12/APR/2011/TUE 12:25                                              FAX No,                                   P. 006

                                                                                                2003/220729



            Erosion and Sediment Control
            35.   Any person acting on this permit shall prevent erosion and sediment export from leaving the
                  site. Site control measures such as silt fencing, controlled gravel access to the site and
                  controlled disposal of waste, will be necessary-
                  In this regard plans detailing the methods of controlling erosion and sediment are required to
                  be submitted to the Council for approval prior to obtaining a Development Permit for
                  Operational Works.
            Vegetation Protection
            36.   Vehicular pavements within the drip zone of any of the existing trees on site to be retained
                  shall be designed as a pervious pavement (such as grass paving cells or similar), as this will
                  allow water that falls on this surface to penetrate to the trees root system. The pavement shall
                  be constructed so as not to damage the tree or their root system and in this regard temporary
                  fencing shall be provided around the trees during construction to help protect them.
                  Plans shall be submitted to the Council for approval that clearly show the type and extent of
                  the pervious pavement and the temporary fencing prior to obtaining a Development Permit for
                  Operational Works.
            Roadworks Contributions
            37.   A roadworks contribution of $2,524 towards the Coastal Major Road Network in accordance
                  with Planning Scheme Policy PSP42, shall be paid to the Council prior to obtaining a
                  Development Permit for Operational Works. This amount will be subject to variations in the
                  Price Index, All Groups Brisbane from March 2004 until the date of payment.
            Pathway Contributions
            38.   A pathway contribution of $246 towards external major pathways, in accordance with Planning
                  Scheme Policy PSP41 Coastal Major Pathway Contributions, shall be paid to the Council prior
                  to obtaining a Development Permit for Operational Works. This amount will be subject to
                  variations in the Price Index, All Groups Brisbane from March 2004 until the date of payment.
            General
            39.   Any damage caused to any public utility during the course of construction shall be repaired to
                  Council's standards and at no cost to Council.
            40.   Any alteration of any public utility or other facilities necessitated by the development of the
                  land or associated construction works external to the site shall be at no cost to Council.
            41.   The transportation of all materials to and from the site shall be undertaken in a mariner such
    I             that no particle matter escapes onto a public road. All vehicles carrying materials either to or
                  from the site shall be covered to prevent materials including dust being windblown from the
                  vehicle.
            Building
            42.   A verification survey of the building is to be carried out by a Licensed Surveyor and a
                  certificate lodged with Council at completion of the work confirming compliance with the
                  maximum building height of 9 metres above natural surface.
            43.   All building works shall be in accordance with the Geotechnical reports prepared by Golder
                  Associates dated July 2003 and Morrison Geotchnio dated 23 November 2006 subject to the
                  following conditions:-
                  43.1      An amended Geotechnical Report addressing the design amendments associated
                            with this approval shall be submitted to Council for its information prior to the
                            application for Operational Works;
                  43.2      There is to be no uncontrolled discharge of water onto the slope;


                                                                                                 Page5of10

Used in these records

About this file

File size
3.2 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

132003.220729.6 Request to Change Existing Approval 14 Park Rd Noosa.pdf · 3.2 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.