Original source · versioned page text
MCU15/0034 - Advice Agency Response
Aurecon Group for NBN Co 2 L 12 on RP883248
ADVICE AGENCY'S RESPONSE
Sections 291 and 292
of the Sustainable Planning Act 2009
RESPONSE TO DEVELOPMENT APPLICATION
Powerlink Queensland, acting as an advice agency under the Sustainable Planning Act
2009 provides its response to the above application.
The advice agency's response is that:
[g] this application should be approved subject to the following conditions:
1. Compliance with the terms and conditions of easement dealing no. 601108825.
2. Any variation to the proposed layout as shown on the enclosed copy of the
submitted Drawing "Overall Site Plan" 4GYM-51-32-SCHR-C2 Rev 02 dated
23/04/2015 shall require resubmission.
3. This advice is valid for a period of 2 years from the date of this response, should the
development not be initiated within that period, the applicant should resubmit the
application for re-consideration.
4. This response does not constitute an approval to commence any works within
the transmission line corridor. While Powerlink Queensland has no 'in principle'
objection to the proposed MCU, any works on easement would require detailed final
design submissions, assessments and approvals (or otherwise) by Powerlink
Queensland. We would prefer this information to be submitted in electronic format
3D DXF of final design RL's AHD and MGA GDA94 in applicable zone.
In addition, the following requirements should be considered in your Operational Works
application for proposed on-easement work.
5. Compliance with the generic requirements in respect to proposed works in the
vicinity of Powerlink Queensland infrastructure as detailed in the enclosed Annexure
"A".
6. Compliance with the Electrical Safety Act 2002 ("the Act") including any Code of
Practice under the Act and the Electrical Safety Regulation 2013 ("the Regulation")
including any safety exclusion zones defined in the Regulation.
In respect to this application the exclusion zone for untrained persons and for
operating plant operated by untrained persons is six (6) metres from the 275,000-
volt wires and exposed electrical parts.
Should any doubt exist in maintaining the prescribed clearance to the conductors
and electrical infrastructure, then the applicant is obliged under the Act to seek
advice from Powerlink Queensland.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.