SERVICES & ORGANISATION COMMITTEE MEETING 12 NOVEMBER 2024
6.1 CAPITAL PROGRAM 2024/25 DELIVERY STATUS
Author Infrastructure Planning Design and Delivery Manager, Craig Eldridge
Infrastructure Planning Design & Delivery | Infrastructure Services
Department
Index ECM / Budget / 2024 - 2025 Capital Works Program
ECM / Project Management / Planning and Infrastructure Projects
Attachments None
EXECUTIVE SUMMARY
• This report provides a status update for the Capital Works Program as at 30 September
2024, and excludes disaster recovery projects.
• The approved capital budget provision for the 2024/25 financial year is $53.8m, inclusive of
carry forwards of $22.4m. Projects in direct control of the Infrastructure Team have a budget
of $41.2m. Other capital projects, such as Information Communication and Technology
(ICT) and fleet, have a budget of $12.6m.
• Actual expenditure achieved to date is $6m (11% of budget) with $9.3m remaining in
commitments.
• There are currently 127 projects on the Capital Works Program in varying stages of delivery.
• Projects continue to be managed within overall budget and time limitations to the extent
possible. Contractor resources and material availability remain a constraint and continue to
drive up project pricing.
• Council has a current forecast of grant funding revenue of $14.2m with Council’s
contribution to these projects being $8.4m.
• Infrastructure Planning Design and Delivery (IPDD) is making substantial progress in its
restructuring process, with the major restructure aiming to create additional leadership
capacity, enhance delivery efficiencies and maximize team output.
• The IPDD Branch is continuing to face resourcing constraints and challenges.
• Enhancements in systems, tools and processes are continuously being rolled out across
IPDD, particularly in the area of project controls, reporting and forecasting.
• Innovative strategies for project delivery are currently being explored, such as optimising
the size of procurement packages and utilising external resources to supplement resource
constraints.
RECOMMENDATION
That Council note the report by the Infrastructure Planning Design and Delivery Manager to the
Services & Organisation Committee Meeting, 12 November 2024, providing an update on the
delivery of the 2024/25 Capital Works Program as at 30 September 2024.
REPORT
This report is to inform Council of the overall status of the Capital Works Program, excluding disaster
recovery projects as at the end of September 2024, marking the end of the first quarter of the 2024/25
financial year.
Page 66 of 79
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.