132003.220729.6 Request to Change Existing Approval 14 Park Rd Noosa

of 38

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

12/APR/2011/TUE 12:25                                             FAX No,                                        P. 005

                                                                                                  20031220729




            Town Water Supply
            25.   The site shall be connected to Council's existing town water supply in Allambi Rise and be
                  constructed In accordance with Council's standards and requirements at no cost to Council.
            26.   Each water connection to the water reticulation system shall extend to the property boundary
                  and be metered.
            Geotechnical Issues/Construction
            27.   All construction works on site shall accord with the Geotechnical Reports prepared by Golder
                  Associates dated July 2003 and Morrison Geotechnic dated 23 November 2006 and
                  subsequent reports specific to the amended design (including the pool), subject to
                  amendments to address condition No. 43, with cut and fill for retaining walls not to exceed a
                  maximum depth of 1.5 metres.
                  The applicant's geotechnical engineer Is required to be an site for the whole of the time during
                  any excavation and house foundations including the construction of the retaining walls and the
                  footing for the falsework. Such work shall only be carried out during y weather conditions.
                  The geotechnical engineer shall also inspect the site periodically throughout the construction
                  of the dwelling and certify the stability of the structure upon its completion, Should any risk of
                  sand movement occur - all work shall be suspended until steps (approved by the Geotechnical
                  engineer) have been taken to ensure that no further slippage will result.
            28.   The disposal of sand, soil or any materials created by the construction of the dwellings shall
                  be removed In accordance with the Construction Management Plan. Details of the method of
                  this disposal of materials are to be submitted to Council at the Building Application stage. Not
                  more than one vehicle at a particular time will be parked in Park Road for the removal of, or
                  the delivery of, materials associated with the site and no such vehicle shall remain overnight.
                  No materials are permitted to be stored within the road reserve.
            29.   A program of works is to be submitted with any application for any Development Permit for
                  Operational Works detailing the construction schedule and proposed environmental protection
                  measures, Including a vegetation management plan, which addresses stabilisation of
                  disturbed areas.
                  Where the program is changed for any reason whatsoever, a copy of the revised program
                  shall be submitted to Council's Works Inspector within seven (7) days.
            30.   A Traffic Management Plan for the Construction of the Dwelling addressing the access to the
                  site, the locating of equipment, carparking arrangements for workers on the site and any
                  potential conflicts with local traffic shall be submitted to Council for approval prior to works
                  commencing on site.
            31.   Prior to the Issue of Building Permit the builder shall submit written acknowledgment that
                  building works shall proceed in accordance with the 9 tonne load limit applicable to Park Road,
                  unless varied by Council.
            32.   At the completion of construction the consulting geotechnical engineer will certify that all works
                  were carried out in accordance with their recommendations and that the structures and the site
                  are stable.
            33.   A Condition Survey is to be carried out on adjoining buildings, structures and services prior to
                  any construction works taking place on site. If distress already exists, a photographic survey
                  shall be undertaken, the distress measured and a plan to monitor changes to distress shall be
                  implemented. A copy of this report is to be submitted to Council within 5 business days of
                  survey and prior to construction work proceeding.
            34.   The use of vibratory equipment of any kind is not permitted to be used, including vibrating
                  rollers, the use of vibrating installation techniques for sheet piling and other construction
                  vibrations caused by excavating, earthmoving or demolition machinery or other similar
                  construction techniques.

                                                                                                  Page 4 of 10

Used in these records

About this file

File size
3.2 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

132003.220729.6 Request to Change Existing Approval 14 Park Rd Noosa.pdf · 3.2 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.