SUPERSEDED Decision Notice - Council Meeting Decision MCU21 0110.pdf
Odour
2. Be advised that the development is located in near proximity to the Unity Water Noosa
Sewerage Treatment Plant, the operation of which may, at times, result in detectable
odours on the development land. This advice is provided to ensure that the developer
and resort operator are informed of the potential for detectable odours due to sewerage
treatment plan operation and the basis for conditions in this approval package with
respect to odour monitoring/management measures. It is the responsibility of the
developer/resort operator to ensure that compliance with odour monitoring/management
conditions is achieved at all times.
Building and Construction Industry (Portable Long Service Leave) Levy
3. The QLeave levy must be paid prior to the issue of a development permit where it is
required. Council will not be able to issue a Decision Notice without receipt of details
that the Levy has been paid.
Co-ordination of Operational Works Assessment
4. Additional application fees apply to Operational Work applications where the different
aspects of the works are lodged separately. Significant savings in application fees will
result if all works are lodged in a single application.
Qualified Person
5. For the purpose of preparing a Geotechnical Report, and for certifying geotechnical
stability for the development, a qualified person is considered to be a person who:
a. is a Registered Professional Engineer of Queensland (RPEQ); and
b. has a degree in civil engineering or engineering geology; and
c. has a minimum of 5 years experience in the field of geotechnical engineering or
engineering geology.
Preparation of a Preliminary Construction Management Plan
6. A preliminary Construction Management Plan must be submitted with the Operational
Works application and must address the following:
a. traffic management during all aspects of the construction phase including:
i. a Traffic Management Control Plan in accordance with the Manual of
Uniform Traffic Control Devices (MUTCD) detailing all temporary signage
and traffic control measures prior to construction
ii. maintenance of safe pedestrian access for the areas affected by the works
during and after daily construction has ceased
iii. proposed fencing to the site during the construction phase of the
development
iv. approval of the Traffic Management Control Plan by the Department of
Transport and Main Roads (DTMR) for any works on State controlled roads
v. provision for worker car parking
b. maintenance and protection of water quality and existing drainage lines through
the construction site, through the implementation of appropriate erosion and
sediment control measures
c. works programme identifying key components of the works and their respective
durations
Page 15 of 53
Document Set ID: 23746767
Version: 6, Version Date: 22/05/2025
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewSearchable page text hides email addresses. Original files are unchanged and may show email addresses.