ADG Consulting Pty Ltd
The calculation results are based on the following parameters and known site‐specific conditions:
Approximate length of excavation = 36 m
Approximate width of excavation = 17 m
Reduction in depth of groundwater across the excavation = 2.6 m (based on an approximate
groundwater depth of 0.5 m AHD)
Approximate depth of saturated thickness of unconfined aquifer = 10 m (conservative standardised
approximation)
A conservative soil profile of fine to medium grained sands, has a hydraulic conductivity of approximately
8.2 m/day, or equivalent 0.0000949 m/sec (WA Calculator). The results of the calculation are shown in
Table 4 below, and provided in Appendix D.
Table 4 Dewatering extraction rate results
Output Result
Effective radius of pumping well (m) 14
Dewatering radius of influence (m) 76
Discharge rate (L/sec) 8
Discharge rate (L/hr) 28,600
Establishment of cone of depression (hours) 102
Based on the above inputs, a groundwater flow rate of approximately 480 L/min or 28,600 L/hr has been
predicted for the development. Flow rates are predicted to be highest during initial drawdown of the
groundwater table within the basement excavation footprint and reducing to approximately 5 – 6 L/sec
following establishment of the cone of depression within the excavation. Flow rates may fluctuate due
to tidal variations, generally approximately ± 0.5 m, and will also be influenced by rainfall and surface
water collection within the basement excavation footprint noting the underlying predominantly sand
profile encountered during geotechnical investigations.
Regardless of the contractor employed, groundwater treatment systems should be installed with
capability for treating flow rates of up to 8 to 10 L/sec, as a contingency against higher than anticipated
flow rates exceeding the estimated 7 L/sec as a result of varying ground conditions across the extent of
excavation.
However, it should be noted that the WA Calculator provides a conservative assessment of inflows to an
excavation footprint based on area and depth but does not take account of the shoring wall, which will
inhibit lateral inflows to some extent. Also note that the cone of depression radius measure includes
water table depressions of 1 mm depth or more, so any significant depression of the water table is limited
to much closer to the dewatering spears or wells (generally within 3 to 10 m from the shoring wall in fine‐
medium grained sands, depending on density of the strata).
5.4 Dewatering duration
Dewatering will be necessary throughout the basement construction phase, which is expected to require
continual dewatering for approximately eight to twelve weeks. To minimise the potential impacts during
construction of short‐term dewatering, periods of active dewatering will be minimised as much as
possible. However, ADG notes that once active dewatering has commenced, dewatering will not be able
to be ceased until both: a) the basement hydrostatic uplift forces have been compensated to the
satisfaction of the consulting RPEQ engineer; and b) potential hydraulic loading on the external face of
the shoring system has been compensated to the satisfaction of the consulting RPEQ engineer and
shoring contractor.
5.5 Groundwater drawdown
Groundwater drawdown caused by dewatering has the potential to create settlement in unconsolidated
sediments and loose sands. It is noted that dilapidation reports for surrounding structures and services
ADG1777.25 Dewatering Management Plan_Rev0_01.05.25 Page 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Appendix H - Dewatering Management Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 14.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.