Decision Notice - MCU22 0038 01 [As Published] · MCU22/0038.01

of 15

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

                      d.      accommodation for both severe storms or severe blockage of the underground
                              drainage network. A Severe Storm/Severe Blockage Assessment for the drainage
                              system proposed for the site is to be provided with the development application for
                              operational works, and is to demonstrate that finished floor levels will not be inundated
                              under either a severe blockage of the underground drainage network in the 1%AEP
                              event at year 2100, or for a severe storm exceeding the 1%AEP based on design
                              blockage.
                      Acid Sulfate Soils
               63.    An Acid Sulfate Soil Management Plan must be prepared and submitted with the Operational
                      Works application for the site. The acid sulfate management plan must include testing,
                      monitoring and treatment requirements for the works.
                      Services
               64.    Unless otherwise stipulated by telecommunications legislation at the time of construction, the
                      development must be provided with all necessary conduits, pits and pipes to accommodate
                      the future connection of optic fibre technology telecommunications.
               65.    Certification must be submitted to Council from all relevant service providers (Energex, NBN
                      and Unitywater which certifies that the development has met the requirements of this
                      Decision Notice and all applicable legislation at the time of construction.
                      Easements
               66.    Unless otherwise agreed in writing by the relevant service provider, any public or third party
                      infrastructure located on the subject site must be placed within an easement registered
                      against the title of the property.
               67.    All easements must be designed in accordance with the planning scheme and granted at no
                      cost to the Grantee. Where the Grantee is Council or a service authority, the easement
                      documentation must be in accordance with the Grantee’s standard easement terms. Draft
                      easement documentation must be submitted to Council for endorsement.
               68.    All works must be kept clear of any existing or proposed easements on the subject land,
                      unless agreed otherwise in writing by the Grantee.
                      Earthworks and Retaining Walls
               69.    All excavation, fill, soil retaining structures and associated batters must be undertaken in
                      accordance with an Operational Works approval, and contained entirely within the subject
                      site unless written permission from the respective landowner(s) is provided to Council.
               70.    All retaining walls must be designed and constructed in accordance with the planning scheme
                      and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
                      are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
                      safety fence.
                      Damage to Services and Assets
               71.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.
               WASTE DISPOSAL
               72.    Prior to the issue of any Operational Works approvals the Operational Waste Management
                      Plan must be amended to reflect that all waste collection will be undertaken by Council’s
                      contractor via rear lift trucks with the trucks collecting 1100 litre bins.


                                                                                                         Page 8 of 15
Document Set ID: 22385500
Version: 8, Version Date: 28/04/2023

Used in these records

About this file

File size
323 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - MCU22 0038 01 [As Published].pdf · 323 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.