A DRAINS model was completed to compare the impact of Catchment B connecting to the existing
drainage.
Survey data and pipe sizing of the infrastructure was obtained. Catchment areas for the pits along the
pipe run were obtained from Council’s mapping system.
They are as follows: -
Pit Number Catch Area (m2)
H5 18900
H4 5700
H3 3400
H2 2800
H1 2100
Hydraulic grade line comparisons were made for existing and proposed states.
SCG Consulting Engineers Page 20 SCG Ref: 33132(SWMP)