Council archive · source document
Appendix H - Dewatering Management Plan · MCU25/0053
Plans and drawings: the text below has words only, no drawings.
Very large file (14.2 MB): may take a few minutes to open.
ADG Consulting Pty Ltd
are proposed to be undertaken which were not supplied to ADG for the purposes of preparing this DMP
and are to be provided to Council separately from this DMP.
Groundwater drawdown may also oxidise potential acid sulfate soils within the cone of depression,
subsequently producing acidic groundwater conditions and mobilising heavy metals. Monitoring of the
extracted untreated groundwater will be undertaken to detect in‐situ oxidation of soils, as required and
at the frequencies stated in Section Error! Reference source not found.. Groundwater monitoring bores
for groundwater level gauging external to the excavation footprint are expected to be unable to be
established and monitored prior to and during construction on the site, due to limited space (SCG
Consulting Engineers).
Civil Engineering plans of the proposed development and basement arrangement are provided at
Appendix C.
5.6 Groundwater treatment
All extracted groundwater will be treated on‐site using available technologies prior to discharge to the
stormwater network. The following treatment measures (or similar depending on final dewatering
contractor selection) will be adopted, and will be installed and operational prior to the commencement
of dewatering:
1. A groundwater pH buffering treatment system (primary treatment)
2. A sedimentation tank to provide additional residence time and sedimentation (secondary
treatment)
3. A fine media filtration system designed for effective removal of heavy metals (tertiary treatment),
tertiar
if required.
Details of the treatment systems and methodologies are provided in Section 6 of this report.
Note: Consideration should be taken regarding placement of treatment gear on site to enable easy
cleaning and maintenance throughout the dewatering phase for the project. Consider the potential
requirement for regular de‐sludging of sedimentation tank/s to suitable area onsite, if available (cost
minimisation).
5.7 Nominated Hold Points
In accordance with anticipated DA Conditions, nominated hold points to be enacted during construction
have been proposed to facilitate for certification by the suitably qualified person experienced with Acid
Sulfate Soils, as well as Council Development Engineer to ensure all possible avenues for continual
dewatering below permanent groundwater level, including around pipework bedding that outlet to
waterways, are appropriately sealed. The nominated hold points regarding dewatering for this project
are:
1. Prior to commencement of dewatering/initial pump out
2. At finished excavation level, prior to blinding layer application
3. External to basement service installation trench opening/s prior to backfilling.
The above nominated hold points are subject to confirmation by the consulting engineer, and liaison with
council representatives and the Site Manager.
ADG1777.25 Dewatering Management Plan_Rev0_01.05.25 Page 12
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Appendix H - Dewatering Management Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 14.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.