The Developer shall provide at its cost a sewerage reticulation system including
rising mains and pump station for the whole of the development to connect to a
point nominated by the Shire Engineer on Council's system. The nominated site in
this case will be at or close to the inlet structure of Noosa Council sewerage
treatment plant. The size shall be such as to meet expected demand flows for the
proposed development. The mains extension from this nominated point to the site
including all pump stations necessary shall be deemed to be external works and will
be at the full cost of the Developer. The main shall be constructed in conjunction
with Stage 1 of the development.

All works external to the site shall be included wherever possible within road
reserves. Should it be necessary for the mains to cross private lands an easement
will be required to be obtained and dedicated in Council's favour. The costs of
obtaining and dedicating the easement/s shall be borne by the Developer.

Headworks contributions for sewerage reticulation shall be paid in accordance with
Council's policy current at the time of issue of the building approval plus C.P.I.
where relevant, and shall become due within fourteen (14) days of such approval:
Such timing shall only be varied should development of the pertinent stage bring
forward works required to meet the expected demands of that specific stage.
Deductions in accordance with Council's headworks policy shall apply to those
pertinent developments which form part of the overall development complex.

All augmentation works required to Council's existing sewerage system by the
development shall be done by the Developer at its full cost. Augmentation works
shall be deemed necessary as a result of the development if works in excess of
Council's existing and projected demands (excluding the development) are required
as a result of the development.

All pump stations not within a public road reserve are to be contained within a
separate parcel of land to be transferred to Council in fee simple. An easement of a
minimum width of 4.0 m. is to be granted in favour of Council over all rising mains
which are not contained within road reserves.

Standby power shall be provided for the main pump stations on the site and any
pump station not having standby power shall be constructed as a lift station.

An all weather road shall be provided to service the proposed rising main and pump
stations both internal and external to the site.

The Developer shall provide a water supply connection to all pump stations and
associated facilities.

The operation and maintenance of all sewerage mains and pump stations provided in
association with the development shall, after acceptance of works “on maintenance",
remain with Council. Rates in accordance with Council's policy shall be levied on
the developments contained within the subject site.

Log in to download the original (Original Conditions December 1994.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.