b. Submit to Council (with each inspection request) a Rehabilitation Status Report (written
and photographic), mapping:
i. The condition of the regeneration area.
ii. Detailing works undertaken in the previous year.
iii. The percentage cover of indigenous recruitment.
iv. Measuring the works against the conditioned Performance Criteria.
*(Refer to Advisory Notes)
19. Rehabilitation works must meet the following Performance Criteria for:
a. Year One – 12 months after installation:
i. Planted trees have achieved an average height of 1m.
ii. Planted shrubs have achieved an average height of 0.4m.
b. Year Two - 24 months after the installation:
i. Planted trees have achieved an average height of 2m.
ii. Planted shrubs have achieved an average height of 1m.
c. Year Three - Final acceptance installation:
i. Planted trees have achieved an average height of 3m.
ii. Planted shrubs have achieved an average height of 1.2m.
iii. Canopy and / or vegetative strata must not be devoid for any area greater than
1.0m2 within any 10m2 sample.
iv. Plant density shading out and/or self-mulching.
d. The duration of the establishment period:
i. Adherence to maintenance regime for rehabilitation and revegetation areas.
ii. No evidence of woody weeds reshooting from stumps, poisoned trees or the
regrowth of cut stumps.
iii. No evidence of over-weeding or impact on non-target species.
iv. Signs of indigenous recruitment in rehabilitation areas.
v. Weed infestations less than 5% of the rehabilitation areas.
vi. Any failed plants within the previous 12 month period have been replaced.
vii. Healthy and vigorous growth allowed to grow to full form.
viii. Mulch layer sufficient to suppress weeds.
Bushfire Management
20. A qualified person* must be engaged for the duration of the works to ensure:
a. Works are carried out in accordance with the approved Bushfire Hazard Assessment
(Ver. 1) prepared by Equilibrium Ecology dated 31 August 2022.
b. The asset protection zones and the fire management access paths are established for
both the new and existing building envelopes.
Engineering
21. The developer must meet any costs to repair damage to any Council asset during
construction, where damage is a result of the development works. Damage to assets must
be repaired immediately where it creates a hazard to the community. In circumstances where
the damage does not create a hazard to the community, it must be repaired immediately on
completion of the works associated with the development.
Page 5 of 13
Document Set ID: 23009397
Version: 3, Version Date: 10/05/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - OPW24 0025.pdfRelated documentApplication case desk ↗
About this file
- File size
- 182 KB (small file)
- File type
No other editions are linked here.