedestrian access for the areas affected by
the works during and after daily construction has ceased
iii. Proposed fencing to the site during the construction phase of the
development
iv. Approval of the Traffic Management Control Plan by the Department of
Transport and Main Roads (DTMR) for any works on State controlled roads
v. Provision for worker car parking
b. Maintenance and protection of water quality and existing drainage lines through
the construction site, through the implementation of appropriate erosion and
sediment control measures
c. Works programme identifying key components of the works and their respective
durations
d. Establishment of a communication protocol with the general public, adjoining
owners, emergency services and local businesses to advise of agreed
construction times, impacts on traffic, services and other relevant issues.
e. Include a post out to the local residents and businesses advising of the proposed
development, the expected time frames and the site contact details.
f. Include signage in prominent locations on the boundaries of the site advising of
the proposed development, the expected time frames and the site contact details.
g. Identification of complaint management procedures including:
i. Contact details for the on-site manager
ii. Dispute resolution procedures
h. Details on the location of external fill/dump sites/sources, the haulage route, type
of vehicle to be utilised during filling operations and frequency of usage. NB any
damage to the existing road system as a result of haulage operations shall be fully
repaired at the applicant’s expense
i. It is acknowledged that the preliminary Construction Management Plan will be a
draft document requiring finalisation upon appointment of the Principal Contractor
employed to construct the works and a final document will be required to be
submitted at the Pre-Start Meeting for the project.”
Information Required
2. Provide a preliminary Construction Management Plan in accordance with Advisory Note
12 and in accordance with the Noosa Plan 2020.
Issue –Table Drain Conveyance
It is unclear how stormwater flows from the existing table drain along Church Street will be
conveyed southwards along the development frontage as shown on the proposed External
Roadworks Layout Plan (Drawing 184-001-800 Rev A, Dated 25.10.23) at CH 70.00m.
Page 2 of 4