12. Appendix I - Engineering Services Report
Original PDF page 12, section 1. The text section number identifies this passage in the reader.
Infrastructure Services Report
Noosa Marketplace Development, 2 - 20 Hofmann Dr, Noosaville
4.4 Electricity Supply
Energex is the responsible authority for the provision of electricity supply facilities for the development. A
network of high voltage cables traverse along Hofmann Drive, which will be sufficient in providing power
supply to the development.
Transformers, high voltage cables and kiosk substations will be required to be extended across the site to
provide trunk electricity supply for the development.
Figure 4-4 Power assets (Energex asset plans)
17 May 2019 Cardno 12