Original source · versioned page text
Attachment 3 -C_ Planning Scheme Assessment
Appendix C
Assessment Against the Planning Scheme – Earthworks Code
Performance Outcomes Acceptable Outcomes Compliance
Assessable development
PO1
Development near a stormwater No acceptable outcome provided
drain, overland flow path or Can comply – engineering plans have been
associated structure does not— prepared by Arcos to demonstrate the ability to
1. adversely affect the comply and are included in Appendix B. The
function of the service; development approval for this development
2. place an additional load application can be conditioned accordingly if
on the service; and considered necessary by Council.
3. unduly increase future
maintenance costs.
PO2
Maintenance access is provided AO2.1 Can comply – engineering plans have been
to all stormwater drains, overland For trunk infrastructure, a registered easement in prepared by Arcos to demonstrate the ability to
flow paths and associated favour of Council is created over all underground comply and are included in Appendix B. The
structures. infrastructure located in private property. development approval for this development
application can be conditioned accordingly if
AO2.2 considered necessary by Council.
The width of the easement required is in
accordance with Council’s Planning Scheme
Policy PSP6 Engineering Design Standards –
Roads, drainage and earthworks.
AO2.3
The easement is centred over the centreline of
the infrastructure.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.