Bushfire Hazard Assessment & Management Plan v2 - 30 Pottery St Pomona 2021

of 62

Page text read automatically using OCR, there may be inaccuracies

Bushfire Hazard Assessment & Management Plan v2                                NCES REF: J000864
Lot 496 on MCH591 – 30 Pottery St, Pomona



5    BUSHFIRE IMPACT REDUCTION MEASURES

5.1 General
The following section describes bushfire impact reduction measures to be incorporated into
the proposed development to reduce the risk of bushfire impacts to people and property.
Implementation of the identified measures is not implied nor intended to advocate that building
occupants remain on the site during a bushfire event, nor that people and property will be
protected from bushfire impacts. The measures are intended to reduce the potential severity
of bushfire impact to the development and not prevent bushfire impact. The bushfire mitigation
measures have been derived from:
    •    Department of State Development, Manufacturing, Infrastructure and Planning’s State
         Planning Policy – State interest guidance material – Natural hazards, risk and
         resilience – Bushfire (December 2019) (referenced herein as SPP (Bushfire) 2019);
         and
    •    Queensland Fire and Emergency Services. (2019). Planning for Bushfire Resilient
         Communities.

5.2 Asset Protection Zones
5.2.1    General
Asset Protection Zones (APZ) provide a defensive tool to assist in the reduction of potential
bushfire impact to people and property situated in bushfire prone areas. For illustrative
purposes, Plate 13 depicts the concept of an APZ surrounding a dwelling in a bushfire prone
areas.




                                      Plate 13 – Asset Protection Zones

The development has been confirmed to be located within a bushfire hazard area hence
provision of adequate separation between the building envelopes nominated immediately
flanking the western hazardous vegetation (i.e. Lot 8 in Stage 1 and Lots 8 and 9 in Stage 2)
is required to provide a reasonable level of safety to site occupants and emergency services
staff.
The configuration of APZ’s is typically determined based on the results of the site-specific
hazard assessment including risk of bushfire impact, flame length analysis, applicable
AS3959-2018 Bushfire Attack Levels and SPP Assessment Benchmark setback
requirements. In this instance, the assessed plan of development offers a minimum of 19m
separation between the Lot 8-10 building envelopes and the VHC 9.1 open eucalypt forest,
which is proposed to be protected within the conservation covenant.




© 2021                                                   21

Log in to download the original (Bushfire Hazard Assessment & Management Plan v2 - 30 Pottery St Pomona 2021.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.