               11.    A Construction Management Plan must be submitted to Council prior to the prestart meeting
                      and must specifically address the following:
                      a.      Traffic Management during all aspects of the construct phase including:
                              i.       A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
                                       Control Devices (MUTCD) detailing all needed temporary warring signage and
                                       traffic control measures near the construction site and on the approaching roads.
                              ii.      Details of managing access and manoeuvring of construction vehicles and
                                       appliances (eg concrete trucks) into and from the construction site.
                              iii.     Details of timing and measures to minimise impact on the local traffic flows in the
                                       area and avoid peak hours/ periods traffic.
                              iv.      Maintenance of safe pedestrian access across the frontage of the site both during
                                       daily construction and after daily construction has ceased.
                              v.       Proposed fencing to the site during the construction phase of the development.
                              vi.      Appropriate parking arrangements for construction’s workers and vehicles that
                                       ensure no adverse impact on parking spaces availability to the public.
                      b.      Maintenance and protection of water quality and existing drainage lines through the
                              construction site through the implementation of appropriate erosion and sediment
                              control measures
                      c.      Works programme identifying key components of the works and their respective
                              durations
                      d.      Establishment of a communication protocol (eg letterbox drop letters) with the general
                              public, adjoining owners, emergency services, local police and local businesses to
                              advise of agreed construction times, impacts on traffic and services and other relevant
                              issues.
                      e.      Identification of complaint management procedures including:
                              i.       contact details for the on-site manager
                              ii.      dispute resolution procedures
               12.    Any changes to the details associated with the supervising RPEQ or Principal Contractor
                      during construction, must be notified to council in writing within five business days of the
                      change occurring.
               13.    Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.
               DURING CONSTRUCTION
                      Engineering General
               14.    The developer must meet any costs to repair damage to any Council asset during
                      construction, where damage is a result of the development works. Damage to assets must
                      be repaired immediately where it creates a hazard to the community. In circumstances where
                      the damage does not create a hazard to the community, it must be repaired immediately on
                      completion of the works associated with the development.
               15.    All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where municipal works are involved, such
                      confirmation must be submitted for the respective hold points prior to any site inspection by
                      Council Officers.
               16.    All works must be constructed and work procedure undertaken in accordance with:
                      a.      The approved plans and conditions detailed in this Decision Notice.




                                                                                                            Page 4 of 11
Document Set ID: 21120931
Version: 3, Version Date: 23/04/2020                                                                     Print Date: 24 April 2020, 12:22 PM
Log in to download the original file

Approval for OPW.pdf · 4.9 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.