ORDINARY MEETING AGENDA 15 OCTOBER 2020
Pedestrian and Bicycle Facilities
16. Pedestrian and bicycle facilities must be provided for the development. The works must be
undertaken in accordance with an Operational Works approval and must include in particular:
a. Internal pedestrian footpaths in accordance with the approved plans
b. a total of 11 bicycle parking spaces
c. end of trip facilities involving 9 lockers, 1 male and female shower and change rooms.
Public Safety
17. During operating hours, all parking areas, pedestrian areas and entrances/exits to all
stairwells, travelators, lifts, foyers and public toilets must be well lit with vandal resistant
lighting and with intensities to satisfy the requirements of Australian Standard AS1158 “Public
Lighting Code”. Lighting must be designed to reduce the contrast between shadows and
well lit areas.
Community Management Statement
18. Any proposed Community Management Statement required for the development pursuant to
the Body Corporate and Community Management Act 1997 must be submitted to Council for
endorsement at the same time as submission of the Building Format Plan (or similar) to
Council for compliance assessment.
19. All clauses and by-laws of the proposed Community Management Statement must accord
with the requirements of this Decision Notice.
ENGINEERING
External Works - Maple Street
20. Maple Street must be upgraded for the length of its frontage to the subject site. The works
must be undertaken in accordance with an Operational Works approval and must include in
particular:
a. Concrete pedestrian pathway to 2.0m wide. This new concrete pathway must be
designed in accordance with standard drawing RS-065 and must be tapered and
extended beyond the frontage of the site to match the width and levels of adjoining
existing sections of pathway.
b. Any reinstatement of verge area to match the new pathway, including the provision of
topsoil and turf where the existing verge is grassed.
c. Any required reinstatement of existing kerb and channel.
d. Landscaping as required by the landscape conditions of this permit.
This condition is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Site Access and Driveways
21. Sealed access driveways must be provided from Maple Street to all parking and manoeuvring
areas of the development generally in accordance with the approved plans. The works must
be undertaken in accordance with an Operational Works approval and must include in
particular:
a. Driveway crossovers in accordance with IPWEAQ standard drawing RS-051.
b. Modification, adjustment or relocation to any existing services affected by the driveway
construction.
c. Suitable safety measures, including warning signage, to improve driver awareness of
pedestrians and enhance pedestrian safety.
Page 22 of 27