Approval for OPW
Noosa Council documents
b. The relevant conditions of the higher order Material Change of Use approval Ref:
MCU19/0031 - dated 22 August 2018 to which this approval relate.
c. All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines.
d. The latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site.
Pavement Design and Construction
17. Pavement design for privately owned works must be undertaken in accordance with the
relevant standards. Structural integrity of the driveway and car park areas will remain the
responsibility of the property owner/developer and must be certified by an RPEQ.
Works within Road Reserve/Reinstatement
18. Safe pedestrian access on all streets in the vicinity of the development must be maintained
at all times. Should footpath/road closures be necessary to carry out construction works,
Council’s Engineering Officer must be notified prior to the proposed closure and all
requirements complied with.
19. All frontage works must match neatly with existing road and verge/footpath features.
Additional works beyond the frontage may be required to provide an acceptable transition to
existing road and verge/footpath profiles and ensuring no trip or fall hazard to the public and
the property users.
20. Any existing kerb & channel and/or concrete footpath sections requiring removal due to the
new works must be saw-cut and removed to allow for a smooth and neat finish with the new
works.
21. Electrical conduits or other services proposed to be installed within existing and proposed
road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
driveways or significant vegetation must be installed by boring. Trenching is not permitted,
unless specifically approved by Council in writing.
Site Access, Driveway and Car Parking Area
22. New driveway must be constructed generally in accordance with the approved plans.
23. Landscaping, fences and other fixtures near the access must be provided to allow for clear
sight distances to pedestrians and drivers in compliance with the requirements of Section
3.2.4 and Figure 3.3 of AS/ANZS 2890.1.
24. The following must be complied with during the construction of the required
crossover/driveway and car park:
a. The driveway must be constructed so as not to concentrate stormwater runoff onto
neighbouring properties or on the road verge and public pathway.
b. Where there is an existing or proposed pedestrian path, a matching crossfall must be
provided for the driveway for the full width of the path and ensuring no trip or slip hazard
is created due to the new works.
25. All paved areas for the driveway, parking, vehicles manoeuvring and pedestrian access must
be slip resistant in accordance with the applicable standards.
26. Parking area, internal kerb construction and linemarking must be provided generally in
accordance with the approved plans and in compliance with applicable standards and best
engineering practices.
Page 5 of 11
Document Set ID: 21120931
Version: 3, Version Date: 23/04/2020 Print Date: 24 April 2020, 12:22 PM
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.