Skip to the record
Mmm.. taste the original NoosaWatch™

Council archive · source document

132003.220729.6 Request to Change Existing Approval 14 Park Rd Noosa

of 38

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

12/APR/2011/TUE 12:26                                             FAX No,                                         P, 007

                                                                                                   2003/220729




                  43.3      Stripping of vegetation for construction purposes should be minimised. If vegetation
                            is destroyed it should be reinstated immediately after construction is completed;
                  43.4      Additional load due to fill, construction equipment or stockpiled materials should not
                            be located on the dune slope;
                  43.5      The use of vibratory equipment of any kind is not permitted to be used, including
                            vibrating rollers, the use of vibrating installation techniques for sheet piling and other
                            construction vibrations caused by excavating, earthmoving or demolition machinery
                            or other similar construction techniques;
                  43.6      The construction management plan is to be adhered to;
                  43.7      Copies of all inspection reports by engineers are to be submitted to Council within 5
                            business days of the inspection taking place;
                  43.8      The applicant's Geotechnical engineer will be required to be on site for the whole of
                            the time during any excavation. The construction of the whole of the foundations
                            and retaining walls is to be supervised and directed on site by a consulting
                            Geotechnical engineer. No work of any such kind relating to the foundations shall
                            be carried out if he is not on the site and supervising and directing this work. Such
                            works shall only be carried out during dry weather conditions and if there is a risk of
                            sand movement occurring, all work shall be suspended until such steps, approved
                            by the applicant's Geotechnical engineer and the Council's Building Surveyor, have
                            been taken to ensure that no further slippage will result.
                  43.9      Survey marks should be established on the structure to monitor the construction and
                            surrounds for movement. Monitoring for any potential movement shall be carried out
                            at regular intervals of a maximum length time of three (3) months for at least the first
                            year from the use commencing. The monitoring results shall be assessed by a
                            geotechnical engineer and may be scaled down or stoped depending on the results
                            and subject to the geotechnical engineer recommendations.
            Additional Condition 29/03/07
            44.   The sewer connection shall be undertaken in accordance with an approved Arborist's report
                  and the following requirements:
                  44.1      The route for the service trench shall be a minimum of 1.5 metres clear of all trees
                            and shrubs, unless otherwise agreed to by the Manager, Land Use.
                  44.2     An arborist shall be on site all times supervising the works being undertaken.
                  44.3      Prior to commencing any works, the route for the service trench shall be pegged and
                            inspected by Manager, Land Use.
                  44.4      Prior to excavation existing mulch/leaf cover material over proposed trench shall be
                            raked back and stockpiled for covering of trench area after completion.
                  44.5     Works shall be,undertaken in a progressive manner and route reinstated as works
                           progress.
                  44.6      Uphill anchor roots of trees shall not be disturbed.
                  44.7     All works shall be carried out by hand excavation. other then the sewer trench under
                           existing road pavement.
                  44.8     All excavated material shall be placed on a 'tarpaulin' or the like laid immediately
                           adjacent to the proposed trench.
                  44.9     Excavated material shall be used as bedding and backfilling of trench.
                  44.10    Where works disturb the understorey vegetation, rehabilitation works shall be
                           undertaken to the reasonable satisfaction of Manager, Land Use.


                                                                                                   Page 0 of 10

Used in these records

About this file

File size
3.2 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

132003.220729.6 Request to Change Existing Approval 14 Park Rd Noosa.pdf · 3.2 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.