Original PDF page 5, section 1. The text section number identifies this passage in the reader.

INTRODUCTION
This report outlines a Stormwater Management Plan (SMP) for a Material Change of Use (MCU)
application, 51 Elanda Street, Lot 403RP48112 (the subject site).

The report has been prepared for Archend and proposes relevant Stormwater Quality Improvement
Devices (SQID) and stormwater Best Management Practices (BMP) to ensure the proposed
development meets the stormwater quantity and quality requirements during the operational phase.

This report is for development assessment purposes only and does not provide detailed engineering
designs. A detailed design will be required to finalise the stormwater concepts as presented in this
report. Detailed design documentation should be prepared with the rest of the requirements
associated with civil operational works.

Objective
The main objective of this report is to present a workable SMP that can be incorporated into the
development proposal to ensure that the development does not have an unacceptable impact or
cause a nuisance that could lead to actionable damage to receiving environments and downstream
properties during the development's operational phase. Table 1 below summarises the objectives.

Stormwater management for the proposed development has been designed in accordance with the
following documents:

    •   Noosa Shire Council Development Codes, 2020;
    •   State Planning Policy (SPP), 2017;
    •   Environmental Protection (Water) Policy, 2009;
    •   Queensland Urban Drainage Manual (QUDM) Fourth Edition, 2016;
    •   Water By Design MUSIC Modelling Guidelines, Version 3.0, 2018;
    •   Australian Rainfall and Runoff Guideline (ARR);
    •   International Erosion Control Association – Best Practise Erosion and Sediment Control,
        2008;
                                        TABLE 1: OBJECTIVES

 Objectives                  Description
 Stormwater Quantity -       Maintain a Lawful Point of Discharge (LPD) for all site catchments in
 Operational Phase           accordance with QUDM (2016).
 Stormwater Quantity -       Development should not result in water being diverted onto land that
 Operational Phase           is not ordinarily subject to overland flow.
 Stormwater Quantity -       Ensure the development does not create adverse flood impacts on
 Operational Phase           upstream or adjacent properties.
 Stormwater Quality -        Stormwater discharged from the site is treated to achieve maximum
 Operational Phase           removal of nutrients, gross pollutants and suspended solids.




24083 – 51 Elanda Street, Sunshine Beach - SMP                                                Page 5

Used in these records

About this file

File size
15.9 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Stormwater Management Plan.pdf · 15.9 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.