ORDINARY MEETING AGENDA 21 SEPTEMBER 2017
7. A condition report including photographs of the frontage of the site must be completed
and submitted to council at the prestart meeting / prior to any works commencing.
8. Certificates demonstrating currency of public liability insurance and works insurance
covering the works must be submitted to Council at the prestart meeting.
9. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6245.
The pre-start meeting must include the relevant parties for the following aspects of the
works:
a. Civil engineering works;
b. Other relevant parties
10. A Construction Management Plan must be submitted to Council at least 5 working days
prior to the pre-start meeting and must specifically address the following:
a. Traffic Management during all aspects of the construct phase including:
i. A Traffic Management Control Plan in accordance with Manual of Uniform
Traffic Control Devices (MUTCD) detailing all temporary signage and traffic
control measures prior to construction
ii. Maintenance of safe pedestrian access across the frontage of the site both
during daily construction and after daily construction has ceased
iii. Proposed fencing to the site during the construction phase of the
development
iv. Adequate parking arrangements for construction workers
v. No queuing of trucks is permitted on residential streets, especially prior to
7.00am. Further parked trucks must have engines turned off
b. Works programme identifying key components of the works and their respective
durations
c. Establishment of a communication protocol with the general public, adjoining
owners, emergency services and local businesses to advise of agreed
construction times, impacts on traffic and services and other relevant issues
d. identification of complaint management procedures including:
i. contact details for the on-site manager
ii. dispute resolution procedures
During Construction
11. The developer must meet any costs to repair damage to any Council asset during
construction, where damage is a result of the development works. Damage to assets
must be repaired immediately where it creates a hazard to the community. In
circumstances where the damage does not create a hazard to the community, it must
be repaired immediately on completion of the works associated with the development.
12. All works must be supervised by a Registered Professional Engineer of Queensland
(RPEQ) who is independent of the Developer and Principal Contractor, and they must
certify that all works conform to the permit.
13. Safe pedestrian access on all streets in the vicinity of the development must be
maintained at all times. Should footpath/road closures be necessary to carry out
construction works, Council must be notified prior to the proposed closure and all
requirements complied with.
Page 19 of 22