ORDINARY MEETING MINUTES 18 JULY 2019
b. Maintenance and protection of the adjoining Lake Doonella Bush Reserve
c. Maintenance and protection of water quality and existing drainage lines
through the construction site through the implementation of appropriate
erosion and sediment control measures
d. Works programme identifying key components of the works and their
respective durations
e. Establishment of a communication protocol with the general public,
adjoining owners (especially residential), emergency services and local
businesses to advise of agreed construction times, impacts on traffic and
services and other relevant issues
f. Identification of complaint management procedures including:
i. contact details for the on-site manager
ii. dispute resolution procedures
For haulage operations involving significant volumes of fill material or excavated
material being transported onto or off the site: details on the location of external
fill sites/sources, the haulage route, type of vehicle to be utilised during filling
operations and frequency of usage. Any damage to the existing road system as
a result of haulage operations shall be fully repaired at the applicant’s expense.
Landscaping
75. The area between Stage D and the extent of the northern boundary must be
densely landscaped at a minimum width of 2 metres in accordance with an
Operational Works approval. Screening vegetation must be planted in accordance
with Council’s Planning Scheme Policy PSP3 Landscaping Plants and Guidelines.
The planted vegetation must consist of native, endemic species.
Nature and Extent of Approved Use - Veterinary
76. Service vehicle movements associated with the approved use (including loading
and unloading) must not occur outside the hours of 7am to 7pm. The requirements
of this condition must be included in the Community Management Statement for
anybody corporate for the subject site
Sunset Clause
77. Pursuant to s88(1) of the Planning Act 2016, the uncompleted aspects of the
approval for Stage D lapses if the whole of the approved use has not happened
18 July 2025.
C. Advise the applicant that the construction of the bus stop and at grade car park required
by conditions 1, 36, 37, 39, 40 & 66 are outstanding and must be completed by 18
January 2020.
D. Note the report is provided in accordance with Section 63(5) of the Planning Act 2016.
3 MCU18 0009 01 - MINOR CHANGE TO DEVELOPMENT APPROVAL FOR MATERIAL
CHANGE OF USE - MULTIPLE HOUSING - TYPE 3 RETIREMENT & SPECIAL NEEDS AT
186 COOROY-NOOSA ROAD TEWANTIN
That Council note the report by the Coordinator Planning to the Planning & Environment
Committee Meeting dated 9 July 2019 regarding Application No. MCU18/0009.01 to make a
minor change to an existing approval for Material Change of Use - Multiple Housing –Type 3
Retirement & Special Needs situated at 186 Cooroy Noosa Rd Tewantin and:
A. Approve the change and amend conditions 1, 6, 26 and 36 to read as follows:
Page 8 of 20
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.