PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA 6 NOVEMBER 2018
e. The Addendum Letter by Cardno (document number WE17064) dated 23 March
2018.
f. The Technical Memorandum by Cardno (ref WE17064_Carramar_TM01) dated 13
July 2018.
g. A minimum Finished Floor Level (FFL) of the Aged Care Facility and any associated
facilities at 8.80m AHD.
h. A minimum Finished Floor Level (FFL) of the Independent Living Units of 8.80m
AHD.
i. All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines are to be adhered to.
Prior to the issue of a Development Permit for Material Change of Use these reports must
be amended to reflect the amended development proposal as required by Condition 2.
Applicant’s Request
The applicant submits the following revised reports to address the condition:
a) Amended plans are submitted that located all buildings outside the Q100 flood line as
required by condition 2.1
b) A revised Integrated Water Management Plan prepared by Callaghan and Toth will be
submitted to address the amended development proposal.
c) Refer b) above
d) A technical memorandum reviewing the revised proposal with reference to flooding has
been prepared by Cardno.
e) Refer d) above.
f) Refer d) above.
g) Proposal able to comply with minimum floor heights.
h) Proposal able to comply with minimum floor heights.
The amended plans and further addendums to the specialist reports addresses the condition
above.
Proposed amended condition: Update condition to reflect additional documentation provided.
Assessment
The applicant has provided amended reports which have been reviewed by Council officers and
Council’s consultant Traffic Engineer and Water Quality/Quantity Engineer. The reports satisfy
the condition and therefore, it is recommended that the condition be updated to reflect the
amended reports as follows:
26. All works must be constructed and work procedures undertaken in accordance with:
a. The approved plans, the approved amended plans and the conditions detailed in this
Decision Notice.
b. The document ‘Proposed Cartwright Village Extension – Carramar, Noosa Care
Integrated Water Management Plan Version 2 by Callaghan & Toth dated September
2018.
c. The document ‘Noosa Care Inc Cartwright Village Extension Carramar, Cooroy
Noosa Road, Tewantin Preliminary Design of Stormwater Detention Volume’ by BSM
dated 21 December 2017.
d. The document ‘Flood Study Noosa Care – Carramar’ by Cardno dated 24 July 2017.
Page 36 of 84
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.