Skip to the record
Mmm.. taste the original NoosaWatch™

Original source · versioned page text

Development Application part 2 Report and Plans MCU13/0052

of 132

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (119 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
                                        SCRC CORRESPONDENCE



                  Place barcode here   1111111111111111111111111
                                             80538887

    THIS IS THE NEXT PART OF A
 MULTIPLE PART RECORD

           Part   1_ Of ~                           ~c1t5 &,,-. ~......Iff
                                                                   ~




Application number:             1\1\ W )’)/ao 52
Log in to download the original file

Development Application part 2 Report and Plans MCU13_0052.pdf · 119 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of pages 2 to 78 (of 132)

Page 2

.   I




         .,: ~\’elopmei1t Counter
                                        ~
                22 MAR 2013          c:::~
                                     ~~
                                          ~

        L- ~"aroochydore            BNC
                                     Limited


[OCR of page images]
Broadbanding
Australia

Planning Report

Proposed Fixed Wireless Facility

153 Lake Flat Road
Boreen Point 4565

NBN Site Reference

NBN-4NBZ-4POM-5136 — Boreen Point
North

Prepared on behalf of NBN Co Limited
by Aurecon Australia Pty Ltd

NBNCo

Limited

 

Page 3

            Do iiment Control Record

            Document prepared by;

            Aurecon Australia Pty Ltd
            ABN 54005 139 873

            Level 14, 32 Turbot Street
            Brisbane QLD 4000

            Locked Bag 331
            Brisbane QLD 4001
            Australia


            T     +61731738000

            ~     +61 7 3173 8001

            E     [email protected]
            w     aurecongroup.com




            A person using Aurecon documents or data accepts the risk of:

            a)    Using the documents of data in electronic form without requesting and checking them for accuracy against
                  the original hard copy version.

            b)    Using the documents or data for any purpose not agr.eed to in writing by Aurecon.




        I    Document control                                                                                      aurecon


            Report Title                       Planning Assessm~nt Report (ImpactAssessment) Pr pose-d Telecommunication
                                               Facility at Lake Flat Rd, Boreen Point QLD 4565
            Document ID                        Planning Assessment Report    .
                                                                                 Project Number       226420-001-01

                                               (ImpactAssessment)
            File Path                          P:\Telco\6. Ericsso!1 NBN\Site Clusters\Nambour Cluster\Site Folders\Boreen Point
                                               North\Planning\Development Applic;ation
            Client                                                  Client Contact                                      ..




            Rev               Date             Revision             Prepared by       Author       Verifier        Approver
                                               Details/Status
            01                22/ 1/2013       DRAFT                CH      ..
                                                                                      CH           RB              RB
                  .   .
                          .                                                                                                        "’   -




            02                08/02/13         FINAL                CH                CH           RB              RB

.   .


            Current.Revision                   2




            NBN-4NBZ-4POM-5136             -
                                               Boreen Point North                                                     Page 1

Page 4

Table of Contents

Document Control Record .......................................................................1

EXECUTIVE SUMMARY .............................................................................4

1.0     INTRODUCTION ..............................................................................5

2.0     BACKGROUND ...............................................................................6

  2.1     NBN Co and the National Broadband Network ..........................................;........... 6

  2.2     What is Fixed Wireless and how is it different to Mobile Broadband?                                     ...................
                                                                                                                                        6

  2.3     The Fixed Wireless Network               -

                                                       Interdependencies ..................................................6

3.0     SITE SELECTION             ..............................................................................
                                                                                                                            9

  3.1     Identification of areas requiring Fixed Wireless coverage...................................... 9

  3.2     Site Selection Parameters......................................................................................9

  3.3     Candidate Sites.................................................................................................... 10

4.0     SUBJECT SITE & SURROUNDS.......................................................14

  4.1     Site Details...............................    ...........................................................................
                                                                                                                                       14

  4.2     Site Surrounds..................................................................................................... 17


5.0     THE PROPOSAL.................           ................................................................
                                                                                                                          18

  5.1      Facility and Equipment Details ............................................................................18
  5.2     Site Selection......................................................................................    .................
                                                                                                                                       21

6.0     CURRENT PLANNING CONTROLS......................................................... 22

  6.1     Commonwealth Legislation                -
                                                       The Telecommunications Act 1997........................ 22

  6.2     State Legislation        -
                                     Sustainable Planning Act 2009                   ...............................................
                                                                                                                                       22

  6.3     State Legislation        -


                                     Vegetation Management Act 1999......................................... 22

  6.4     State Planning Policy Framework                   ........................................................................
                                                                                                                                       24

  6.5      Draft Coastal Protection State Planning Regulatory Provision.............................. 27

  6.6      Regional Plan....................................................................................................... 27
  6.7      Referral Agencies ...........................................................................:.....................28

  6.8      Local Government Regulatory Framework                          ..........................................................
                                                                                                                                       28

  6.8.1    Planning Scheme use definition...........................................................................28

7.0     PLANNING CONSIDERATIONS............................................................. 33

  7.1 Desired Environmental Outcomes ...........................................................................33

  7.2 Applicable Codes .....................................................................................................35




NBN-4NBZ-4POM-5136         -   Boreen Point North                                                                          Page 2

Page 5

  7.2.1 Boreen Point, Kin Kin & Cootharaba Locality Code                            ................................................
                                                                                                                                        36

  7.2.2 Infrastructure Uses Code .................:....................................................................39

  7.2.3 Earthworks Code           ..................................................................................................
                                                                                                                                        40

  7.2.4 Landscaping Code .................................................................................................41

  7.2.5 Driveways and Carparking Code............................................................................ 42

  7.2.6 Biodiversity Overlay Code ..............;~:.............................:...;....................................43

  7.2.7 Natural Hazards Overlay Code                  ..............................................................................
                                                                                                                                        44

  7.2.8 Natural Resources Overlay Code.................................................................::........ 45

  aJ for agricultural land conservation areas- .................................................................45

8.0     OTHER ENVIRONMENTAL CONSTRAINTS AND OPPORTUNITIES ...46

  8.1     Visual Amenity and Setting..........:..........................;.............................................. 46

  8.2      Heritage.    .............................................................................................................
                                                                                                                                        52

  8.3      Electrical Interference and Grounding of the Facility ....................:..............;......... 52

  8.4      Erosion, Sedimentation Control and Waste Management........                                   ...........................
                                                                                                                                        52

  8.5      Remnant and Regrowth Vegetation ........................................................:.,......... 52
                                                                               .                            .




  8.6      Flora and Fauna & Endangered Species ......................................:......................... 53

  8.7     Social and Economic Impacts...............................................................................53

  8.8      Public Safety........................................................................................................53

  8.9     The Public Interest and the Benefits of Telecommunications...................:........... 54

9.0     CONCLUSION ................,..............................................................55




APPENDICES

Appendix 1-Transmission Imagery

Appendix 2 Copy of Title
              -




Appendix 3    -

                  Proposal Plans

Appendix 4    -
                  Code Table Assessment

Appendix 5    -
                  Environmental Searches

Appendix 6    -
                  ARPANSA EME Report


Appendix 7    -
                  Communications Plan and Advertising




NBN-4NBZ-4POM-5136         -   Boreen Point North                                                                        Page 3

Page 6

                         ._   -           ~~
                                  .....




EXECUTIVE SUMMARY’

                                     NBN Co propose to install a new fixed wireless broadband
                                    facility at Boreen Point North comprised of the following:
                                             40 m monopole;
                                             3 X parabolic dish antennas;
                                             2 X panel antennas;
                                               2 X remote radio units;
                                               2 X 0.65 m2 outdoor cabinets (one future & one
                                               proposed); &
                                               Ancillary equipment associated with operation of
                                               facility, including cable trays, cabling, safe access
                                               methods, bird proofing, earthing, electrical works
                                               and air-conditioning equipment.



                                    The proposed facility is necessary to provide NBN Co fixed
                                    wireless broadband coverage to the Boreen Point North
                                     region.

                                    Lot & Plan No: Lot 2 RP126723
                                     Street Address: 153 Lake Flat Road, Boreen Point OLD
                                    4565
                                     Property Owner: Graeme Arbuckle

                                     Council: Sunshine Coast Regional Council
                                    Zones: Boreen Point North Kin Kin & Cootharaba Locality
                                    -
                                           Rural Zone
                                     Overlays: Refer to Section 6..8.3
                                     Use Definition: Infrastructures Use, Service & Utility (Type
                                    3-T

                                     Relevant State, Regional & Local Planning
                                     Policies
                                                                                         Complies

                                    The Noosa Plan 2009                                  Yes


                                    South East Oueensland Regional Plan
                                                                                         Yes
                                    2009-2031


                                    State Planning Policies                              Yes


                                    Use and development of the land for the purposes of
                                    construction & operation of a Telecommunication Facility
                                    (Fixed Wireless Broadband)

                                     NBN Co Limited (NBN Co)
                                    c/- Aurecon
                                     Locked Bag 331
                                     Brisbane OLD 4001
                                    Contact: Claire Harris
                                    Our Ref: Boreen Point North- NBN




NBN-4NBZ-4POM-5136   Boreen Point North
                     -

                                                                                                 Page 4

Page 7

 1.0.. INTRODUCTION

NBN Co has engaged Ericsson as the equipment vendor and project manager to establish
the fixed wireless component of the National Broadband Network (or NBN). Ericsson has
consequently engaged Aurecon Australia to act on its behalf                            in   relation   to   the
establishment of the required fixed wireless network infrastructure.


The NBN is a high speed broadband network that utilises a combination of optical fibre,
fixed   wireless       and       satellite   technology   to    offer   advanced   broadband. services       to
households and businesses across Australia. As part of the Australia wide progressive roll
out, these improvements to broadband services will ultimately deliver benefits to’various
areas such as business, education, entertainment and health.



To enable" the fixed wireless component of this network, NBN Co requires a fixed wireless
transmission site to provide high speed wireless broadband coverage to the Boreen Point
North and Cootharaba area; and also to serve as a key communications anchor point for
other NBN.Wireless facilities in the wider region.


An in-depth site selection process was undertaken in the area prior to confirming the site
as   the   preferred location. This process matched potential candidates against .four key
factors, namely:
     .     Town planning considerations (such as zoning, surrounding land uses,
           environmental significance and visual impact);

     .     The ability of the site to provide acceptable coverage levels to the area;

     .     Construction feasibility; and
                                         ,


     .     The ability for NBN Co to secure a lease agreement with the landowner.


:rhis application seeks planning consent for:
     .     A 40 m monopole;
                                                           ..




     .     Radio transmission equipment; and

     .     Outdoor equipment cabinets.


The facily will be located at 153 Lake Flat R ad, Soreen Point; legally described as Lot 2
                                                                            .

                   .                            .                                            .




on RP126723.



This submission provides an assessment of the r levant plal")ning guidelines applicable to
the project site and proposed land use. This report demonstrates that:
     .     The proposed site is appropriately located within an existing highly modified rural
           area largely used for intensive agricultural cropping land and provides an adequate
                                                                                                             .




           separation distance from environmentally and community sensitiv~ land uses;
     .     The site w l achieve the required coverage objectives for the area;

     .     The proposal complies with the Noosa Plan 2009 and the Sustainable Planning Act
           2009;
     .     The proposal operates within the regulatory framework of Commonwealth, State
           and Local Government; and

     .     The facility operates within all current and relevant standards and is’ regulated by
           the Australian Communications and Media Authority.




NBN-4NBZ-4POM-5136           -   Boreen Point North                                                Page 5

Page 8

2.0              BACKGROUND
2.1     NBN Co and the National Broadband Network

NBN Co is a Government Business Enterprise and is a wholly Federal Government owned
company established to design, build and operate the National Broadband Network (NBN).


The NBN seeks to deliver high speed broadband to all Australian households, businesses
and   enterprises through a combination of fibre, wireless and satellite technology. The
NBN will service 93% of homes, schools and workplaces with optical fibre connection
(fibre to the premises or "FTTP"), providing superfast broadband services to Australians in
both urban and regional towns. For the remaining 7% of sites located outside the fibre
network boundary, NBN Co will utilise a combination of next generation fixed wireless and
satellite technologies.


2.2     What is Fixed Wireless and how is it different to Mobile
        Broadband?

Fixed Wireless is a network of base station facilities that provide a broadband service via
radio transmissions. These base stations communicate directly with antennas fixed to
individual premises (e.g. dwellings or businesses) to deliver wireless broadband access.


While a mobile network caters to unpredictable numbers of concurrent users at unknown,
transient locations, the Fixed Wireless network communicates to   a known number of

subscribers in fixed locations.


This design difference means that the Fixed Wireless network can target higher levels of
assurance, quality and speed than mobile broadband services, even in peak times of use.
By quantifying the number of subscribers each facility is designed to service, NBN Co
ensures     that the fixed wireless network has the    capacity to deliver high-speed data
transfer.


The Fixed Wireless network is capable of delivering a minimum peak download speed of
12 Mbps, regardless of the distance of the      premises to the facility. This is also an
important distinction to existing ADSL services, where download speeds fall off
significantly the further away a user is from the nearest exchange. The Fixed Wireless
network thereby provides more universal access to reliable, high-speed broadband
services.


Fixed Wireless is not impeded by the variables that affect mobile networks, and as such
can   offer   reliably faster, more universally accessible broadband speeds with greater
certainty.

2.3     The Fixed Wireless Network              -
                                                    Interdependencies

Although the Fixed Wireless facilities are submitted to Council as stand-alone
developments from a planning perspective, from a technical perspective, they are highly
interdependent connected to each other to form a daisy chain of facilities that link back
                  -




to the fibre network via a series of radio transmission dishes.


Each Fixed Wireless     facility comprises of three panel antennas, which communicate
directly with the premises. The data transmitted to and from these panel antennas is then
relayed via a chain of radio transmission dishes back to the fibre network. This is referred



NBN-4NBZ-4POM-5136     -   Boreen Point North                                     Page 6

Page 9

to   as   the "transmission network". The transmission network requires line of sight from
facility to facility until it reaches a Fixed Wireless facility that is physically connected to the
fibre network (referred to as the "Fibre HUB").


The Fixed Wireless network remains unconnected without this transmission network. A
break in this chain of transmission interdependencies can have flow on effects to multiple
communities, cutting them off from access to wireless broadband services.

Each NBN Co Fixed Wireless facility has been designed to heights that allow the panel
antennas to have clear line of sight to the surrounding premises (radio coverage), and also
ensure     that the radio transmission dish has clear line of sight to the adjoining network
facility to link the sites back into the broader network.

The character of the Fixed Wireless network is visually demonstrated through Figure 2.1
below. Additionally, Appendix 1             provides 3D imagery of the Fixed Wireless Network
transmission links and the            topographical challenges in the Sunshine Coast Regional
Council region.




                                                           Physical ,eonnectio:n
                                                           to optical: fibre.   the
                                                                                -




                                                           f.ibre spur




                                                                         Fixed: wireless facility-
                                                                         the Fibre Hub




                                                           Tlransmis~ion signal
                    lFacilit "COoverage area               connecting:fhe facilities



                                                                         Fixed, wirele~s. faility
                                                                         -
                                                                           wireless hub site



                                                               "
                      liransmission   signal/’                     Transmission signal
                      oonnectingthe fa    lifies I               \ eonlledingthe facilities
                                               I                  ,
                                               I                    ,




                                                                                         Fixed wire~ess fac.ility
                                                                                         -
                                                                                          transmission end

      Fixed. wireless facility
      -nmMmliMj n end
                                               Faoility coverage area

                                   Figure 2.1: The fixed wireless network.




NBN-4NBZ-4POM-5136       -
                             Boreen Point North                                                           Page 7

Page 10

Specifically the Boreen Point North site connects three other sites back into the Fibre
Network including the Boreen Point site which is located approximately 1.4 km north west
and on the same 318 ha property (Lot 2 on RP126723). Figure 2.2 below, illustrates the
proposed location of the Boreen Point North and Boreen Point facilities.




  Figure 2.2: Location of Boreen Point North and Boreen Point North Proposed Facilities (Source:Google Earth)


The Boreen Point site (which will be provided in a separate Development Application) has
been designed specifically to provide service to the concentrated residential settlement in
Boreen Point. In comparison the Boreen Point North facility is an essential wireless hub
site for the larger network as it can obtain line of site to the other wireless facilities located
further away where a 30 m monopole in the location of Boreen Point cannot. The Boreen
Point North facility not only provides wireless broadband services to surrounding premises
(specifically the scattered residential dwellings along Lake Flat Road, Kildeys Road and
Cootharaba Road) but is also a critical connection point for other fixed wireless facilities
located further away from the fibre network including the Fixed Wireless Sites at Boreen
Point, Coondoo West and David Cootharaba (Davis Road Cootharaba). In summary
Boreen Point North will enable data from both facilities at Boreen Point North and Boreen
Point to be    relayed back to the fibre network via a chain of transmission dishes, as
described above.




NBN-4NBZ-4POM-5136      -   Boreen Point North                                                      Page 8

Page 11

                         .   .




                             ..                            .




3.0
                     .




                         SITE SELECTION
Planning for a new fixed wireless broadband facility is a complex process. NBN Co
conducts a rigorous multi-stage scoping process, as outlined below.


3.1            Identification of areas requiring Fixed Wireless coverage

The NBN Co Fixed Wireless locations will be determined by a number of factors including
the availability of, both the NBN Co Fibre transit network and the availability of Point of
Interconnect (POI)facilities to allow for the installation of NBN Co equipment. NBN Co
uses a         number of methods .to identify those parts of Australia that require Fixed Wireless
coverage. When an area is’identified as requiring Fixed Wir~less coverage,.investigations
are undertaken to determine the me sures required to .provide this coverage.



NBN Co’has identified a requirement to provide a fixed wireless facility in Boreen Point.
The facility will provide Fixed Wireless coverage to dwellings in the Boreen Point North
and Cootharaba area, in addition to serving as a key communications link for other NBN
Fixed Wireless facilities in the wider Sunshine Coast region.


3.2            Site Selection Parameters

NBN Co identifies an area where the requirement for a Fixed Wireless broadband facility
would be highest, a ’search area.’      A preliminary investigation of the area is then
undertaken, in’   njunction with planning and property consult~nts; radiofrequency
                             c

engineers and designers in order to identify possible locations to establish a facility.

c:;enerally, new sites must be located within, or immediately adjacent to, the identified
search area in order to be technically feasible. However, while the operational and
geographical aspects of deploying new facilities are primary factors, there are also many
other issues that influence network design, which have to be resolved in parallel.


Some of the issues that are ..considered include:
       .       visual amenity
   :   ~       potential co-location opportunities
       .the availability and suitabilit              of land as well as a willing site provider
       .       occupational health and safety
      ..
           .




               construction issues (including structural and loading feasibility and              access    for
       :
               m intenance purposes)

       .       topographical constraints affecting network line of site
       .       legislative policy constraints
       .       envir nmental impacts
       .       cost implications.


The number, type and height of facilities required to complete the Fixed Wireless network
are  largely determined by the operational, geographical and other factors discussed
above, which influence final network design. These compounding factors often severely
restrict the available search area within which a facility can be established to provide
                                                                                                   .




reliable Fixed Wireless broadband to a local community.




NBN-4NBZ-4POM-5136                -   Boreen Point North                                           Page 9

Page 12

    3.3      Candidate Sites

    Following the identification of the search area for the Soreen Point North facility, a number
    of candidate sites were examined around the search area. Each candidate was assessed
    based on the ability to meet the coverage objectives and site considerations detailed
    above.    A total of three (3) candidates were selected for in-depth             investigation for the
    Soreen Point North facility, as per Figure 3.1 below.


    NSN Co endeavours to avoid locating facilities in close proximity to residential localities
    and potentially sensitive land uses, where practicable. The Soreen Point North locality is
    comprised predominantly of rural land uses, with scattered residential dwellings. As such,
    it is considered that the Soreen Point North area provides an appropriate location for a
    facility, given the physical separation provided from residential and other sensitive land
    uses.




I                        Figure 3.1: Location of Candidate Sites (Source:Google Earth)

    A summary of the proposed candidates is located below, including a description of the
    opportunities and constraints that each site afforded.




    NBN-4NBZ-4POM-5136   -
                             Boreen Point North                                                 Page 10

Page 13

Candidate A: Private Property, Lot 9 on RP181850, 91 Kildeys Road, Cootharaba.


Candidate A comprises the erection of a 40 m monopole on 14.3 ha parcel of land within
the ’Boreen Point North, Kin Kin & Cootharaba Locality           -
                                                                     Rural Zone’ under the Noosa
Plan 2009. The property is heavily vegetated with large mature gum trees and contains an
existing residential dwelling.

A 40 m monopole in the location of Candidate A would not provide adequate coverage to
the targeted localities throughout Boreen Point North and Cootharaba. This is because
some of the existing nearby gum trees exceed 40 m in height and therefore the antennas

would not have clear line of sight to the targeted dwellings or the Boreen Point facility
(required for transmission purposes). In addition. this candidate would be in close proximity
to multiple residential dwellings which align Kildeys Road and would require the removal of
remnant and koala habitat vegetation.


Pursuing this candidate was deemed unnec~ssary given that Candidate C provides a
more appropriate option in terms of achieving NBN’s coverage objectives, and will not

require vegetation removal. Furthermore, the land owners were unwillng to agree to
commercial terms to enable the developme’nt. For these reasons Candidate A was
discounted.


Candidate B: Noosa Shire Council Property, Lot 4 on RP803972, 304 Lake Flat Road,
Cootharaba


Candidate 8comprises the erection of a 40 m monopole on a 36.5 ha parcel of land within
the ’Boreen Point North, Kin Kin & Cootharaba Locality           -
                                                                     Rural Zone’ under the Noosa
Plan 2009. The property is owned by the Noosa Shire ’Council and is currently used for
Waste Treatment purposes.


A 40 m monopole in the location of Candidate 8would provide adequ.ate coverage to the
target d Idcalities througho t Boreen Point North. However it would be in proximity to a
number of residential dwellings and would require the -removal of a large portion of
                                                                                  .




vegetation for both the access track nd compound area.

 Pursuing this candidate was deemed unnecessary given that Candidate C provides a
 more appropriate .option as it will not require vegetatic:m remQval and ’provides a better

’separation from ’community sensitive locations. Furthermore, the land owners were
 unwilling to agree to commercial terms to enable the development.. For these’ reasons
                                                      ..                  .   .          .




GafJdidate"8 was discounted.
                                                             ’
                      .




Can idate C: Private Property,.Lot 2 on RP126723, ’153 Lake Flat Road, Boreen Point
North.


Candidate C r~lates to the current proposal and comprises the erection.of. a new 40 m
monopole 011 land within the ’Boreen Point North, Kin Kin & Cootharaba Locality          -
                                                                                             Rural
Zone’ und~r the Noosa Plan 2009. The 106 ha property is predominantly used for pine
forestry and logging and also contains an ancillary shed:in the centre of the site.
                                                                 "




      locality,surrounding the site is charact~rised by agricultural land uses,. heavily
The
vegetated   areas   and associ ted rural       dwellings. A proposed facility in the location of
                                                                                                     I
Candidate C will be suitably located on a site that contains similar infrastructure such as
the existing energex electricity network which runs from north to south on the subject site
(approximately 20 m east of the proposed facility). Candidate C has been sited an
appropriate separation distance from environmental and community sensitive locations, as
it is located within proximity to only three (3)residential dwellings within a 500 m radius.




NBN-4NBZ-.4POM-5136   -   Boreen Point North                                           Page 11

Page 14

These setbacks in conjunction with the natural vegetation on site will assist with visually
integrating the monopole within its surroundings and minimising the visual dominance of
the structure.


This site was determined to be the most appropriate location for the current facility as it is
able to achieve NBN Co’s coverage objectives for the Boreen Point North and Cootharaba
locality. Furthermore, the site maximises physical separation from community and
environmentally sensitive locations, and no vegetation removal is required. As such,
potential impacts associated with the proposal, will be minimised. For these reasons,
Candidate C was considered the most viable option and has been selected as the prime
candidate.


Co-location opportunities


The    area of Boreen Point North did not offer any possible or feasible co-location

opportunities. Figure 3.2 below illustrates the location of existing telecommunication
facilities in the wider area. Within a 11 km radius of the Candidate C (Prime)there is only
one existing facility. As shown the closest existing facility is located approximately 10.8 km

south of Candidate C (Prime) in the suburb of Cooroibah. This facility is outside of the
search area for Boreen Point North and would not provide reliable coverageto the
townshi   .




              Figure 3.2: Existing telecommunication facilities in the wider area (Source:Google




NBN-4NBZ-4POM-5136        -
                              Boreen Point North                                                   Page 12

Page 15

Prime Site Selection Reasons
Considering the factors identified above, Candidate C was ranked, as the preferred
location for the facility as the site is able to meet NBN’s target coverage objectives, whilst
maximising physical separation from surrounding rural-residential properties and
minimising potential visual amenity impacts. In summary, the site is considered to offer the
best solution because:

   .   The site is appropriately located within          a    rural area which is characterised      by
       agricultural      properties, heavily      vegetated    areas    and    large   rural-residential
       allotments;
   .   The site has already been significantly modified and contains similar infrastructure
       such as the energex electricity network, which runs from north to south through the
       property (approximately 20 m east of the proposed facility);
   .   The    existing    use    of the site for forestry and     logging purposes would        not be
       compro’mised by the proposed facility;
   .   The proposed location provides an adequate separation distance from community
       sensitive land         uses   and is located in   proximity     to   only three (3) residential
       dwellings within a 500 m radius;
   .   The proposed facility is located a sufficient buffer distance from environmentally
       sensitive locations (approximately 900 m from the edge of Lake Cootharaba) and
       no   significant vegetation removal will be required;
   .   The location  provides line of sight to other planned site$ in the NBN wireless
       network specifically Boreen Point, Coondoo West and David Cootharaba (Davis
       Road Cootharaba); and

   .   The  siting of a Telecommunication Facility               on   this site will   meet   coverage
       objectives for the area; and
   .   Visual   impact will be minimised given the pr sence of mature vegetation
       surrounding the site which will assist with visually integrating the monopole within
       its surroundings ana reducing the visual dominance of the structure.




NBN-4NBZ-4POM-5136       -
                             Boreen Point North                                               Page 13

Page 16

                                                                                                                ,




4.0               SUBJECT SITE & SURROUNDS

4.1     Site Details

The   subject site is located at 153 Lake Flat Road, Soreen Point. The site is legally
described   as Lot 2 on RP126723 and has an approximate land area of 106 ha. The

topography of the site is relatively flat, and the site is situated on relatively low terrain,
ranging from 29 m AHD at its highest point in the north-west where the proposed facility
will be located, to 10 m AHD at its lowest point, in the south-eastern corner. The Local
Government Authority for the proposal is the Sunshine Coast Regional Council and the
site is currently included in the ’Soreen Point, Kin Kin and Cootharaba locality        Rural              -




Zone’ under the Noosa Plan 2009. Figure 4.1 illustrates the proposed subject site and
location of the facility (indicated in yellow).




                                                                                                 /’~
                                                                                           /J
                                                                                           I




                                                                                       (
      Proposed Facility




                                                                               \,
                                                                                  ,(
                                                                      \
                                                                      I
                                                                               (
                                                                      I
                                                                      I
                                                                          !


                                   ~                                      \
                                           i          ________            I.
                                           I                                  \
                                           ’-                                  \
                                       I                                       \
                                       I
                                                                                   \
                                      L

                                                                                    I-"        ,




 ~
                                                                                    .’/’ llr.::s
                                                                                          lIod         ~trt ~
 Figure 4.1: Proposed subject site and location of facility (Source:http://qspatial.information.qld.gov.au/IQAtlas/)


The site is located approximately 2 km north west of the Soreen Point township, and 10.5
km north of Cooroibah. The subject site borders rural residential allotments to the south
and north, Lake Flat Rd to the north and east, and large agricultural properties to the west
which are predominantly used for pine tree plantations and conservation purposes. The

subject site is currently used for farming purposes, predominantly forestry and logging.
The site contains an ancillary shed in the middle of the lot and an energex electricity
network which runs overhead from north to south through the middle of the site
(approximately 20 m east of the proposed facility). The subject site is heavily vegetated
which will provide visual screening. There are three existing residential dwellings within




NBN-4NBZ-4POM-5136       -
                             Boreen Point North                                                           Page 14

Page 17

500 m ef the propesed facility, lecated to. the nerth ef the subject preperty. Figure 4.2
illustrates’the site lecqtien and characteristics.




The prepesed 7 m x 10m lease area (NBN ce’mpeund) is lecated in the nerthern portien ef
the preperty. The NBN cempeund will be setback apprpximately 40 m from the nerthern
preperty beundary, 630 m frem the eastern let beundary, appreximately 240 m from the
western let beundary and appreximately 1.1 km frem ttie seuthern let beundary. Altheugh
the propesed facility is lecated approximately 60 m frem the berder ef the Great Sandy
Natienal Park, the lecatien is censidered appropriate as the facility will be separated from
the Natienal Park by a bitumen road and lecated ever 350 m frem the clesest pertien ef
 mapped .remnant veget tien within the Natienal Park The prepesed facility is etherwise
 appropriately setback frem environmentally sensitive areas (eg mere than 900 m frem
 lake Ceetharaba and 300 m from ensite Remnant Vegetatien) and will net require
’remeval ef any vegetatien. Access to. the property is currently provided via lake Flat Read
 via an existing 180 m inte~nal access track.


Figure 4.3 and 4.4 shews the propesed lecatien ef the facility en the subject site.




NBN-4NBZ-4POM-5136    -   Boreen Point North                                          Page 15

Page 18

                      Figure 4.3   -
                                       Proposed location of the facility (arrowed)looking south east




,..




                           Figure 4.4   -

                                            Proposed location of the facility (arrowed)looking west




      NBN-4NBZ-4POM-5136   -
                               Boreen Point North                                                      Page 16

Page 19

4.2        Site Surrounds
The site surrounds        characterised by large farming properties, heavily vegetated
                              are

hinterland     areas    large rural-residential allotments. The closest dwelling located
                        and
outside of the property boundary lies approximately 100 m north of the proposed facility,
however there are only two other residential dwellings within a 500 m radius of the facility.
.




    Nearby villages and townships in the wider locality include Coondoo and Como (north),
    Kin Kin (west), Cootharaba (south west) and Cooroibah (south). The wider locality also
contains areas of environmental and heritage significance, including but not limited to:
       .   Lake Cootharaba located east
                          ,


       . Cooloothin Conservation Park, Noosa River and Lake Cooroiba located south
       . Lake Cooloola, Lake Como and Great Sandy National Park located north




Figure 4.4 below provides an                 aerial view of the             subject site     in the context of the
surrounding area.




            Figure 4.4: "Aerial view of the subj   t ’site   nd surroundin’g lan(l uses. (Source:




NBN-4NBZ-4POM-5136         -
                               Boreen Point North                                                        Page 17

Page 20

    5.0            THE PROPOSAL
    5.1     Facility and Equipment Details

    5.1.1   Lease Agreement

    NBN Co Limited will enter into two (2)x ten year consecutive leases with the land owner.


    In accordance with section 10 of the Sustainable Planning Regulation 2009, the definition
    of a Reconfiguration of a Lot includes:
            (d) dividing land into parts by agreement rendering different parts of a lot
            immediately available for separate disposition or separate occupation, other than
            by an agreement that is-
            (i) a lease for a term, including renewal options, not exceeding 10 years

    The proposed lease term will not require a Reconfiguration of a Lot application to be
    lodged with Council as the terms of the lease will not exceed ten years.

    5.1.2   Equipment to be Installed
    Approval is sought for the use and development of a Telecommunication Facility,
    comprising a 40 m monopole and two (2)x outdoor cabinets (one proposed and one future
    with total base area less than 7.5 m2). The outdoor cabinets will be constructed on
    elevated steel grillage located at the base of the facility within a secure compound which
    measures approximately 70 m2 in area or 10m x 7 m.



    The proposed monopole will feature a circular headframe accommodating two (2)x panel
    antennas (1.18 m    long) mounted at a centreline elevation of 40 m and two (2)x remote
    radio units (0.5 m long) positioned below the antennas. Three (3)parabolic dish antennas
    (1 x 0.3 m, 1 x 0.9 m and 1 x 0.6 m in diameter) will also be installed at approximately 40
    m, 36.5 m and 38 m respectively on the monopole. Please refer to Appendix 3                  -




    Proposal Plans for further details.

    5.1.3   Access and Parking Details

    Access to the property is currently provided via the existing    crossover on   the northern
    property boundary and via Lake Flat Road. The location of the access track can be seen
    on   the attached   drawings within Appendix 3 and     in   Figures 5.1   and 5.2. NBN Co
    proposes to utilise the existing access track to the proposed facility (approximately 180 m
    long) during construction and operation. The existing access track may need minor
    upgrades to meet all weather access requirements.

    The facility and all ancillary components will be constructed over the one title (Lot 2 on
    RP126723). A copy of the title for the subject site is provided as Appendix 2. Plans
    indicating the details of the proposal form part of the documentation of this application.
    The proposed development plans are provided as Appendix 3.




r




    NBN-4NBZ-4POM-5136   -
                             Boreen Point North                                        Page 18

Page 21

NBN-4NBZ-4POM-5136   -
                         Boreen Point North   Page 19


[OCR of page images]
Figure 5.2 — Existing access track (arrowed) looking east towards location of proposed facility

NBN-4NBZ-4POM-5136 — Boreen Point North Page 19

 

Page 22

    The site access is considered to be appropriate given the NBN Co facility will not be a
    significant generator of traffic. Once operational, the facility will require maintenance visits
    approximately once per year, but will remain unattended at all other times. As the facility
    generates minimal trips per year, it is considered that traffic interference will be negligible.

    During the construction phase, a truck will be used to deliver the equipment and a crane
    will be used to lift the equipment into place. Any traffic impacts associated with
    construction will be of a short-term duration and are not anticipated to adversely impact on
    the surrounding road network. In the unlikely event that road closure will be required; NBN
    Co will apply to Council for permission.


    5.1.4 Installation Details


    A total construction period of approximately ten weeks (including Civil works and network
    integration    and    equipment commissioning) is anticipated. Construction                  activities will
    involve four basic stages:

         .     Stage 1 (Week 1)     -
                                        Site preparation works, including field testing, excavation and
               construction of foundations;

         .     Stage 2 (Weeks2,3 and 4)           -
                                                       Construction of the tower;

         .
               Stage 3 (Weeks5 and 6)         -
                                                  Construction of the outdoor cabinets and fences;

         .
               Stage 4 (Weeks 7     -

                                        10) -
                                                Installation of antennas and radio equipment, as well as
               equipment testing.

    Once   operational, the facility will function on a continuously unstaffed basis and will
    typically only require maintenance works once a year, for approximately one day per year.

    5.1.5      Utility Service Details
    Power for the proposed facility will be sourced from an existing network on Lake Flat Road
    approximately 50m away. The conditions of supply are subject to further investigation.
    Please refer to Drawing C2 of the Proposal Plans attached as Appendix 3 for further
    details.


    5.1.6      Construction and Noise

    Noise and vibration emissions associated with the proposed facility will be limited to the
    construction phase outlined above. Noise generated during the construction phase will be
    of   short duration     and     will   be     in   accordance    with   the   standards   outlined   in   the
    Environmental Protection  Regulation 1998 and Environmental Protection (Noise) Policy
    1997. Construction works will only occur between the hours of 7.00am and 6.00pm.


    There will be        some   low level noise from the
                                                      ongoing operation of air conditioning
    equipment associated with the equipment shelter, once installed. Noise emanating from
    the air conditioning equipment is at a comparable level to a domestic air conditioning
    installation, and will generally accord with the background noise levels prescribed by
    Australian Standard AS 1055.




r




    NBN-4NBZ-4POM-5136      -
                                Boreen Point North                                                   Page 20

Page 23

5.2    Site Selection
The proposal site was selected as it met the NSN Co coverage objectives. As discussed
in Section    3, a number of candidates were examined within the search area which
resulted in the chosen candidate at 153 Lake Flat Road, Soreen Point. Furthermore, the
reasons for   selecting this site are as follows:
   .   The site is appropriately located within        a    rural   area   which is characterised    by
       agricultural    properties, heavily      vegetated     areas    and     large   rural-residential
       allotments;

   .   The site has already been significantly modified and contains similar infrastructure
       such as the energex electricity network, which runs from north to south through the
       property (approximately 20 m east of the proposed facility);
   .   The existing use of the site for forestry and logging purposes would                     not be
       compromised by the proposed facility;
   .   The proposed location provides an adequate separation distance from community
       sensitive land       uses   and is located in   proximity to only three (3) residential
       dwellings within a 500 m radius;
   .   The proposed facility is located a sufficient buffer distance from environmentally
       sensitive locations (approximately 900 m from the edge of Lake Cootharaba) and
       no   signifi~nt vegetation removal will be required;
   .   The location  provides line of sight to other planned sites in the NSN wireless
       network specifically Soreen Point, Coondoo West and David Cootharaba (Davis
       Road Cootharaba); and

   .   The  siting of a Telecommunication Facility             on    this site will    meet   coverage
       objectives for the area; and
   .
       V!sual impact will be minimised given the presence of mature vegetation
       surrounding the site which will assist with visually integrating the monopole within
       its surroundings and reducing the visual dominance of the structure.




NBN-4NBZ-4POM-5136     -   Boreen Point North                                                 Page 21

Page 24

    6.0            CURRENT PLANNING
                   CONTROLS
    6.1      Commonwealth            Legislation            The Telecommunications Act
    1997

    The Telecommunications Act 1997 has been operative since 1 July 1997. This legislation
    establishes the criteria for ’low impact’ telecommunication facilities. If a proposed facility
    satisfies the requirements of a ’low impact’ facility, the development is exempt from the
    planning approval process.

    Further clarification of the term ’low impact’ is provided in the Telecommunications Act
    1997 and the Telecommunications (Low Impact Facilities) Determination 1997, which was
    gazetted subsequent to       the Act.       The   Telecommunications      (Low Impact Facilities)
    Determination 1997 establishes certain facilities, which cannot be considered low impact
    facilities.


    The proposed facility is not considered to be low impact under the definitions contained in
    the Commonwealth legislation as it involves the construction of a new tower. It is therefore
    subject to the Sustainable Planning Act 2009 and requires development approval under
    the provisions of the Noosa Plan 2009.




    6.2      State Legislation        -
                                          Sustainable Planning Act 2009

    The Sustainable Planning Act 2009 (the SPA) is the legislation that governs planning in
    Queensland.    The   SPA      seeks    to     achieve   ecologically   sustainable   outcomes   for
    development within Queensland by coordinating and integrating planning mechanisms at
    local, regional and state levels, managing the effects of development on the environment,
    and managing the process by which development takes place.


    Where a Telecommunication Facility is not considered a low-impact facility, it is subject to
    the provisions of the relevant local government planning provisions.


    Therefore, because the proposed facility is not ’low-impact’ as the proposal involves the
    installation of a 40m Tower; the provisions of the Planning Scheme apply. This
    development report has been compiled to accompany an Impact Assessable application
    to Sunshine Coast Regional Council under the provisions of the Noosa Plan 2009. The
    provisions of the Planning Scheme are assessed in Section 7.0 below.


    6.3      State Legislation        -

                                          Vegetation Management Act 1999
    The Vegetation Management Act 1999 (VMA)is the legislation that regulates vegetation
    management and the clearing of native vegetation in Queensland. The VMA, managed by
    the Department of Natural Resources and Mines (DNRM),regulates clearing, and how it
    must be undertaken to meet the requirements of the law.


    Clearing for some activities is exempt. This includes most routine activities like fence lines,
r
    yards, firebreaks and burning off. The clearing of native vegetation (identified on Regional
    Ecosystem and Remnant Maps or Regrowth Vegetation Maps and PMAVs) for a MCU
    however, is not considered an exempt activity.




    NBN-4NBZ-4POM-5136   -
                             Boreen Point North                                              Page 22

Page 25

Therefore clearing of remnant vegetation identified on a regional ecosystem or remnant
map, for a MCU on freehold land can only be carried out if a permit is granted by DNRM,
which               assesses the            application against the regional vegetation management codes. No
permit is required to clear regulated regrowth. However, the department must be notified
of the intended clearing in compliance with the regrowth vegetation code.


6.3.1                Regrowth Vegetation

Under the VMA the subject site is mapped                                       as   containing a small area of High Value
Regrowth Vegetation that is classified as containing ’Of Concern Regional Ecosystems’
.




and two    ’Regrowth Watercourses (Stream Order 1)’ (refer to Figure 6.1 below and
Appendix 5 Environmental Searches). In accordance with the Regrowth Vegetation
                                 -




Code a Regrowth Watercourse classified as Stream Order 1 requires a minimum stream
protection distance of 10 metres. The proposed development will not require a permit or
notification to the DNRM as, it is does not require removal of any vegetation and is located
approximately 1.3 km from the mapped regrowth vegetation and approximately 300 m
from the closest regrowth watercourse.




              r’
                       \
                                                                                                     v
                           ..




      fg \_                           ’-       _.t=~--’-

      ,


      t




                       -~

                                --,
                                   "




                        /r")
     Legend:
     IiQUl lleaetatlon Management AI;t Essential AeglOWlh
           Halihl with "".m~lelabel numbGt
     ~ Great Ilarrie, Reel Wetland Proteetion Area                                                                        II

     o ’Hiah VIIlue revrowth vegetation cont8ining
           Erilangered re9i nul eco..,.tems                                                                         ’\.
     o I1lg11 1I1lItJe regrowth veget lon cont8ft1111ll
           Of       m reg.lonal """,yslems

     o High velue regrowth vegetation that is .
           I  st Concern region ecosystem

     r-I           Remnant V     etation
                   (Reier to tll Vegft tlMaIlaaeMent Act RegIonal
          .




                   Ecosystem.""RamilaJtt Map ."0avalable 110m the
                   =~=,~’i:i:r:,’:~i~::ct..::~=::a~t’D.1Mnt
                   NOfHemnant                                                                        tp
                                                                    Regrowth Vegetation Map (DNRM)
                                                                    :




    NBN-4NBZ-4POM-5136                     -   Boreen Point North                                               Page 23

Page 26

    6.3.2 Remnant Vegetation

    Under the VMA, the subject site is     mapped as predominantly ’Plantation Forest’ and
    containing small portions of Remnant Vegetation that is an ’of concern’ regional
    ecosystem and Remnant Vegetation that is a ’least concern’ regional ecosystem (refer to
    Figure 6.2 below). Parts of this vegetation are also identified as being Essential Habitat.
    The proposed development will not require a permit or notification to the DNRM as, it is
    located in a cleared area, approximately 300 m from the assessable vegetation, and the
    proposal does not require removal of any significant vegetation.


                                                                     _/

                                                                            ,/




.
~




                                                                                            .~’ :   ~"~’




       _ Remnant vegetation conrsi1lng endangered
         regional ecosystems
       _ Remnant vegetation containing of concern
         regional ecosystems
       ..Remnant vegetation that is a least concern
                 regional ecosystem
       CJ        Plantation Forest

       c:::::J   Dam or Reservoir

       c::J      Remnant Veget tion

       CJ        PMAV Category X area

       E::] Vegetation Management Aet Essential Habitat
                 For further Information on VMA Essential Habltot.
                 please seethe attached VMA Essential Hobi’.! map.




    6.4          State Planning Policy Framework

    A State Planning                  Policy (SPP)is a statutory instrument developed by the Queensland
    State Government under the Sustainable Planning Act 2009 (or the former Integrated
    Planning Act 1997) on matters of State interest. SPPs apply when development is
    assessed, land is designated for community infrastructure, and when proposed                      new

r
    planning schemes are made or amended under the SPA. The SPP’s below are current.
    State planning policies developed under the Integrated Planning Act 1997 remain current
    under the Sustainable Planning Act 2009. There are currently twelve (12) active SPPs,
    one   (1)of which apply to the proposed development, as demonstrated in Table 6.1 below.




    NBN-4NBZ-4POM-5136                   -
                                             Boreen Point North                                Page 24

Page 27

SPP 1/92   -

               Development and the       N t        plicable
Conservation of Agricultural Land        This SPP lapsed on the 18 December 2012 and has been
                                         replaced by SPP 1/12 Protection of Queensland’s Strategic
                                         Cropping Land (Referto SPP 1/12 below for an assessment).

                                         Notwithstanding this, the site is identified within the Noosa
                                         Plan   2009     Natural Resources Overlay as containing
                                                         -




                                         Agricultural Land Conservation Areas (ALCA). However the
                                         proposed facility is loeated approximately 300 m north of the
                                         mapped ALCA and will not ’impact on the current or future
                                         use of the agricultural land. Furthermore, the establishment
                                         of the proposed facility will occupy a relatively small lease
                                         area (70 m2) of the total ’106 ha site area. The f cility is also

                                         located on the periphery of the site and on cleared land to
                                         avoid interference. Additionally the proposed use for a
                                         telecommunication facility will not affect the agricultural
                                         practices on site as the proposal is not for a habitable or
                                         sensitive land use, and if the facility is no longer operational
                                         the site can be decommissioned and the land rehabilitated.
SPP 1      -

             Development in the          Not Applicable
Vicinity of Certain Airports and         The subject site is located within an area defined in Annex 1
Aviation Facilities                      of the SPP. However, the ’site is not identified within the
                                         Noosa Plan 2009 as being ’Iocated within the Joint
                                         Obstruction      Clearance     Surfaces of the Sunshine              Coast
                                         airport. The proposal will           not have      an   impact on the safe
                                                       of the         facil
SPP 2/02  Planning and Managing
           -




Development Involving Acid Sulfate       The subject site is located within             a   local government area
Soils                                    listed in Annex 1 of the SPP. The site ’is id~ntified within the
                                         Noosa Plan 2009        -
                                                                    Natural Hazard Bushfire & Acid Sulphate
                                         Soils Overlay as containing both High (0 5 m AHD)and Low-




                                         (5   -
                                                  20 m AHD) Potential Acid Suifate Soils. The facility has
                                         been sited within the L w            (5   -
                                                                                       20 m      AHD) Potential Acid
                                         Sulfate Soils area. However, the locati n of the facility will be
                                         on land that is 29 m AHD and associated works will not

                                         involve excavating more than 100 m3 of soil or filling more
                                         than 500 m3 of material as specified in section 2.3 of the

                                         SPP.




NBN-4NBZ-4POM-5136      -   Boreen Point North                                                            Page 25

Page 28

    .....".,.                                                                                                                         ^.

                ~1’~~~’l:.oJ\’:tr.\v."""it’:"1 .,~~-~ r’,-~,
                                                          ,    ~~’J.J."J’,1""’<"""~l\~~.=~::’tE’"’~-’C’r"7t~;J(’’’’’’                       V"’-"~""’’fJ~~._l,’\m’’’~’’’’’T.!:l~tf’’’’~....l    ."
                                                                                                                                                                                                      i FollT
                                                                                                                                     ’.,
    ~/~ ~~,<",iJ.t[~i;:.~,,~ ’::’,’                            .~:"i:"’::’l":’ ,’:{~~~!~~~(;;~;’~~:F’~~~;’.,              .

                                                                                                                                            .’, :_.~~.~:. ::..":~~.;~.~,.- ’{",’~i,;;
       SPP 1/03            -

                               Mitigating the Impacts                      Applicable
       of Flood, Bushfire and Landslide                                    The subject site is in a local government area listed in Annex
                                                                           2 of the SPP. The subject site is also identified on the Natural
                                                                           Hazard: Landslide & Flooding Overlay as containing a ’Flood
                                                                           Hazard Area’ and containing small portions of land ’Subject
                                                                           to minimum floor                   height          In addition the Natural Hazard:
                                                                           Bushfire & Acid Sulfate Soils Overlay identifies the subject
                                                                           site as containing ’Medium Bushfire Hazard Areas’,


                                                                           However, the proposed facility will be located outside of the
                                                                           areasidentified as ’Landslide Hazard Area’, ’Flood Hazard
                                                                           Area’ and land ’Subject to minimum floor height’. The use will
                                                                           not increase the risk or impact of a natural hazard since it is
                                                                           already          cleared           of        significant    vegetation,                          where                    the
                                                                           foundations and earthworks are to follow engineering design
                                                                           standards and                 will      not        use   equipment that significantly
                                                                           increases the risk of fire, The proposed telecommunication
                                                                           facility is not a habitable use and has been sited and
                                                                           designed to minimise the hazards associated with flooding,
                                                                           The proposed development is not listed in A 1.1 Annex 1 and
                                                                           will    not result in             an     increased risk of flood, bushfire                                                 or

                                                                           landslide for the area and therefore complies with the SPP.
       SPP 1/07            -

                               Housing and                                 Not Applicable
        Residential Development                                            This   SPP is not applicable in the assessment of the
                                                                           development application.
       SPP 2/07            -
                               Protection of Extractive                    Not Applicable
        Resources                                                          The site is not located in a Key Resource Area or identified
                                                                           within the Noosa Plan 2009     Natural Resources Overlay as
                                                                                                                               -




                                                                           containing Key Resource Areas.
       SPP 2/10            -
                               South East                                  Not Applicable
       Queensland Koala Conservation                                       The subject site is located within a local government area
                                                                           listed within Section 2.4 of the SPP and is covered by the
                                                                           South East Queensland Koala Protection Area Koala Habitat
                                                                           Values          mapping            as        containing         ’low         to        medium                       value
                                                                           bush land         However, the SPP does not apply to
                                                                                              habitat’.
                                                                           development for a MCU which does not require the removal
                                                                           of vegetation. Additionally, the subject lot is not located within
                                                                           a   Koala Assessable                    Development Area of the SEQ Koala
                                                                           Conservation State Planning Regulatory Provisions (SPRP).
       SPP 3/10            -
                               Acceleration of                             Not Applicable
       Compliance Assessment                                               The    proposal does not seek compliance assessment for
                                                                           Reconfiguration of Lot or Operational Works.
       SPP 4/10            -

                               Healthy Waterways                           Not Applicable
                                                                           The location of the proposed facility is situated on land that is
                                                                           in proximity to Lake Cootharaba. However, the proposed
                                                                           facility will be located approximately 900 m west of the lake
                                                                           and is not likely to have any notable impact on the water
                                                                           body. Stormwater run-off will be minimal due to the small site
                                                                           footprint
       SPP 5/10            -
                               Air, Noise and                              Not Applicable
        Hazardous Materials                                                The subject site is not located within                                 a      Management Area
                                                                           listed under Schedule 5 of the SPP.
       SPP 3/11 Coastal Protection                                         Not Applicable
                                                                           This       SPP        has       been
                                                                                                    suspended by the Draft Coastal
r
                                                                           Protection State   Planning Regulatory Provision (Refer to
                                                                           section 6.5 below).
       SPP 4/11 Protecting wetlands of                                     Not Applicable
        high ecological significance in                                    The proposed site is not located within the Great Barrier Reef
       Great Barrier Reef catchments                                       catchment area.




       NBN-4NBZ-4POM-5136                        -
                                                     Boreen Point North                                                                                                         Page 26

Page 29

          12 Protection of
Queensland’s Strategic Cropping
Land



                                                  in assessi
Temporary SPP 2/12 Planning for           Not Applicable
Prosperity                                The    proposed site is currently used for farming purposes.
                                          Notwithstanding this the current and future capabilities of the
                                          site will not be affected by the establishment of the proposed
                                          facility as the facility will occupy a relatively small lease area
                                          (70 m2) of the total 106 ha of land. The proposed facility has
                                          been intentionally located adjacent to the south eastern
                                          property boundary to minimise interference with farming
                                          activities. In addition the proposed facility will provide the
                                          necessary infrastructure and fixed wireless services to
                                          improve the economic growth and long term sustainability of
                                          the Soreen Point area. This SPP is otherwise not applicable
                                          in assessi     the d




6.5       Draft     :.Coastal          Protection              State     Planning         Regulatory
Provision

The Draft Coastal Protection State Planning Regulatory Provision (the draft SPRP) was
released(October 2012) to simplify and streamline planning, assessment and approval
processes for development in Queensland’s coastal zone.


The draft SPRP ensures the Government manages development in Queensland’s coastal
zone  and grows the economy, while                balancing environmental and social resources for
present and future generations.

It will   provide certainty for coastal planning while the state government reviews and
undertakes consultation     on the Queensland Coastal Plan including the State Planning

Policy 3/11: Coastal Protection.

The draft SPRP does not apply in             assessing this development application as it is not
identified as .any of the prescribed types of development applications set out under Part 2,
Section 2.1 (1), namely;
    .     for   impact. ass~ssable development in              a   coastal   management district by     an

          assessment manager
    .     considered   by the chief executive administering the Coastal Protection and
          Management Act 1995 as assessment manager in accordance with the
          Sustainable Planning Regulation 2009
    .     for development in a coastal management district by an agency with jurisdiction
          under the Coastal Protection and Management Act 1995
    .     for a master plan application.




6.6       Regional Plan
The proposed development falls within the south-east Queensland region which is covered
under the South East Queensland                   Regional Plan 2009-2031 (Regional Pian). The
Regional Plan covers Noosa in the north, the New South Wales-Queensland border in the
south, and Toowoomba in the west.




NBN-4NBZ-4POM-5136       -   Boreen Point North                                                 Page 27

Page 30

The  Regional Plan allocates all land into one of three land use categories; Regional
Landscape and Rural Production Area, Urban Footprint and Rural Living Area. These
categories provide the spatial context for the regulatory provisions of the Regional Plan.
The subject site falls within the Regional Landscape and Rural Production Area under the
Regional Plan and is not within the identified Urban Footprint boundaries.

The   Regional Landscape and Rural Production Area identifies land with regional
landscape, rural production or other non-urban values. It protects this land from
inappropriate development, particularly urban or rural residential development.

The proposed development is identified as an urban activity under the Regional Plan and
is generally consistent with the development outcomes for urban activities outside the
Urban   Footprint. Division 2, Section 2.1, Table 2E of the SEQRP SPRP identifies the
referral assessment criteria for Material Change of Use development outside the Urban
Footprint where:

1. A material change of use for an industrial and commercial purpose having a GFA of no
more than    750 m2 on the premises where       -




(a)any incidental retail activity on the premises is no more than 50 m2; and
(b)any associated outdoor area on the premises is no more than 1500 m2.

The proposed facility is compliant with the provisions of the SPRP because the site:
     .   has a total footprint less than 750 m2
     .   will not trigger any incidental retail activity; and
     .   does not contain any outdoor areas on the premises.


In addition, the facility will provide a service for community benefit without compromising
the productive capacity of the site by supporting economy and employment provisions of
the Sunshine Coast area identified by the Regional Plan as follows:
         The small rural hinterland centres and surrounding rural production        areas   will
         continue to play an important role in diversifying the Sunshine Coast’s economy
         and lifestyle. They will also support the long-term sustainability of rural areas. The
         encouragement of home-based businesses and rural enterprises with access to
         high-speed broadband telecommunications provides additional economic and
                                                                         ’

         employment growth opportunities outside the Urban Footprint.


6.7      Referral Agencies
There are no referral agencies applicable to this development.




6.8      Local Government Regulatory Framework

6.8.1    Planning Scheme use definition
The proposed     development is defined within the Noosa Plan 2009 (the Noosa Plan) as
follows:
     .   Primary Use: ’Infrastructure Uses’
     .   Use Class: ’Service and utility’
     .   Use: Type 3 Tower’


Type 3 Tower is defined as: The use of premises for a tower, antennas or mast and
supporting shelter or equipment, in the provision or supply of electricity or
telecommunications. The use excludes facilities deemed to be "Low Impact Facilities"




NBN-4NBZ-4POM-5136     -
                           Boreen Point North                                        Page 28

Page 31

under the Telecommunication (Low Impact Facility) Determination Act 1997, and excludes
power poles. The use includes a telecommunication tower, wind              turbine, high voltage
                                         ’
transmission lines (110kv or greater).


6.8.2   Zoning
This site is withi.n the ’Boreen Point, Kin Kin & Cootharaba       -
                                                                       Rural Zone’ of the Noosa
Plan 2009. The proposed Material Change of Use for a ’Type 3 Tower’ will be Impact
Assessable (Inconsistent) within this zone according to Table 4.6 of the Noosa Plan
2009. Figure 6.3 below indicates the zoning of the site.




  Legend:
  DDetached Housing
  DViUageMix
  D Com inunity Services
  .Industry
  .Rural Settlement
  . Rural
  DOpen Space Re-creali.on
  ~Dpen Space Conservation


6.8.3   Overlays
The subject site is identified on four (4)applicable overlays under the Noosa Plan 2009.
The applicable overlays are as follows:
    .   Biodiversity Overlay    -
                                    the subject site is identified as containing ’Environmental
        Protection Areas’ and ’Watercourses and Drainage Lines’ (Referto figure 6.4)
    .   Natural Hazard: landslide & Flooding Overlay        -
                                                                the subject site is identified as
        containing a ’Flood Hazard Area’ and also contains portions of land ’Subject to
        minimum floor height’. (Refer to figure 6.5)
    .   Natural Hazard: Bushfire & Acid Sulfate Soils Overlay          the subject site is
                                                                          -




        identified as containing both High and low Potential Acid Sulfate Areas, as well as
        ’Medium Bushfire Hazard Areas’. (Referto figure 6.6)




NBN-4NBZ-4POM-5136   -   Boreen Point North                                            Page 29

Page 32

         .       Natural Resources            Overlay   -   the      subject site   is identified   as   containing   an

                 ’Agricultural land Conservation Area’. (Referto figure 6.7)




                                     Watercourses and
                                     Drainage Lines
     [,i:.::] Riparian Buffer Area
     .
     Environmental Protection Area

     .
     Environmental Enhancement Area
     r~~~J KoaIa HabitatArea
     ’;’:.;A;~



                            Figure 6.4: Biodiversity Overlay   -
                                                                   Map OM1.1 (Source: Noosa Plan 2009)




(




    NBN-4NBZ-4POM-5136           -
                                     Boreen Point North                                                      Page 30

Page 33

 Legend:
     Extent<of
  ...
     Flood Map,ping

 -Flood HUl"’iCf A~a
     .
           Area Subject to
      .


           Min Floor Height
                                      .. _            ._,




      Figure 6.5: Natural Hazard: Landsl’ide & Flooding Overlay   Map OM1.3 (Source:Noosa Plan 2009)
                                                                  -




NBN-4NBZ-4POM-5136     -   Boreen Point North                                                    Page 31

Page 34

        Legend:
                  Coastal Protection
         L        Area
               Agricultural Land
         II (ALCA)
               Conservation Area




                                                            ,
f




    NBN-4NBZ-4POM-5136   -
                             Boreen Point North   Page 32

Page 35

7.0)<:,: PLANNING’CONSIDE.RATIONS
This section of the report assesses the proposal against the relevant provisions of the
Planning Scheme which include the relevant codes.
                                                                        .   .




7.1 Desired .Environmental Outcomes

As the proposed         use    is identified   as   Impact Assessable and an inconsistent land use
within the Rural Zone, assessment against the DEO’s of the Noosa Plan 2009 is required.


There ar      twelve (12)categories of DEOs within the Noosa Plan 2009, five (5)of which
are    considered to be relevant to this proposal. Demonstration of compliance with the
relevant DEO’s is contained below.




                                                                    es.

Agr cultural industry is maintained by-                   The subject site is currently used for farming
    ( conserving land for economically viable             purposes,             predominantly forestry and logging.
          and environmentally sustainable                 However, the proposed development will not
            agricultural purposes;                        compromise the capabil"ies or practices of the
      (H) preventing the fragmentation of good            site     or           surrounding      land    uses       as   the
            quality.agricultura1Iand;                     establishment             of    the    proposed     facility   will
      (iii) facilitating the growth :Ofnon-traditional,   occupy    a       relatively small lease area (70m2)of
            though high value, crops which have           the total 106ha of land and is also located on
            minimal impact on the natural                 the periphery of the site on cleared land to avoid
            environment or adjacent crops;                interference.
      (iv) facilitating the growth of non-traditional
            animal husbandry practices such as            The introduction of fixed wireless coverage will
            aquaculture where it does not alienate        enhance the community’s potential in regard to
            good quality agricultural land or have a      economic              wellbeing   and social    growth. Fixed
            detrimental impact upon the                   wireless in Soreen Point North/Cootharaba and
          environment;                                    Soreen Point which is identified                   as a   ’Village
      (v) protecting agricultural pursuits from           Centre’ on the Noosa Plan Strategy Map will aid
           incompatible uses;                             economic and social growth ahd diversification
      (vi) facilitating the growth of farm forestry       within the agricultural sectors of the shire, and
           practices;                                     create        an         opportunity     for   supplementary
      (vH)value adding to farm produce to                 incomes and business pursuits.
           enhance economic viability; and
      (viH)adop.ting water and energy efficient           Therefore the propOsal. is consistent with DEO
                                                          3.1.3
3.1.3 (c)Community Uses and facilities                    Comp
An adequate .range of community services and              The  proposed development is considered an
facilities supporting the physical, safety, artistic      essential community service for residents within
and social needs of the community are equitably           the Soreen Point and Cootharaba locality. The
distributed having regard to the-                         proposed facility will provide improved wireless
      (i) Location and density of housing                 broadband access to remote locations within the
      (H) Location of transport infrastructure            region    to           help    service   current    and    future
      (Hi) Location of business centres                   resident’s needs.
       (iv)Social, economic and demographic
           patterns of Noosa; and                         The use has been appropriately located on the
      (v) Functions of towns and villages                 periphery of the residential areas and adjacent
                                                          to    other    community     services,     including
                                                          significant transport and electricity infrastructure
                                                          and is well removed from community sensitive
                                                          locations. For these reasons the proposal is
                                                          consistent with DEO 3.1.3 (c).




NBN-4NBZ-4POM-5136        -   Boreen Point North                                                                Page 33

Page 36

        3.1.3 (d)Heritage                                        Complies.
        The     indigenous and non-indigenous history,           The proposed          development will be located on
        culture and traditions are reflected in the built        freehold land for which there        are no heritage

        and natural heritage      of Noosa          and    are   items identified.
        preserved for future generations.
                                                                 Therefore the proposal is consistent with DEO
                                                                 3.1.3 (d).
        3.1.3 (g) Open space,             environment      and   Complies.
        conservation functions                                   The  subject       site    is   not   identified     as   being
        Networks of open space and natural habitat,              located    in    anopen space corridor and the
        vegetated lands, and riparian zones along                specific   location of the facility is not within
        watercourses-                                            existing native vegetation as outlined on Map 4
              (i)   Are sensitively managed and protected        Open Space Networks. The proposal is
                       from any adverse impacts, including       appropriately located within a low density rural
                       cumulative impacts, resulting from        area used for agricultural purposes and will not

                      development;                               require vegetation removal. Although the
              (ii) Set Noosa apart from other coastal            proposed facility is located within approximately
                      parts of south-east Queensland by          60 m from the border of the Great Sandy
                      strongly protecting the natural            National        Park,     the   location      is    considered
                       environment                               appropriate as the facility will be separated from
              (iii) Support  the economy        through    the   the National Park by a bitumen road and located
                       tourism industry                          over 350 m from the closest portion of mapped

              (iv) Define the boundaries to or of each of        remnant vegetation within the National Park.
                       the distinct localities of Noosa;         The proposed facility is otherwise appropriately
              (v) Protect water quality, landscape stability     setback from environmentally sensitive areas
                       and biodiversity                          (eg more than 900 m from Lake Cootharaba and
              (vi) Provide      passive,        nature-based     300 m from onsite Remnant Vegetation) and will
                       recreational       and     educational    not require removal of any vegetation.

I                     opportunities;
              (vii)Enhance visual amenity; and                   Additionally, the subject site is heavily vegetated
              (viii)  Provide linkages beyond Noosa’s            by a combination of the pine plantation and
                       boundaries.                               existing mature vegetation which borders the
                                                                 subject site and road network. Onsite and
                                                                 nearby vegetation will provide significant
                                                                 screening. The facility has been designed as a
                                                                 slim line monopole, which can be colour
                                                                 matched to the surrounding vegetation.


                                                                 The introduction of fixed wireless coverage will
                                                                 enhance the community’s potential in regard to
                                                                 economic wellbeing and social                 growth      of the
                                                                 wider Noosa area. Fixed wireless in the Soreen
                                                                 Point and Cootharaba             area   will aid economic
                                                                 and social growth and diversification within the
                                                                 tourism sectors of the shire.


                                                                 The proposal is set back on a private property
                                                                 and will not adversely impact or remove
                                                                 opportunities for recreational or educational
                                                                 facilities to occur. There are no other significant
                                                                 conservation areas present within the subject
                                                                 site.   For      these     reasons      the        proposal    is

!   \
                                                                 consistent with DEO 3.1.3 (g).

1
                                                                                            "




        NBN-4NBZ-4POM-5136        -
                                      Boreen Point North                                                              Page 34

Page 37

                                                      ,        ,


                                                          .   ...




3.1.3 (I)Infra!?tructure and services           Complies.
(i) The efficient provision and use of services The proposed use’ for a telec,ommunications
such     as      water,    sewerage,    power, facility is identified as an infrastructure’service
telecommunications and waste disposal, caters as per DEO 3.1.3 (I).’ The locality of Boreen
for the needs of residents and visitors, relative               Point North/Cootharaba has been identified for
to their location within Noosa                                  development of       a   new      facility    to    provide
(ii) the ongoing viability of existing infrastructure           broadband  services to residents, visitors and
uses and     facilities are protected from the                  businesses within the area. The facility will serve
impacts of future development.                                 as a key link in the NBN network, transmitting

                                                               ,and receiving information between the Boreen
                                                               Point Facility, Condoo West Facility and David
                                                               Cootharaba Facility (Davis Road Cootharaba).


                                                                To minimise .amenity impacts, the facility has
                                                                been     appropriately   co-located
                                                                                                  with existing
                                                                infrastructural   uses   in   the
                                                                                              surrounding area
                                                                including powerlines and poles.

                                                                The siting of this facility has been           a   strategic
                                                                and  comprehensive process undertaken to
                                                                provide an efficient and high quality service to
                                                                the community, whilst minimising        potential
                                                                impacts on the environment.

                                                                Existing infrastructure uses within the area will
                                                                not be  impacted by the development. Instead
                                                                the     proposed       facility   will   provide
                                                                telecommunications services and infrastructure
                                                                and thus an opportunity for other mobile phone
                                                                carriers to collocate which         will     increase the          "




                                                                efficient  provIsion      of      telecommunications
                                                                services in the Boreen Point and Cootharaba
                                                                area.



                                                                For these reasons, the proposal is considered to
                                                                comply with the intent of DEO 3.1.3 (I).



7.2 Applicable Codes

This section contains the applicable codes for the proposed development. The Noosa Plan
2009 sets out the Codes and those of which are applicable to this application are outlined
hereunder;
        .    Boreen Poirit, Kin Kin & Cootharaba Locality Code
        .    Infrastructure Uses Code
        .    Earthworks Code
        .
            Landscaping Code
        .   Driveways and Carparking Code
        .   Biodiversity Overlay the subject site is identified as containing ’Environmental
                                       -




            Protection Areas’ and ’Water courses and Drainage Lines’ (Referto figure 6.4)
        .   Natural Hazard Overlay: Landslide & Flooding Overlay          the subject site is -




                                                                                                                               ,   \

            identified as containing a ’Flood Hazard Area’ and also contains portions of
            land ’Subject to minimum floor height’ and the Bushfire & Acid Sulfate Soils
            Overlay     the subject site is identified as containing both High and Low
                        ._



             Potential Acid Sulfate Areas, as well                      as   ’Medium Bushfire Hazard Areas’.
             (R~fer to figure 6.5 and 6.6)
        .    Natural Resources Overlay       the subject site is identified as containing an
                                                  -




             ’Agricultural Land Conservation Area’. (Refer to figure 6.7)



NBN-4NBZ-4POM-5136      -    Boreen Point North                                                                Page 35

Page 38

.
    I




        7.2.1 Boreen Point, Kin Kin & Cootharaba Locality Code

        A ’Tower’ in the Boreen Point, Kin Kin & Cootharaba Locality is assessable against the
        Boreen Point, Kin Kin & Cootharaba Locality Code. The Overall Outcomes for the Boreen
        Point, Kin Kin & Cootharaba Locality which         are   relevant to the current   proposal are
        addressed below.


        a) New uses and works are located, designed and managed to-
           i. be compatible with other uses and works;
          ii. maintain the safety ofpeople and works;
         iii. avoid significant adverse impacts on the amenity enjoyed by users of other
              premises, including impacts on acoustic and visual qualities; and
         iv.  avoid significant adverse effects on the natural environment, including native
              habitat removal, fragmentation and attrition;


        b) The remote setting, small scale village focus, agricultural and natural environmental
            values of the locality are maintained and enhanced;


        c) The rural and bushland character and lifestyle enjoyed by residents and visitors is
            retained;

        d) Rural lands are protected and made available for sustainable Agricultural Uses;

        e) Agricultural Uses provide for appropriate value adding on site, where amenity impacts
                can be avoided;



        f) The natural environmental and cultural heritage values of the locality are well conserved
        and well managed, including-


          i.       Cooloola section of Great Sandy National Park, Cooloothin Conservation Park, Mill
                   Point, Borg Park, the Kin Kin Junction Arboretum and Wahpunga School Park;
          ii.      the riparian zones of the Noosa River, Cooloothin Creek, Kin Kin Creek, its many
                   tributaries and other watercourses;
         iii.      Lake Cootharaba and its riparian zones; iv Woondum, Toolara and Ringtail State
                   Forests;
         iv.       the Kin Kin Memorial School ofArts, Country Life Hotel, St Luke’s Church, Kin Kin
                   Junction Uniting Church, Kin Kin State School, Kin Kin Masonic Lodge, Former Kin
                   Kin Post Office, Kin Kin General Store, Former Kin Kin Junction State School
                   (sportsground clubhouse), Former ES & A Bank and Residence, ’Bangunyah’
                   Private Residence, and Former w.o. Francis House amongst others;


        g) Areas used or suitable for rural or extractive uses are protected from land uses which
        would impact on the utilisation of the extractive resources;


        h) Residential development, including short stay visitor accommodation in the form of bed
        and breakfast accommodation, is of a scale consistent with its natural and rural setting and
        is focused on the rural villages of Kin Kin and Boreen Point;


        i) Pomona Kin Kin Gympie Road, Sister Tree Creek Road, Cootharaba Road, Dr
                      -           -




        Pages Road, Junction Road, Kinmond Creek Road, Main Street, Lake Flat Road,
        McKinnon Drive, Neusavale Road, Laguna Street and Louis Bazzo Drive, are protected as
        part of the major road network.




        NBN-4NBZ-4POM-5136        -   Boreen Point North                                      Page 36

Page 39

  j) The function, safety and visual amenity of the major road network are protected and
  enhanced;

  k) Open space networks are protected and enhanced to provide recreational,
  environmental and aesthetic amenity opportunities across the locality;


  I) Kin Kin village and Boreen Point village are the urban focal points, supporting the only
  urban settlement in the locality, and consolidated through the provision of an appropriate
  level of service to residents of the locality;


  t) For the Rural Zone-rural land is protected and appropriately managed such that the
  scenic and environmental values, the distinct rural amenity and agricultural productivity of
  the locality are preserved and are not adversely impacted as a consequence of
  development on or adjacent to that land;

  Compliance
  Development for a ’Tower’ is recognised as an inconsistent land use within the Boreen
  Point, Kin Kin & Cootharaba Locality Rural Zone. However, the proposed subject site is
                                              -




  considered appropriate to accommodate the proposed facility whilst minimising potential
  visual and amenity impacts. In order to achieve this, a comprehensive site selection
  process was undertaken prior to identifying a preferred site for the development of a new
  facility. This process involved consideration to not on meet the coverage objectives, but
  also minimise visual and amenity impacts to the surrounding area.


  The facility is considered to be appropriately located with other compatible uses and works
  as the subject site is predominantly used for pine tree harvesting and logging and contains

  existing infrastructure including the energex corridor of powerline and poles which runs
  from north to south through the centre of the subject site (approximately 20 m east of the
  proposed facility). Fixed wireless coverage in the Boreen Point North and Cootharaba area
  will also aid economic development through potentially increasing business growth and
  education potential. As previously stated the Boreen Point North Facility is an essential
  wireless hub site for the larger network as it can obtain line of site to the other wireless
  facilities located further away where a 30 m monopole in the location of Boreen Point
  cannot. The site will connect the Boreen’ Point north facility, which provides service to the
  township identified as a identified as a ’Village Centre’ on the Noosa Plan Strategy Map,
  back into the fibre network and therefore this facility will provide benefits to both the
  Boreen Point North/Cootharaba and Boreen Point areas.


   Significant areas of mature vegetation on site and within the surrounding area which will
   provide screening benefits in all directions from the adjacent properties, transport routes
   and recreational users of Lake Cootharaba. Existing vegetation in the surrounding area
   will mitigate impacts on multiple views as follows:
      .     It is anticipated that the headframe of the facility will only be seen above the
            existing tree canopy when viewed by recreational users of Lake Cootharaba, as
            there is a 900m buffer of dense vegetation (where the tallest tree is 25m high)
            separating the facility from edge of Lake Cootharaba;
:.:’  .     When viewed from Lake. Flat Road the facility will only become intermittently
            visible at a few minor clearings in the vegetation which aligns with the road
          network; and
      .   The existing vegetation bu,ffer aligning the northern lot boundary will separate and
          screen the   facility from the closest residential dwellings situated north east of the
          facility.

  The current site is considered to demonstrate an appropriate balance of the above overall
  outcomes whereby the facility has been appropriately located within a predominantly low




  NBN-4NBZ-4POM-5136     -
                             Boreen Point North                                         Page 37

Page 40

    density rural area and will provide improved network access to remote locations within the
    region. In conjunction with the natural vegetation screening, the proposed location also
    provides an adequate separation distance from community sensitive land uses and
    residential dwellings to assist in minimising the visual obtrusiveness of the facility as
    follows:
       .    Sited on the periphery of the concentrated residential dwellings (aligning Kildeys
            Road)and over 2 km from the Boreen Point township;
       .    Located within proximity to only (3)residential dwellings within a 500 m radius; and
       .    Setback from all public open space areas including but not limited to;
                  o    More than 900 m from the edge of Lake Cootharaba
                  o    More than 2.3 km from Boreen Field Park
                  o    More than 2.6 km from Boreen Point Foreshore Park


    While it is acknowledged that the proposed facility will be an addition to the locality; it will
    not obstruct any significant views or landmarks in the community. This is because the
    location of the facility and wider vicinity of the area is not identified as containing any
    significant areas, viewpoints or movement corridors in the Planning Scheme maps, namely
    as follows:

            .     The subject site is not identified on the Strategy Plan, Noosa Trail Network Map
                  or   Transport Map as being located adjacent to or within vicinity to a Major Road
                  Network;
            .     The    subject site is not identified on the Noosa Trail Network Map as being
                  located adjacent to or within vicinity to any Existing or Future Trail Network;
            .     The    subject    site   is   not   identified   on   thePathways and Trunk Network
                  Infrastructure     Map    as   being    located   within proximity of any pathways or
                  bike paths; and
            .     The    subject site is not identified on the Heritage Overlay as being located
                  within proximity to any heritage sites or character areas.


    In addition, visual impacts will be further mitigated by the slimline monopole design and
    being   colour matched to the  surroundings (if requested by Council). Therefore it is
    considered that the proposed facility will be effectively screened from nearby residential
    dwellings and other scenic vistas and views from the surrounding area. Refer to Section
    8.1 for further visual assessment.


    The proposed facility has been appropriately located within               a   low density rural area and
    will not adversely impact the rural zone as the facility has been  intentionally located on
    private rural land to avoid areas of significant natural resources and minimise potential
    environmental impacts associated with the development. Although the proposed facility is
    located approximately 60 m from the border of the Great Sandy National Park, the location
    is considered appropriate as the facility will be separated from the National Park by a
    bitumen road .and located over 350 m from the closest portion of mapped remnant
    vegetation within the National Park. The proposed facility is otherwise appropriately
    setback from environmentally sensitive areas (eg more than 900 m from Lake Cootharaba
    and 300 m from onsite Remnant Vegetation) and will not require removal of any
    vegetation.

’   The  subject site is not identified as being located in an open space corridor and the
    specific location of the facility is not within existing native vegetation as outlined on Map 4
    Open Space Networks. The establishment of the monopole on the subject site will not
    affect the farming capabilities of the site as it will occupy a relatively small lease area
    (70m2) of the total 106ha of land and is located on the periphery outside the area of
    productive land.




    NBN-4NBZ-4POM-5136       -
                                 Boreen Point North                                                Page 38

Page 41

For these reasons the proposal is considered to comply with the Overall Outcomes of the
Soreen Point, Kin Kin & Cootharaba             Locality. Further compliance with the Specific
Outcomes and Probable Solutions is included in Appendix 4             -
                                                                          Code Table Assessment.




7.2.2 Infrastructure Uses Code

A ’Tower’ is considered       as an   Infrastructure Use within the Noosa Plan 2009 and is
therefore assessable ag~inst the Infrastructure Uses Code. The overall outcomes for the
Infrastructure Uses Code are contained below.


14.37.2
   a) Residents and visitors have access to adequate levels of infrastructure to meet
      their needs;

   b) Infrastructure Uses do not detract from the visual amenity of the major road
      network nor on the rural or residential amenity enjoyed by residents of and visitors
         to Noosa;


   c) Facilities are co-located where appropriate and practical;

   d) Infrastructure uses are energy efficient;

   e) Infrastructure Uses do not pose a threat to public safety;

   f)    The natural character and environmental values of Noosa                are   protected from
         adverse impacts associated with Infrastructure Uses; and


   g) Convenient,      comfortable     and     safe   access   is   provided   with   the   design of
         infrastructure uses.


Compliance
The  proposed telecommunications facility is considered to be appropriately located in
order to provide the Soreen Point North and Cootharaba locality with essential
communication services, whilst mitigating potential visual and amenity impacts. The
Soreen Point North Facility is an essential wireless hub site for the larger network as it can
obtain line of site to the other wireless facilities located further away where              a   30   m

mOf)opole in the location of Soreen Point cannot. The site will connect the Soreen Point
north facility, which provides service to the township identified as a identified as a ’Village
Centre’ on the Noosa Plan Strategy Map, back into the fibre network and therefore this
facility will provide- benefits to both the Soreen Point North/Cootharaba and Soreen Point
areas.



The introduction of fixed wireless coverage will enhance the community’s potential in
regard to economic and social growth by providing equitable high speed and reliable
internet and communications, not currently provided throughout rural areas. Fixed wireless
coverage in the Soreen Point North and Cootharaba area will aid economic development
through potentially increasing business growth, increased education potential and
opportunities for residents/farmers to pursue supplementary incomes through alternative
                                                                                                          I   ’




business pursuits; ultimately improving the long term sustainability of Soreen Point and
Cootharaba. Additionally, the introduction of a telecommunication facility will create an
opportunity for other carriers to co-locate.

The proposed facility comprises a 10m x 7 m lease area to be located in the southern
portion of the subject site. It is considered that the facility has been sited appropriately to




NBN-4NBZ-4POM-5136    -   Boreen Point North                                                Page 39

Page 42

    mlnlmlse      detrimental    environmental       impacts. The location of the facility supports
    compliance with the infrastructure code as follows:
        .    The        proposed facility has been appropriately sited              on   the   periphery   of
             concentrated residential dwellings (aligning Kildeys Road) while providing service
             to the targeted dwellings and achieving line of sight to the adjoining facilities;
             The establishment of the          monopole       on  subject site will not affect the
                                                                   the
              agricultural capabilities of the land as it will occupy a relatively small lease area
             (70m2)of the total 106ha of land and is located on the periphery of the site outside
             the area of productive land;
        .    the proposed facility is located a sufficient buffer distance from environmentally
              sensitive locations and no vegetation removal will be required; and
        .    The proposal will have negligible impact on the environmental quality, ecological
             values or the nature in the region as it is located in a modified rural area and does
              not produce any type of discharge or effluent run off.


    The proposed facility is for a 40 m monopole and associated infrastructure. The facility has
    been located and        designed appropriately to minimise detrimental visual impacts. Site
    location and design elements of the proposal that demonstrates compliance visual amenity
    criteria of this Code are as follows:
        .    The proposed       development has been setback over 2 km from the Soreen Point
             Village;
        .    The facility has been located           on a   site surrounded   by heavily vegetated areas
             which will provide significant screening benefits from all areas of Soreen Point, but
             in particular the residential dwellings to the north west, Lake Cootharaba to the
             east, Lake Flat Road and the Soreen Point township; and
        .    The facility has been designed with the minimal required height and as a slim line
             monopole, which can be colour matched to the surrounding vegetation;

    The facility has been      intentionally located within private land for which there is existing
    access   available. The site     access is considered to be appropriate given the NSN Co

    facility will not be a significant generator of traffic and is not anticipated to adversely impact
    on the surrounding road network or residential amenity. The proposed facility will also

    have features aimed at preventing public access, including a secured compound fence
    with a locked gate and warning signs placed around the facility.


I   It is considered the proposed facility is not inconsistent with the character of the area as it
    has been appropriately located in a rural area where similar infrastructure is located, such
    as bitumen roads and the energex power network which runs from north to south through


I   the subject site (approximately 20 m east of the proposed facility) as they provide a
    necessary service.



I   For these reasons the proposal is considered to comply with the overall outcomes for the
    Infrastructure Uses Code. Further compliance with the Specific Outcomes and Probable
    Solutions for the Infrastructure Uses Code is included in                 Appendix 4   -
                                                                                               Code Table

I   Assessment.


    7.2.3 Earthworks Code

I
    The Overall Outcomes of the Earthworks Code are the following               -




I       (a) To ensure that earthworks do not unreasonably impact on the natural environment
           or other properties with regard to         -




           (i)    Land stability (including differential settlement or expansion in reactive

I                 soils);



I   NBN-4NBZ-4POM-5136      -
                                Boreen Point North                                                Page 40

Page 43

                                                                                               .   .


                                                                                               .   .




            (N)      Contamination of land;
            (iii)    Flooding and drainage;
            (iv)     Groundwater, watercourses and wetlands;
            (v)      Loss of native remnant or regrowth vegetation; and

        (b) Earthworks are designed and constructed to be structurally sound.


    Compliance
    The   proposed facility     will   be   located   within   a   lease   area   of   approximately 70m2.
    Earthworks required to construct the facility will be minimal, limited to the- extent required
    to establish appropriate foundations for the monopole and will not result in any adverse
    impacts on land stability, drainage, soil disturbance or existing amenity.

    The proposed telecommunication facility has been setback outside of areas identified as
    ’Flood Hazard Area’ and ’Landslide Hazard Area’ on the Natural Hazard: Landslide &
    Flooding Overlay. Additionally the proposed facility is not for. a. habitable use, will not
    produce effluent run off and. has been sited and designed to mini mise the hazards
    associated with flooding and land stability as follows;
        .  The foundations and earthworks are to follow engineering design standards and
           stormwater dissipation is provided through the proposed gravel compound finish;
        .  The proposed facility will include an elevated steel grillage to raise the equipment
            shelters;
       .    Any discharge points will not affect downstream, upstream or underground streams
            on  any adjoining properties as the facility has been located away from
            watercourses and does not produce effluent run off.


    The proposal is appropriately located within a low density rural area used for agrcultural
    purposes and will not require vegetation removal. Although the proposed facility is located
    within approximately 60 m from the border of the Great Sandy National Park, the location is
.
    considered appropriate as the facility will be separated from the National Park by a bitumen
    road and located over 350 m from the closest portion of mapped remnant vegetation within
    the : National Park. The proposed facility is otherwise appropriately setback from
    environmentally sensitive areas (e.g. more than 900 m from Lake Cootharaba, 300 m from
    onsite Remnant Vegetation and 300 m from the closest Regrowth Watercourse) and will
    not require removal of any vegetation.


    For these reasons, the proposed development is considered to comply with the intent and
    overall outcomes of the Earthworks Code, and further assessment is not considered to be
    necessary.
                                                                                                                 ,   .




    7.2.4 Landscaping Code

    The Code for Landscaping is required to be assessed as part of this application. The
    Overall Outcomes of this code state the following:


       a) retains, reinforces and enhances the natural landscape character of the site,
          streetscape and locality;
       b) retains existing vegetation and other natural features for their ecological, aesthetic
            and cultural values;                      .




       c)   ensures the revegetation and rehabilitation of native wildlife habitat and riparian
          zones to protect and enhance ecological and biodiversity values;

       d) facilitates water management including on-site detention and the efficient infiltration
            of stormwater;




    NBN-4NBZ-4POM-5136    -   Boreen Point North                                                       Page 41

Page 44

             e) enables the establishment of appropriate plantings that are of a scale and density
                commensurate with building height, bulk and scale to buffer development and
                conflicting land uses;
             f) enhances privacy between dwelling units and accommodation units;
             g) accommodates the outdoor recreation needs of dwelling occupants; and\
             h) provides adequate vegetation treatment to steep slopes and unstable landforms.


        Compliance

        The current development does not propose the establishment of additional landscaping.
        Although    the   subject site predominately    contains     pines   trees for timber   harvesting,
        corridors and areas of existing mature remnant and regrowth vegetation existing around
        the proposed facility which are unlikely to be removed. The proposed facility in an area
        which is bordered    by this existing mature vegetation will help reduce visual dominance.
        Additionally, the facility only requires a small footprint area (70m2)and does not require
i   ’
        the removal of vegetation. Additional landscaping to screen the facility is not considered
        necessary.



        Therefore, the proposal is considered to have a minimal impact on the natural landscape
        or built environment as the existing mature vegetation will be maintained and will act as a

        buffer.


        7.2.5 Driveways and Carparking Code

        The Code for    Driveways and Carparking is required to be assessed as part of this
        application. The Overall Outcomes of this code are:

             a) Safe and reasonable access to and from vehicle accommodation and standing
                areas within a property and from the public road is provided;

             b) The safety ofpedestrians and cyclists is protected;
             c) Development reduces the reliance on private vehicles and promotes public and
                nonmotorised transport options;
             d) Carparking spaces and the associated manoeuvring areas provided are designed
                to be safe and functional and meet the reasonable requirements of the particular
                  land use;
             e) Adequate provision is made for the standing, parking, loading and unloading,
                access and manoeuvring of service vehicles within the development site;

             f) Development does not adversely impact on existing public parking;
             g) Adequate monetary contributions are made in circumstances where Council
                considers the provision of external parking will fulfill the parking demand generated
                by the development and will not have an adverse impact on existing public parking;
                  and
             h)   Vehicular access does not impact adversely upon existing landscaping or native
                  vegetation. Settling

        Compliance
    \


I       The car parking requirements in the Code for Driveways and Carparking does not provide
        a   parking requirement for an ’Infrastructure Use’. However, the points below demonstrate
        a   general compliance with the intent of the code:

             .    Access to the     property is currently provided    via the   existing crossover on the
                  northern property boundary and via Lake Flat Road.




        NBN-4NBZ-4POM-5136     -
                                   Boreen Point North                                            Page 42

Page 45

     .   This access track is considered to provide safe and convenient access to meet the
         needs of the maintenance vehicles which will infrequently access the site;
     .Adequate provision has been allocated for service vehicles to access the site and
      park whilst undertaking maintenance works;
     .The proposed development will not increase the number of people living or working
      in the area and does not require the provision of any formal parking; and
     .The site access is considered to be
                                              appropriate given the NBN Co facility will not
      be a significant generator of traffic and is not anticipated to adversely impact on the
      surrounding road network or residential amenity.

For these reasons, the development is considered to comply with the Driveways and
Carparking Code.


7.2.6 Biodiversity Overlay Code
                                                                                                    I
The   subject lot   is identified   ascontaining ’Watercourses and Drainage Lines’ and
                                                                                                I




’Environmental Protection Areas’ within the Biodiversity Overlay. The Overall Outcomes
relevant to the subject site are as follows:

a) The natural resources of the former Noosa Shire are conserved including-
    (i) land which is of scenic, cultural, historical, educational, recreational, scientific,
        ecological, biodiversity, economic, social or aesthetic value;
    (H) soil or landforms such as watercourses, drainage lines, foreshores, dunes and
        steep slopes;
    ()the ecosystem health and quality of the water, land and other natural resources;
         and
     (iv) the extent and condition of native and remnant vegetation, including wetlands and
         areas of significant regrowth of local origin;



b) The biological diversity of native flora and fauna and their habitats is maintained;

c) Wildlife corridors, vegetation links and riparian vegetation are conserved, managed and
rehabilitated to ensure the long term ecological viability and sustainability of native flora
and fauna species;


d) Activities that may impact upon vegetation are managed so as to minimise the impact
upon Noosa’s natural resources, including-
    (i) the ecological values of water catchment areas;
    (H) that part of the natural environment that may be environmentally harmed by
         vermin, pests, noxious plants or threats such as fire, development and
         inappropriate land management; and
    (Hi) vistas and scenic amenity of the landscape;

f)   The replanting or rehabilitation of degraded ecosystems and habitat is achieved;


f) In the case of urban areas, urban amenity, quality of life and ecosystem health is
maintained and enhanced.


Compliance
The proposed facility has been located within a private rural property which is currently
used for farming purposes and outside of areas mapped as ’Riparian Buffer Area’, ’Koala
Habitat Area’ and ’Environmental Enhancement Area’ on the Biodiversity Overlay.


Although the subject site is mapped as containing ’Watercourses and Drainage Lines’ and
’Environmental Protection Areas’, the location of the facility is well removed from these




NBN-4NBZ-4POM-5136    -   Boreen Point North                                          Page 43

Page 46

        identified natural areas and within a significantly modified rural environment used for pine
        tree harvesting and logging. Additionally, the development will occupy a small footprint
        within the site (70 m2) and will involve only minor excavation works during construction of
        the facility. As such, the development will not impact on existing ecological processes or
        natural drainage systems within the site as it is setback over 300 m from the closest
        regrowth watercourse and will not involve the removal of any vegetation.

        For these reasons, the proposed development complies with the Overall Outcomes of the
        Biodiversity Overlay Code, and further assessment is not considered necessary.


        7.2.7 Natural Hazards Overlay Code

        The subject site is identified as containing ’Flood Hazard Area’ and ’Subject to minimum
        floor height’ within the Landslide & Flooding          Overlay (refer to Figure 6.5) as well as
        ’Medium Bushfire Hazard Area’ and’ High          -
                                                             Low Potential Acid Sulfate Areas’ within the
        Bushfire & Acid Sulfate Soils Overlay (refer to Figure 6.6). The Overall Outcomes relevant
        to the subject site are as follows:


             a) development in areas at risk from natural hazards is compatible with the nature of
                the natural hazard;
             b) the risk to people, property and the natural environment from natural hazards is
                minimised;
             c) development does not result in a material increase in the extent or severity of
                natural hazards; and
             d) for acid sulfate areas-the generation or release of acid and associated metal
                contaminants into the environment is avoided


        Compliance
        The proposed    facility is identified on the Natural Hazard: Bushfire & Acid Sulfate Soils
        Overlay as being located within a ’Medium Bushfire Hazard Area’. However, the proposed
        use will not increase the risk or impact of this natural hazard since the proposed site it is

        already cleared of substantial vegetation. Furthermore, the foundations and earthworks
        are to follow engineering design standards and the facility will not include materials that

        significantly increase the risk of fire. In addition, no buildings are proposed and the
        proposed Telecommunication Facility is not a habitable use that will result in an additional
        increase in the number of people living, working or congregating in the Bushfire Hazard
        Area.


        The site is identified within the Natural Hazard Bushfire & Acid Sulphate Soils Overlay as
        containing both High (0 5 m AHD) and Low (5 20 m AHD) Potential Acid Sulfate Soils.
                                      -                        -




        The proposal for a 40 m monopole has been sited within the Low (5 20 m AHD) Potential
                                                                                  -




    \
J
        Acid Sulfate Soils area and located on land at approximately 29 m AHD natural ground
        level. The proposed development complies with the overall outcomes of the Natural
        Hazards Overlay Code as it is not anticipated to involve excavation of more than 100 m3 or
        filling of more than 500 m3 nor is excavation expected to be undertaken below 5 m AHD
        natural ground level. As such, the proposed development will not result in the disturbance
        of acid sulfate soils and reflects the State Planning Policy 2/02 Planning and Managing
1
        Development involving Acid Sulfate Soils.
I   I


        The proposed facility will also be located outside of the areas identified on the Natural
        Hazard: Landslide & Flooding Overlay as ’Landslide Hazard Area’, ’Flood Hazard Area’
        and land ’Subject to minimum floor height’. The proposed telecommunication facility is not
        a   habitable   use   and will have minimal run-off. Therefore the proposed       facility will not
        increase the risk of flooding and reflects the State Planning Policy 1/03 Mitigating the
        Impacts of Flood, Bushfire and Landslide.



        NBN-4NBZ-4POM-5136      -
                                    Boreen Point North                                          Page 44

Page 47

For these reasons, the proposed development complies with the Natural Hazards Area
Code and further assessment is not considered necessary.




7.2.8 Natural Resources Overlay Code

The subject site is identified as containing ’Agricultural Land Conservation Areas’ within
the Natural Resources Overlay (refer to Figure 6.7).The Overall Outcomes relevant to the
subject site are as follows:

a) for agricultural land conservation areas-
  I.     the use of good quality agricultural land for agriculture is not adversely affected by
         other forms of development; and
 II.     uses that are able to be located elsewhere do not locate within agricultural land

        conservation areas;
                                                                                                    ,   t




Compliance
The site is identified on the Natural Resources Overlay as containing Agricultural Land
Conservation Areas (ALGA). However, the proposed facility is located approximately 300
m   north of the ALGA and not located within a Coastal Protection Area. Furthermore, the
establishment of the proposed facility will occupy a relatively small lease area (70 m2) of
the total 106ha site   area      and has been located   on   the   periphery of the site to avoid
interference. The proposed telecommunication facility will not affect the current or future
agricultural practices on site as the proposal is not for a habitable or sensitive land use. If
the facility is no longer operation l the site can be easily decommissioned and the land
rehabilitated. As such, the proposed development will not result in the disturbance of
agricultural land conservation areas and reflects the State Planning Policy 1/12 Protection
of Queensland’s Strategic Cropping Land.




                                 .,         ..


                             .   ...   ..   .   .




NBN-4NBZ-4POM-5136   -
                         Boreen Point North                                             Page 45

Page 48

     8.0            OTHER                            ENVIRONM"ENTAL
     CONSTRAINTS AND OPPORTUNITIES
I
     8.1    Visual Amenity and Setting
I    NBN has endeavoured to strike a balance between providing services and minimising any
     visual impact on the community and local environment. Telecommunication facilities need
     to be located in or near the area for which    they are designated to provide or improve
     coverage. This particular location was partly chosen as it provides a significant element of
     separation from nearby sensitive land uses whilst meeting the required radio frequency
     (RF) coverage for the Boreen Point North and Cootharaba area. The height of the
,I   proposed tower is the minimum required to achieve NBN RF objectives.

     The wider area of Boreen Point North and Cootharaba is characterised by large farming
     properties, heavily vegetated areas and large rural-residential allotments. The subject site
     is located approximately 2km north west of the Boreen Point township. The subject
     property is currently used for farming purposes, chiefly forestry and logging. The proposed

I    facility will comprise a 7m x 10m lease area to be located adjacent to the south eastern lot
     boundary of the site. Figure 8.1 below demonstrates the characteristics of the subject site.


I
I
I


I
I
I
I
I
     Although the subject site predominantly contains pine trees for timber harvesting, there are

I    also corridors and areas of existing mature remnant and regrowth vegetation which are
     unlikely to be removed. Figure 8.2 provides an aerial photograph demonstrating the
     existence of existing mature vegetation in the surrounding area which will provide


I
I    NBN-4NBZ-4POM-5136   -
                              Boreen Point North                                       Page 46

Page 49

screening benefits in all directions from the adjacent properties, transport routes and
recreational users of Lake Cootharaba.



                                                        Vegetation buffer
                                                      screening the facility
                                                         from the closest
                                                       residential dwellings




                                                                                                            I   I




                                                                                                                fI



’Figure 8.2:            a    d surrounds de’monstrating existing mature vegetation in tbe Witter vicinity
    which will provide for visual screening bel"!efits (Source:http://maps.sunshinecoast.qld.gov.au)


As indicated in Figure 8.2 existing mature vegetation aligns Lak               Flat Road and provides       I    ’




a   buffer from Lake Cootharaba which             is located
                                                          approximately 900m east of the
proposed    facility. This separation     distance in
                                                    conjunction with the mature vegetation
corridor (where the tallest trees are approximately 25m in height) will screen the majority
of the facility,from recreational users on Lake Cootharaba. It. is anticipated that the users
of Lake Cootharaba will only see the headframe of the facility above the existing tree
canopy. Additi nally when viewed from Lake Flat Road, the facility will only become
intermittently visible at a few minor clearings in the vegetation along the road. These
fleeting views are not anticipated to be visually obtrusive.

Figure 8.2 alSo illustrates the existing vegetation buffer aligning the northern lot boundary
which will screen the facility from the closest residential dwellings situated to the north of
the facility. This existing vegetation will provide a substantial degree of screening and will




NBN-4NBZ-4POM-5136     -   Boreen Point North                                                  Page 47

Page 50

        assist in minimising the visual appearance/impact of the structure when viewed from the
        closest residential dwelling.


        Figures 8.3 and 8.4 below demonstrates the current appearance of the site as viewed from
        lake Flat Road and the existence of trees which align with the road network. Both views
        illustrate a point in which there is a minor clearing in vegetation along the road network.


\   ,




,
    ,




                                             towards proposed location of the facility (arrowed)from Lake Flat Road
                                        (approximately 180 m separation distance).




,   I




        NBN-4NBZ-4POM-5136   -
                                 Boreen Point North                                                      Page 48

Page 51

                                                                                                            I   I




                     ng north-east towards proposed location of the facility (arrowed)from Lake Flaf Road
                                                                          .




                             (approximately 240 m separation distance).


Figure 8.5 illustrates a view west towards the buffer of mature vegetation aligning with the
road network..and    separating the pr posed facility from the closest residential dwellings
located north west of the proposed facility. When viewed from the nearby residential
dwellings it is anticipated that only the top of the facility will be visible. Furthermore these
views are not anticipated to be visually obtrusive or significantly detract from the natural
landscape and character of the area.




NBN-4NBZ-4POM-5136   -
                         Boreen Point North                                                    Page 49

Page 52

                         sting mature vegetation    igning
                                   benefits to the adjoining properties (looking west)


        In conjunction with the natural vegetation screening, the proposed location also provides
        an   adequate separation distance and setbacks from community sensitive locations which
        will also assist in minimising the visual obtrusiveness of the facility as follows:
             .   Sited on the periphery of the concentrated residential dwellings (aligning Kildeys
                 Road)and over 2 km from the Soreen Point township;
             .   Located within proximity to only (3)residential dwellings within a 500 m radius; and
             .   Setback from all public open space areas including but not limited to;
                    o   More than 900 m from the edge of Lake Cootharaba
                    o   More than 2.3 km from Soreen Field Park

,   ,
                    o   More than 2.6 km from Soreen Point Foreshore Park


        Figure 8.6 below illustrates the view looking north (taken from the ancillary shed) towards
        the existing  powerlines and power corridor which runs from north to south through the
        subject site (approximately 20 m east of the proposed facility). The existing power corridor
        can also be seen in previous Figure 8.2 and demonstrates the facility has been

        appropriately located on a site that contains existing infrastructure.




        NBN-4NBZ-4POM-5136    -
                                  Boreen Point North                                          Page 50

Page 53

                                                                                                                          II
                                                  "   "


                                             .   ....




                                                                                                                          ,I
                                                                                                                  ,       I




                                                                                                                              I

                        ng south towards the existing eriergex electricity n"etwork which runs from north
                                    to south through the subject site.


While it is acknowledged that the proposed facility will be an addition to the locality; it will
not obstruct any significant views or landmarks in the community. This is because the
location of the facility and wider vicinity of the area is not identified as containing any
significant areas, viewpoints or movement corridors in the Planning Scheme maps, namely
as follows;

       .      The subject site is not identified on the Strategy Plan; Noosa Trail Network Map
              or   Transport Map as being located adjacent to or within vicinity to a Major Road
              Network;
       .      The subject site is not identified                  on   the Noosa Trail Network Map as being
              located adjacent to or within vicinity to any Existing or Future Trail Network;
       .      The    subject    site   is   not           identified   on  the Pathways and Trunk Network         ,           I


              Infrastructure     Map    as       being        located    within proximity of any pathways or
              bikepaths; and
       .      The subject site is not identified                  on    the   Heritage Overlay as being located
              within proximity to any heritage sites or character areas.


It is therefore considered the facility has been located and                          designed appropriately to
minimise detrimental visual and environmental impacts. Once established the monopole
will not adversely impact upon the environment or scenic amenity because:
   .   The proposed facility is appropriately located in a rural area that contains man-
       made structures such             as       power lines and sealed roads. In this context, the
       proposed facility is a typical form of infrastructure used                         to   support improved
       telecommunication coverage in rural areas.
    .  The proposed facility is located a sufficient buffer distance from environmentally
        sensitive locations and no vegetation removal will be required;
                                                                                                                      I

                                                                                                                              ’


NBN-4NBZ-4POM-5136       -   Boreen Point North                                                        Page 51

Page 54

              .    The facility has been located  on a site surrounded by heavily vegetated areas

                  which will provide significant screening benefits from all areas of Boreen Point
                   North and Cootharaba, but in particular the residential dwellings to the north west,
                   Lake Cootharaba to the east, Lake Flat Road              and the Boreen        Point North
                   township;
              .    The proposed facility is setback sufficiently from public open spaces within the
                   wider area;
              .    The monopole was selected for the proposal due to its slim line appearance and
                   minimal visual obtrusiveness when viewed from a distance.
              .    The monopole design is deemed to be more appropriate than a lattice tower as it
                   can   bepainted a colour that will provide a degree of visual integration                and
                   camouflage the facility with the surrounding landscape and vegetation

         The proposed facility has been appropriately sited on the periphery of the township and
         located   as far away from residential dwellings as possible whilst still being capable of

         providing service across the township, resulting in a minimal impact on the scenic amenity
         of the area. While it is acknowledged that the proposed facility will be an addition to the
         locality, communication facilities are now an accepted part of the landscape (much like
         powerlines) as they provide a necessary service and essentially contribute to the wellbeing
         of areas such as Boreen Point North and Cootharaba.


         8.2       Heritage
         In order to determine any possible natural or cultural values of state or national
         significance associated with the site, a search was conducted through the relevant
         Heritage Registers (refer to Appendix 5). There are no known items of cultural, historical
    ,)   or environmental      heritage significance located in the vicinity of the proposal site.

         8.3       Electrical Interference and Grounding of the Facility
(
     \
         The NBN fixed wireless broadband network is licensed by the Australian Communications
         and Media Authority (ACMA)for the exclusive use of the OFDMA2400 frequency band. As
         NBN Co is the exclusive licensee of this sub-band, emissions from NBN Co equipment
,I’      within the frequency band will not cause interference.


         Filters also    ensure           facility meets the ACMA specifications for emission of
                                  that each
         spurious signals       outside the NBN  Co frequency allocations. NBN Co will promptly
         investigate any interference issues that are reported.

         The facility is also grounded to the relevant Australian Standards        -
                                                                                       that is, the facility will
         be ’earthed’.


~    I   8.4       Erosion, Sedimentation Control and Waste Management
         All erosion and sediment control mitigation measures will be detailed in construction plans
         and will    comply with the Building         Code of Australia and local Council standards. In
         addition, contractors must comply with the ’NBN Construction Specification’ that requires
         contractors to undertake the necessary erosion and sediment control measures in order to
         protect the surrounding environment. On completion of the installation, the site will be
         restored and reinstated to an appropriate standard. No waste which requires collection or
         disposal will be generated by the operation of the facility.

         8.5       Remnant and Regrowth Vegetation

         In order to determine any existing remnant and regrowth vegetation on site, a search was
         conducted through the relevant environmental searches (refer to Appendix 5). Under the




         NBN-4NBZ-4POM-5136       -
                                      Boreen Point North                                              Page 52

Page 55

                                                                                                               f



VMA the subject site is mapped         containing both Regrowth an Remnant Regional
                                          as

Ecosystems. The proposed development will not require a permit or notification to the
DNRM as it will be located in a cleared area and appropriately set back from the identified
Remnant and Regrowth vegetation.


8.6       Flora and Fauna & Endangered Species

In order to determine any possible Endangered Species associated with the site an EPBC
                                                                                                           I    J
report was obtained (refer to Appendix 5). The EPBC Act Protected Matters Report
illustrates that some endangered species are likely to be present within the 1 km radius
search ring. However, the proposal for a Telecommunication Facility is unlikely to have a
significant impact on any threatened or migratory species in the area.


8.7       Social and Economic Impacts

High quality broadband internet access is a necessary service in modern society. Initially,
small to medium business customers accounted for a significant part of the demand for
broadband technology, but broadband services have now been embraced by the general
public. Usage of broadband services continues to widen as new technologies become
progressively more affordable and accessible for the wider community.

The proposed       development will provide significantly enhanced fixed wireless broadband
coverage to the locality of Boreen Point North. This will be of particular benefit to existing
                                                                                                          ,\
rural businesses and dwellings in the locality.


The new National Broadband Network will provide the community with far greater access
to high quality broadband services. Reliable broadband internet provision             is important to      .~
                                                                                                               \
facilitate the economic growth of communities, and the facility is likely to have significant
social and economic benefits for the local community.


8.8       Public Safety

8.8.1 Radiofrequency Emissions

In relation to public safety and specifically Electromagnetic Emissions (EME)and public
health, NBN        Co operates within       the    operational standards. set by the Australian
Communication qnd Me,dia Authority (ACMA)and Au.stralian Radiation Protection and
Nuclear Safety Agency (ARPANSA). ARPANSA is a Federal Government agency
incorporated under the Health and Ageing portfolio and is charged with the responsibility
for protecting the health and safety of both people and the environment frQm the harmful
effects of radiation (ionising and non-ionising).                                                         ;,    ,



All   NBN    Co    installations   are   designed    and   certified   by qualified professionals    in
accordance with all relevant Australian Standards. This ensures that the NBN Co facility
does not result in any increase in the level of risk to the public. This facility is to be
operated in compliance with the mandatory- standard for human exposure to EME                        -




currently    the   Radio    communications        (Electrom gnetic     Radiation   Human   Exposure)
Standard 2003. The EME Report associated with this s e is included in Appendix 6. The
report shows that the maximum predicted EME level will equate to 0.016% or greater than
4,760 times below the maximum exposure limit. This is substantially less than 1 % of the
maximum allowable exposure limit (where 100% of the limit is still considered to be safe).


Moreover, all NBN Co equipment has the following features, all of which minimise the
amounts of energy used and emitted:

      .   Dynamic/Adaptive Power Control is a network feature that automatically adjusts
          the power and hence minimises EME from the facility.




NBN-4NBZ-4POM-5136      -
                            Boreen Point North                                             Page 53

Page 56

I
I       .
            Varying the facility’s transmit power to the minimal required level, minimising EME
            from the network, and

        .   Discontinuous          transmission,    a   feature   that   reduces   EME    emissions     by
I           automatically switching the transmitter off when no data is being sent.

     8.8.2 Access

I    The proposed facility will have restrictions aimed at preventing public access, including a
     secured compound fence with a locked gate and warning signs placed around the facility.


I    8.9    The Public Interest and the Benefits of Telecommunications

     The proposed NBN Co facility will have significant benefit for residents in the Boreen Point
I    North area. NBN Co believe that the public interest would be served by approval of the
     proposal, providing benefits for enhanced broadband coverage in the area.

I    8.9.1 Other Benefits of Reliable Broadband Services

     There are numerous other benefits of telecommunications connectivity, as follows:

I       .   There are many educational benefits justifying the implementation of the National
            Broadband      Network. Curriculum          and   data   sharing, increased availability   and
            accessibility of research materials, and virtual classroom environments are good
I           examples. Such elements are particularly beneficial within a tertiary education
            context.

        .   Businesses can, through internet usage, increase efficiency through time, resource
I           and  monetary savings. Improved broadband services may effectively                   remove

            physical distance and travel time as a barrier to business.
            Improvements to broadband services may also be of benefit for local employees,
I:
 "
        .



            by enabling telecommuting and home business. The telecommuting trend is
            heavily reliant on access to high quality internet services, and is anticipated to
            continually increase in popularity.
I
     The public benefits of access to high quality broadband have been widely acknowledged
     for many years. Reliable internet access is now more than ever an integral component, so
I    much so that its absence is considered a social disadvantage.


     8.9.2 Consultation
I
     NBN Co is adopting        a   proactive, whole-of LGA approach to consultation for the Fixed
     Wireless Network in the Sunshine Coast region. Following discussions with Council, NBN
I    Co have   designed     a      Communications Plan which outlines the communications and
     consultation approach         supporting the rollout of the NBN Fixed Wireless network in the
     Sunshine Coast LGA.

I    Prior to lodgement of the Development Application to Sunshine Coast Regional Council,
     NBN Co and Aurecon held an Information Session for those residents that will receive the

I    NBN Co services. This involved a high level discussion of the proposed locations, facility
     designs and topographical characteristics and constraints of the area.

     Please refer to   Appendix         7 for NBN       Co’s Communications Plan and all         material
I    advertised to date.



I
I    NBN-4NBZ-4POM-5136    -
                               Boreen Point North                                               Page 54

Page 57

      9.0            C’ONCLUSI’ON

      The   proposed NSN Co facility, comprising a 40 metre high monopole with attached
      antennas and outdoor cabinets has been sited in the most appropriate location whilst
      ensuring adequate coverage is achieved.
                                                                                                       j
                                                    .’.


      The facility has been strategically sited and designed to mlnlmlse visibility within the
      surrounding environment as much as practicable. In this regard the proposal satisfies the
      requirements of the Telecommunications Act 1997, whilst also addressing coverage
      deficiencies within the local area.
4..
                                                                                                   ,   ,

      The proposal is also broadly consistent with the stated objectives of the Noosa Plan 2009.
      It is considered that theproposal will’ provide an important community benefit to the
      Soreen Point North and Cootharaba     area by providing coordinated and open access

      shared   communication infrastructure, and therefore greatly improved fixed wireless
      broadband coverage within the local area.




                                                                                                       ,J




                                                                                                   I
      NBN-4NBZ-4POM-5136   -
                               Boreen Point North                                     Page 55          ,I

Page 58

    Appendix 1
    Transmission Imagery




I
I
I
I


I
I
I
~
I
I
I
I
I
I   NBN-4NBZ-4POM-5136   -
                             Boreen Point North   Page 56

Page 59

NBN Co Fixed Wireless Network   -
                                    Sunshine Coast Regional Council

             Pomona FAN (looking east from Boreen Point)

Page 60

Appendix 2
Copy of Title




NBN-4NBZ-4POM-5136   -
                         Boreen Point North   Page 57


[OCR of page images]
Appendix 2
Copy of Title

NBN-4NBZ-4POM-5136 — Boreen Point North Page 57

Page 61

                                     CURRENT TITLE         SEARCH

                           DEPT   OF NATURAL          RESOURCES AND    MINES, QUEENSLAND
    Request    No:     14374006
   Search Date:        02/08/2012 16:17                                       Title Reference:       14511243

                                                                                   Date   Created:   02/11/1970

   Previous Title:          11860161

                            11901011



   REGISTERED     OWNER



   Dealing No:        702814939       29/07/1998

   GRAEME BERESFORD ARBUCKLE



   ESTATE AND     LAND



    Estate     in Fee      Simple

    LOT   2           REGISTERED      PLAN      126723

                      County of     MARCH                        Parish of NOOSA
                      Local Government: SUNSHINE COAST



   EASEMENTS, ENCUMBRANCES AND                  INTERESTS



          1.   Rights      and    interests reserved to the Crown             by
               Deed    of Grant No.        11211183       (POR 147)
                        (POR 279)
               Deed of Grant No.           11901011       (POR 73)


   ADMINISTRATIVE       ADVICES       -
                                          NIL

   UNREGISTERED       DEALINGS        -
                                          NIL




   CERTIFICATE        OF TITLE      ISSUED      -
                                                    No


                                     **   End       of Current Title   Search      **




   COPYRIGHT    THE     STATE OF     QUEENSLAND          (DEPT OF NATURAL RESOURCES        AND   MINES)   [2012]
   Requested By:       D   APPLICATIONS             SAI GLOBAL




                                                                                                      Page 1/1




Printed by Espreon 02/08/201216:17 PM AEST                          For: LH   Ref: N-4NBZ-4POM-5136-BOREEN P Page 1/1

Page 62

Appendix 3

Proposal Plans




NBN-4NBZ-4POM-5136   -
                         Boreen Point North   Page 58


[OCR of page images]
Appendix 3

Proposal Plans

NBN-4NBZ-4POM-5136 — Boreen Point North Page 58

Page 63

11                                                                                                                                                                                                      Client:




rJ         DATE OF ISSUE
                                                                                                         I ~ I iI I I I I
                                                                                                             1        2
                                                                                                                                                                                                                                            ~
           DRAWING PACKAGE VERSION                                                                       I        I        I
                                                                                                                                                                                                          NBNCo
11         GENERAL
                                                                                                                                                                                                                                     Limited
           4POM-51-36-BPN-T1 I COVER SHEET                                                                   01       02
                                                                                                         I        I        I

11         4POM-51-36-BPN-C1 I SITE SPECIFIC NOTES AND ANTENNA TABLE
                                                                                                         I
                                                                                                             01 I 02
                                                                                                                     I         SITE No: 4POM-51-36-BPN                                                  Client:



           4POM-51-36-BPN-C2

           4POM-51-36-BPN-O
                                  I
                                  I
                                      OVERALL SITE PLAN
                                      SITE SETOUT PLAN
                                                                                                         I

                                                                                                         I
                                                                                                             01

                                                                                                             01
                                                                                                                I

                                                                                                                I
                                                                                                                  02

                                                                                                                  02
                                                                                                                     I

                                                                                                                     I
                                                                                                                                                                                                                              ::II
11         4POM-51-36-BPN-C4
                                  I
                                      SITE ELEVATION AND DETAILS
                                                                                                         I
                                                                                                             01
                                                                                                                I
                                                                                                                  02
                                                                                                                     I                                                                                                        ;iii
                                                                                                                               BOREEN POINT NORTH                                                                  ERICSSON

H          STRUCTURAL

                                                                                                                                                                                                        Client:




1:1                                                                                                                            153 LAKE FLAT ROAD,
                                                                                                                               BOREEN POINT,
1J         ELECTRICAL


                                                                                                                               QLD 4565
I]                                                                                                                                                                                                      Project


                                                                                                                                                                                                        NATIONAL BROADBAND

1~                                                                                                                                                                                                                        NETWORK

                                                                                                                                                                                                        SITE No: 4POM-51-36-BPN
           EME EXCLUSION ZONES                                                                                                                                                                          BOREEN POINT NORTH
L                                                                                                                                                                                                             153 LAKE FLAT ROAD,
                                                                                                                                                                                                                   SOREEN POINT,
                                                                                                                                                                                                                            QLD 4565
I:
                                                                                                                                                                                                                    PRELIMINARY
            REFERENCE DOCUMENTS

IJ
I. J
                                                                                                                                    NBNCo                                                               02 20.02.13 REVIEW UPDA TES
                                                                                                                                                                                                        01
                                                                                                                                                                                                        Rev
                                                                                                                                                                                                              11.02.13
                                                                                                                                                                                                               Date
                                                                                                                                                                                                                         PRELIMINARY ISSUE
                                                                                                                                                                                                                         Revision Details




L                                                                                                                                                                                                       .
                                                                                                                                                            Limited                                     aurecon
                                                                                                                                                                                                        Aurecon Australia Ply Ltd      ABN 54 005 139 873

Ij
                                                                                                                                                                                                         DESIGNER:                          JR
                                                                                                                               PROJECT SUMMARY
IJ                                                                                                                             PROPOSED NBN GREENFIELD 40m MONOPOLE
                                                                                                                                                                                                         CHECKED:                           MR
                                                                                                                                                                                                         APPROVED:                          JI
                                                                                                                               PROPOSED NBN OUTDOOR CABINETS ON CONCRETE SLAB ON GROUND                  Drawing Title:
           DISTRIBUTION
IJ         ERICSSON                               ROB GUY                                                             1
                                                                                                                           I
                                                                                                                                                                                                         COVER SHEET
           AURECON                                JAMES IRWIN


111                                                                                                                                                                                                      Drawing No.




1 :1   COPYRIGHT I{;> NBN Co LIMITED ABN 86136533741   ALL RIGHTS RESERVED. VERSION 10
                                                       .
                                                                                         -   SEPT 2011                                                                                    20   10   0        10          20         30

Page 64

                                                                                                                                                                                                                                                                                                  Client:

                                                                                                                    NBN ANTENNA CONFIGURA TION
                                                                                                                                                                                                                                                                                                                                       ~
                                                                             ANTENNA DETAIL                                                                          MAIN FEEDER DETAIL                        RRU DETAIL                                                     RF TAIL
                                                                                                                                                                                                                                                                                                                                      jiiIIiii=
 SECTOR      SYMBOL
                                                              DIMENSION                       AZIMUTH                                   QUANTITY                     OVERALL   CANISTER CANISTER TO
                                   TYPE                         HxWxD         ClL HEIGHT       (TN)     MECH TILT     DESTINATION         RAU          TYPE          LENGTH     HEIGHT    RRU LENGTH      TYPE                       LOCATION                          TYPE             LENGTH
                                                                                                                                                                                                                                                                                                    NBNCo
     1         ~         ARGUS-LLPX411F-2-V1                1180x300x115             40m        00           20           N/A             N/A                                                    2m       RRUS61         BELOW ANTOOA                                                    15m
                                                                                                                                                                                                                                                                                                                               Limited
                                                                                                                                                                                                                                                                     H8rS 1/2"
     2                                                                                                                                             H&S HYBRID 19mm     50m       38m                                                                            BIRD-PROOFED                      Client:

                                                                                                                                                                                                                                                                    L1SCA CABLE
     3        ~          ARGUS-LLPX411F-2-Vl                1180x300xl15             40m       2600          r            N/A             N/A                                                    2m       RRUS61         BELOW ANTENNA                                                   15m
                                                                                                                                                                                                                                                                                                                         :II!!
     4                                                                                                                                                                                                                                                                                                                   ;ii
     5                                                                                                                                                                                                                                                                                                       ERICSSON

     6

                                                                                                                                                     ERICSSON                                                                                                                                     Client:
     A
                ~              PARABOLIC                         1/>300          40.0m         1500       N/A         BOREEN POINT         1
                                                                                                                                                       7.6mm
                                                                                                                                                                       45m         -             -         -                              -                             -                 -




                                                                                                                                                     ERICSSON
     B         ~               PARABOLIC                          900            365m          3070      N/A          COONDOO WEST         2                           42m         -             -         -                              -                             -                 -




                                                                                                                                                       7.6mm
                                                                                                                                                     ERICSSON
     C         ~               PARABOLIC                          600            38.0m         2320      N/A        DA VID (OOTHARABA      1
                                                                                                                                                       7.6mm
                                                                                                                                                                       45m         -             -         -                              -                             -                 -




    D


     E
                                                                                                                                                                                                                                                                                                  Project
                                                                                                                                                     ERICSSON
   GPS                       KRE 1012082/1                     1/>69x96              2.5m      N/A       N/A              N/A             N/A                          10m         -             -         -                              -                             -                 -




                                                                                                                                                       7.6mm                                                                                                                                      NATIONAL BROADBAND
                                                                                                                                                                                                                                                                                                                    NETWORK

                                                                                                                                                                                                                                                                                                  SITE No: 4POM-51-36-BPN
          SITE INFORMA TION:                                                                                                                                                                                                                                                                      BOREEN POINT NORTH
                                                                                                                                                                                                                                          1
                                                                                                                                                                                                                                                                                                        153 LAKE FLAT ROAD,
         1. SITE ADDRESS
         LOT 2 ON RP126723, 153 LAKE FLAT ROAD, BOREEN POINT, QLD 4565


         2. GENERAL
                                                                                                         8. EXISTING SITE HAZARDS
                                                                                                         THE FOLLOWING HAZARDS ARE PRESENT ON THIS SITE:
                                                                                                         -
                                                                                                             COMMERCIAL FORESTRY PLANT ATION

                                                                                                                                                                                                                                         2
                                                                                                                                                                                                                                                                            @                                BOREEN POINT,
                                                                                                                                                                                                                                                                                                                      OLD 4565

                                                                                                                                                                                                                                                                                                              PRELIMINARY
         THE CONTRACTOR SHALL COMPL Y WITH ALL RELEVANT NBN                                              9. ELECTRICAL SUPPLY
         CONSTRUCTION ST ANDARDS, CURRENT AUSTRALIAN STANDARDS AND                                       SUPPLY AVAILABLE FROM EXISTING NETWORK. SUBJECT TO ENERGEX
         SPECIFICA TIONS.                                                                                OFFER. CLOSEST POLE APPROX. 50m AWAY.
                                                                                                                                                                                             B                                       0
                                                                                                                                                                                                                                              o
                                                                                                                                                                                                                                                  0
                                                                                                                                                                                                                                                      0
                                                                                                                                                                                                                             0
                                                                                                                                                                                                                                                          0
         3. SITE ACCESS                                                                                  10. TRANSMISSION LINK                                                                                       0
                                                                                                                                                                                                                         0


                                                                                                                                                                                                                   0                                                                              02    20.02.13 REVIEW UPOA TES
         SITE ACCESS OFF LAKE FLAT ROAD VIA EXISTING GA TES. EXISTING                                    REFER TO TABLE ABOVE.
                                                                                                                                                                                                                                                                oo~      p>
                                                                                                                                                                                                                                 .0
                                                                                                                                                                                                                                                                                                  01    11.02.1l   PRELIMINARY ISSUE
         4WD ACCESS, APPROX. 180m LONG, SHALL REQUIRE MINOR UPGRADE.                                                                                                                                                                                                                              Rev    Date      Revision Details
                                                                                                                                                                                                                                                      II-       0




                                                                                                                                                                                                      ~
                                                                                                                                                                                                                             .




         NO CLEARING REQUIRED.                                                                           11. ADDITIONAL INFORMATION                                                                                          .
                                                                                                                                                                                                                                 ~                              0


                                                                                                                                                                                                                 0




                                                                                                                                                                                                                                 .~.
                                                                                                         NO RETAINING WALLS ARE PROPOSED.
         4. EQUIPMENT                                                                                    NO LANDSCAPING is PROPOSED                                                                                                                                                               .
                                                                                                                                                                                                                                                                            .4

                                                                                                                                                                                                                                                                                                  aurecon
                                                                                                                                                                                                                                 ~~.
         PROPOSED NBN OUTDOOR CABINETS (ODC)TO BE INSTALLED ON                                           (REFER TO PLANNING REPORT).
                                                                                                                                                                                         3
         CONCRETE SLAB (<75m2)WITHIN NBN LEASE AREA.                                                     NO STORMWA TER DETENTION IS REQUiRED.                                                                                                                                                    Aurecon Australia Ply Ltd      ABN 54 005139873

                                                                                                         NO VEGETATION CLEARING IS REQUIRED.
                                                                                                                                                                                                                       """           ’V                   "’"

         5. STRUCTURE                                                                                    PAINTING/WARNING LIGHTS TO COMPLY WITH STATUTORY AUTHORITY
                                                                                                                                                                                                                                                                                   A
         PROPOSED NBN 40m MONOPOLE.                                                                      REQUIREMENTS.
                                                                                                                                                                                                          C                                                                                        DESIGNER:                          JR
                                                                                                                                                                                                                                                                                                   CHECKED:                           MR
         6. ANTENNA ACCESS
                                                                                                                                                                                                                                                                                                   APPROVED:                          JI
         ANTENNAS ARE PROPOSED TO BE ACCESSED USING LADDER AND
                                                                                                                                                                                                                                                                                                   Drawing Title:
         LAD-SAF BY RIGGER QUALIFIED PERSONNEL ONLY.
                                                                                                                                                                                                                                                                                                   SITE SPECIFIC NOTES                                       ...




         7. EXISTING SERVICES                                                                                                                                                                                                                                                                      AND ANTENNA TABLE
         THE CONTRACTOR SHALL IDENTIFY AND CONFIRM THE LOCATION OF ALL                                                                                                                                ANTENNA SETOUT PLAN
         RELEVANT EXISTING SERVICES AS REQUIRED PRIOR TO COMMENCEMENT
                                                                                                                                                                                                                                 SCALE 1:50                                                                                                       R
         OF WORKS.
                                                                                                                                                                                                                                                                                                   4P M~51-36-BPN-C11 iin
COPYRIGHT ~ NBN Co LIMITED ABN 86 136533741   .
                                                  ALL RIGHTS RESERVED. VERSION 10 SEPT 2011
                                                                                 -                                                                                                                                                                                            20   10         0        10           20        30           40         50mm
                                                                                                                                                                                                                                                                                                                                                             ~

Page 65

                                                                                                                                                                                                                                                                                               Client:

                                                                SITE LOCATION

                                                                                   II
                                                                                                                                ~       ~   ~    ~     w     *
                                                                                                                                                                                                                                                                                                                                   mil
                                                                                                                                                     17

           @_
                                                                                                         "



                                                                                                                                ~       ~   ~    ~~-   ~     ~




                                                                              L’
                                                                                                                                                 ,
                                                                               I



                                             .....~f’IIo.t         -~_j
                                                                                   "
                                                                                                                                                 I
                                                                                                                                                 ,..

                                                                                                                                                                                                                                                                                                 NBNCo
                                                                   ~~
                                                                                           ~~
                                                                                                                                                                                                                                             EXISTING ENERGEX                                                               Limited

                                                                                                                   ~,.
           ,.
                                                                                                                                                                                                                                             POLE 192199
                                                                                                                                                                                                                                                                                               Client:
           ~




                                                                                                                                                                                                                                                                                                                     :II
     ’f"                                                                                                                                    1                                                                                                                                                                        :ii
                                                                                                                                            \\
 .




 I
                                                                                                                                                                                PROPOSED SITE ACCESS
                                                                                                                                                                                                                                                                                                           ERICSSON
                                                                                                                                                                                        (APPROX.180m)
                                            "

                ~
                                                                                                                                             i

                                                                                                                                 ~




                                                                                                                                                \.h~
                                                              _"
           ~                                                                                                                                                                                                                                                                                   Client:




                                                                                                                                                           ....._~      ~
                                                                                                                                                                                                                                ~
                                                    ~


                                                                            (1                                                                   }I,. O.~- J.~J’
                                                                                                                                                      JJ Q~"!>...
                                                                                                                                                                                                                            \
                                                                                                                                                  ~
                                                                                                                                                       ’.....’"-1
                                                                                                                                                                    -

                                                                                                                                                                        0."
                                                                                                                                                                            -




                                                                                                                                                                                                                             ~~
 COPYRIGHT@ OPENSTREETMAP CONTRIBUTORS, CC BY-SA                                                                                                                                                                                 ~\
 http://www.openstreetmap.org
 http://creativecommons.org/licenceslby.sa/2.0/
                                                                                                                                                                                                                        LOT 2       \
 Use of this image is subject to the terms and conditions of the Creative Commons Attribution-ShareAlike 2.0

 licence, the full licence of which can be accessed at       http://creativecommons.ors/licenses/by-sa/2.0/Ie9alcode                                                                                                   RP 126723 ~       \                              ,
                                                                                                                                                                                                                                                                        )>
                                                                                                                                                                                                                                                                        ?"                      Project:



                                                                                                                                                                                                                                        V~
                                                                                                                                                                                                                                                                        I"Tl

                                                                                                                                                                                                                                                                        ."
                                                                                                                                                                                                                                                                        ,                      NATIONAL BROADBAND
                                                                                                                                                                                                                                                                        )>
                                                                                                                                                                                                                                                                         -t
                                                                                                                                                                                                                                                                                                                 NETWORK
                                                                                                                                                                                                                                                                         ;0
                                                                                                                                                                                                                                                                         o
                                                                                                                                                                                                                                                                         )>                    SITE No: 4POM-51-36-BPN
                                          SITE CO...ORDINATES                                                                                                                                                                                                            o




                                                             MONOPOLE LOCATION
                                                                                                                                                                                                                                        l                                                      BOREEN POINT NORTH
                                                                                                                                                                                                                                                                                                     153 LAKE FLAT ROAD,
                                                                                                                                                                                                                                        I     4

                                                                                                                                                                                                                                                    "-._
                                                                                                                                                                                                                                                                                                           BOREEN POINT,
                                       DATUM: MGA (GDA94)                                        I ZONE:                56
                                                                                                                                                                                                        LOT                                       """""=
                                                                                                                                                                                                                                                           4                                                       QLD 4565
                                                                                                                                                                                                                                                                   ~
                                       LA TlTUDE                                                                       -26.266700
                                                                                                                                                                                                      RP 109944                                                                                            PRELIMINARY
                                       LONGITUDE                                                                       152.980790                                                                                                                                   ~
                                                                                                                                                                                                                                                                    LOT 31
                                       EASTING                                                                              498 081
                                                                                                                                                                                                                                                                   SP 149578
                                       NORTHING                                                                         7 094 780
                                                                                                                                                                                                                                                C::::::>C      B
                                                                                                                                                                                                                                                                                               02    20.02.13 REVIEW UPOA TES
                                                                                                                                                                                                                                                                                               01    11.02.13   PRELIMINARY ISSUE
                                                                                                                                                                                                                                                                                               Rev    Date      Revision Details


                                                                                                                                                                                                                   OVERALL SITE PLAN
                                                                                                                                                                                                                                SCALE 1:10000
                                                                                                                                                                                                                                                                                               .

                                                                                                                                                                                                                                                                                               aUfeCOn
                                                                                                                                                                                                                                                                                               Aurecon Australia Pty LId      ABN 54 005 139873




                                                                                                                                                                                                                                                                                                DESIGNER:                          JR
                                                                                                                                                                                                                                                                                                CHECKED:                           MR
                                                                                                                                                             ADDITIONAL NOTES                                     NOTE:
           LEGEND                                                                                                                                                                                                                                                                               APPROVED:                          JI
                                                                                                                                                             NO RETAINING WALLS ARE PROPOSED.
                                                                                                                                                                                                                                                                                                Drawing Title:
                                                    EXISTING AERIAL ELECTRICAL LINES                                                                         NO LANDSCAPING IS PROPOSED                           1.   THE NBN SUB-MAIN ROUTE SHOWN ON THE DRAWINGS IS INDICA TlVE ONLY.
           -
                    A E   -
                                A E     -




                                                                                                                                                                                                                                                                                                OVERALL
                                                                                                                                                             (REFER TO PLANNING REPORT).                               ELECTRICAL CONTRACTOR TO DETERMINE EXACT ROUTE. ELECTRICAL
           -

                    /     -

                                   /   -

                                                    EXISTING PROPERTY FENCE                                                                                                                                                                                                                     SITE PLAN
                                                                                                                                                             NO STORMW A TER DETENTION IS REQUIRED.                    CONTRACTOR TO LOCATE AND IDENTIFY EXISTING U/G SERVICES PRIOR TO
                                                                                                                                                             NO VEGETATION CLEARING IS REQUIRED.                       COMMENCEMENT OF WORK.
                                                                                                                                                             PAINTING/WARNING LIGHTS TO COMPL Y WITH
                                                                                                                                                                                                                                                                                                Drawing No.
                                                                                                                                                             ST A TUTORY AUTHORITY REQUIREMENTS.


COPYRIGHT Q NBN Co LIMITED ABN 86136533741                              .
                                                                         ALL RIGHTS RESERVED. VERSION 10                -   SEPT 2011                                                                                                                                          20   10     o        10          20         30           40

Page 66

                                                                                                                                                                                                          Client:




     @                                                                                                                                                                                                                                        ~
                                                                                                                                                                                                                                                     ~



                                                                                                                                                                                                            NBNCo
                                                                                                                              /                                                                                                        Limited
                                                                                                                          ~
                                                                                                                          ~                                                                               Client:

                                                                                                                          /
                                                                                                                      ~
                                                                                                                      ~

                                                                                                                                                   PROPOSED NBN 3m WIDE ACCESS TRACK
                                                                                                                                                                                                                                :II!
                                                          ...
                                                                                                                                                   (APPROX.180m)                                                                ;i
                                                                                                                  ~                                                                                                   ERICSSON
                           PROPOSED NBN MONOPOLE FOOTING                                                          I
                           (INDICATIVE ONLY)                                                                                                       PROPOSED NBN 2x LLPX411F-V1 PANEL
                                                                                                                                                   ANTENNAS WITH NBN REMOTE RADIO UNITS TO
                                                                                                                                                                                                          Client:
                           PROPOSED GRA VEL OVER NBN                                                                                               BE FIXED BELOW THE PANEL ANTENNA
                           COMPOUND
                                              ~’f                                                                                                  PROPOSED NBN 40m MONOPOLE WITH
                           PROPOSED NBN 1x         900 PARABOLIC
                                                                                                                                                   CIRCULAR HEADFRAME
                           ANTENNA (TO COONDOO WEST)


                           PROPOSED NBN 1x         600 PARABOLIC                                                                                   PROPOSED NBN lx   300 PARABOLIC

                           ANTENNA (TO DAVID COOTHARABA)                                                                                           ANTENNA (TO BOREEN POINT)

                                                   ~
                                                                                                                                                   PROPOSED NBN 300 WIDE CABLE LADDER                      Project:

                                                                                                                                                   WITH (1-0FF)CABLE LADDER SUPPORT POST
                                                                                                                                                                                                          NATIONAL BROADBAND
                           PROPOSED NBN GPS UNIT (1-0FF)
                                                                                                                                                                                                                            NETWORK

                                                                                                                                                  PROPOSED NBN OUTDOOR CABINET SSC-02                     SITE No: 4POM-51-36-BPN
                           PROPOSED NBN 2.4m HIGH CHAINWIRE SECURITY                                                                              (COLOURED GREY) ON CONCRETE SLAB                        BOREEN POINT NORTH
                           FENCE WITH 3.Orn WIDE ACCESS GA TE
                                                                                                                                                                                                                153 LAKE FLAT ROAD,

                                               ~                                              I
                                                                                                                                                   FINAL ELECTRICAL CIRCUITS IN CONDUITS.
                                                                                                                                                   INST ALL AS PER AS/NZS 3000
                                                                                                                                                                                                                      BOREEN POINT,
                           PROPOSED NBN POWER DISTRIBUTION                                                                                                                                                                    OLD 4565
                           BOARD/METER PANEL ON H-FRAME
                                                                                                                                                   PROPOSED NBN OUTDOOR CABINET                                       PRELIMINARY
                                                                                              l                                                    SSC-02 (FUTURE LOCATION)
                                                                                                  I-I
                                                                                                        -I



                                                                                                                                                                                                          02    20.02.13   REVIEW UPOA TES

                                                                                                                                                                                                          01    11.02.13   PRElIMINARY ISSUE
                                                                                                                                                                                                          Rev    Date      Revision Details




                                                                                                                                                                                                          .

                                                                                                                                                                                                          aUfeCOn
                                                                                                                                                                                                          Aurecon Australia Ply Ltd      ABN 54 DOS 139873
       LEGEND

                                                                                                    DETAIL
       -
           NUE    -
                     NUE   -
                                 NBN UNDERGROUND ELECTRICAL LINES
                                                                                                    SCALE 1:100                                                                                            DESIGNER:                          JR
       -
           A E    -
                     A E   -
                                 AERIAL ELECTRICAL LINES                                                                                                                                                   CHECKED:                           MR
                                                                                                                                  NOTE:                                                                    APPROVED:                          JI
       -
             ec   -
                     ec    -
                                 FINAL ELECTRICAL CIRCUITS IN 2x SO                   HDPVC
                                                                                                                                                                                                           Drawing TiUe:
                                 UNDERGROUND ELECTRICAL CONDUIT
                                                                                                                                  1.   THE NBN SUB-MAIN ROUTE SHOWN ON THE DRAWINGS IS INDICATIVE ONLY.
                                                                                                                                                                                                           SITE SETOUT
       -
            /    -
                       /   -
                                 NBN COMPOUND SECURITY FENCE/BOUNDARY                                                                  ELECTRICAL CONTRACTOR TO DETERMINE EXACT ROUTE. ELECTRICAL
                                                                                                                                       CONTRACTOR TO LOCATE AND IDENTIFY EXISTING U/G SERVICES PRIOR TO    PLAN
                                                                                                                                       COMMENCEMENT OF WORK.

                                                                                                                                                                                                           Drawing No.

                                                                                                                                                                                                           4POM-51-36-BPN-C
COPYRIGHT Q NBN Co LIMITED ABN 86136533741. ALL RIGHTS RESERVED. VERSION 10   -   SEPT 2011                                                                                                                    10          20         30

Page 67

                                                                                                                                                                                                 Clienl:




                                                                          EL 40.0m                                                       EL 40.0m
                                                                      y                                                              y
                                                                          TOP OF MONOPPOLE                                               ClL 2x 1180H PROPOSED NBN PANEL ANTENNAS
                                                                                                                                             2x 500H REMOTE RADIO UNITS MOUNTED BELOW ANTENNA
                                                                          EL 38.0m
                                                                      y                                                                      1x NBN  300 PARABOLIC ANTENNA
                                                                          ClL 1x PROPOSED NBN CANISTER                                             OREEN POINT)                                  Client:


                                                                                                                                               m

                                                                                                                                            1x NBN 600 PARABOLIC ANTENNA
                                                                                                                                             (TO DA VID COOTHARABA)
                                                                                                                                                                                                                      :=I
                                                                                                                                         EL 36.5m                                                                     ;ii
                                                                                                                                         ClL 1x NBN 900 PARABOLIC ANTENNA
                                                                                                                                                                                                            ERICSSON
                                                                                                                                             (TO COONDOO WEST)

                                                                          PROPOSED NBN FEEDER CABLES TO BE
                                                                          RUN VERTICALLY INSIDE MONOPOLE                                                                                         Client:




                                                                          PROPOSED NBN 40m MONOPOLE WITH
                                                                          CIRCULAR HEADFRAME




                                                                                                                                                                                                 Project:


                                                                                                                                                                                                NATIONAL BROADBAND
                                                                                                                                                                                                                  NETWORK
                                                                                                                                                                                                SITE No: 4POM-51-36-BPN
                                                                                                                                                                                                BOREEN POINT NORTH
                                                                                                                                                                                                      153 LAKE FLAT ROAD,
                                                                                                                                                                                                            SOREEN POINT,
                                                                                                                                                                                                                    OLD 4565
                                                                  PROPOSED NBN 300 WIDE CABLE LADDER
                                                             WITH (1-0FF)CABLE LADDER SUPPORT POST                                                                                                          PRELIMINARY
                                                                                         \~ \~ \~
                                                                          PROPOSED NBN OUTDOOR CABINET
                                                                                        SSC-02 ON CONCRETE SLAB
                                                                                              /I   II   II
                                                                                                                                                                                                02    20.02.13 REVIEW UPDATES
                                                                          PROPOSED NBN OUTDOOR CABINET
                                                                                                                                                                                                01    11.02.13   PRELIMINARY ISSUE
                                                                                        SSC-02 (FUTURE LOCATION)                                                                                Rev   Date       Revision Details
                                                                                              II   II   1/

                                                                     PROPOSED NBN POWER DISTRIBUTION                                 PROPOSED NBN 2.4m HIGH CHAIN WIRE SECURITY
                                                                      BOARD/METER PANEL ON H-FRAME                                   FENCE WITH 10m WIDE ACCESS GATE                            .

                                                                                                                                                                                                aUfecon
                                                                                                                                                                                                Aurecon Australia Ply Ltd      ABN 54 005 139873
                                                                                                                                                    VEL
                                                                          PROPOSED

                                                                                                                                                                                                 DESIGNER:                          JR

                                                                                                                                                                                                 CHECKED:                           MR
                                                                                                                                                                                                 APPROVED:                          JI
                                                                                                                                                                                                 Drawing Title:

                                                                                                                                                                                                 SITE ELEVATION
                                                                                                                   EAST ELEVATION                                                                AND DETAILS
                                                                                                                       SCALE 1:200
                                                                                                                                                                                                 Drawing No.




COPYRIGHT Q NBN Co LIMITED ABN 86136533741. ALL RIGHTS RESERVED. VERSION 10   -
                                                                                  SEPT 2011

Page 68

Appendix 5
Environmental Searches




NBN-4NBZ-4POM-5136   -
                         Boreen Point North   Page 79


[OCR of page images]
Appendix 5

Environmental Searches

NBN-4NBZ-4POM-5136 — Boreen Point North Page 79

Page 69

Appendix 4
Code Table Assessment

Compliance with the Boreen Point, Kin Kin & Cootharaba Locality Code
.   .                                                               ",.                                                    .-   ...   .".~-
                                                                          ~.,.........   ("                                                    -.,

                    I
           (
               (            (                              :   I                                               ’
                :       r       1   \
                                        (                                                                          r


                                                                                                                       .
                                                                                  .                                        .




4.9 Effects of use


Amenity                                     No solution provided.                 01    Complies.
                                                                                          -




01 Uses are located,                                                              The   proposed development will
designed and operated to                                                          not result in any impacts to
avoid significant adverse                                                         lighting, air quality, noise or
changes to the light, air                                                         accessibility conditions within the
quality, noise, accessibility or                                                  surrounding area.
other conditions enjoyed by
users of associated, adjoining                                                    Furthermore, potential visual and
or nearby uses.                                                                   amenity   impacts have      been
                                                                                  considered      through       the
                                                                                  comprehensive    site   selection
                                                                                  process. An appropriate site has
                                                                                  been        identified which         is able to
                                                                                  meet          the       target           coverage
                                                                                  objectives, as well as minimising
                                                                                  visual impacts to the surrounding
                                                                                  area associated with the proposed

                                                                                  development                                                        ’




                                                                                  The subject site is considered to
                                                                                  be appropriately located given its
                                                                                  adequate separation distance from
                                                                                  community sensitive land uses.
                                                                                  Within       a    500    m       radius         of the
                                                                                 facility      there  only
                                                                                                         are      (3)      three
                                                                                 existing residential dwellings, with
                                                                                 the remainder of the surrounding
                                                                                 area     characterised    by   large
                                                                                 farming       properties,    heavily
                                                                                 vegetated hinterland areas and
                                                                                 large rural-residential allotments
                                                                                  which       are   well removed from the
                                                                                  subject site.

                                                                                  The presence of large                    areas              of
                                                                                  mature     vegetation                on                the
                                                                                  property     and      within    the
                                                                                  surrounding area, particularly to
                                                                                  the north, south and east, will act
                                                                                  to   mitigate    potential   visual
                                                                                  impacts and help to provide
                                                                                  screening to the surrounding
                                                                                  residential           dwellings,             Boreen
                                                                                  Point       Village    and   scenic vistas
                                                                                  such as Lake Cootharaba.


                                                                                  For these reasons, the subject site

Page 70

                                                                                  .                              .




                                                                      is considered             appropriate for the
                                                                      establishment                of        a        new

                                                                      telecommunications              facility and
                                                                      will       result    in    minimal amenity
                                                                      impacts.

    Major Road Network              No solution provided.             02   Complies.
                                                                             -




    02The function of, and visual                                     The  subject site is not located
    amenity and character                                             adjacent to a Major Road Network.
    surrounding, the major road                                       However the proposed facility is
    network, including Pomona-                                        located adjacent to Lake Flat Road
    Kin Kin-Wolvi Road,                                               to the north. Views towards the
    Cootharaba Road, Dr Pages                                         facility from this road c rridor are
    Road and Sister Tree Creek                                        considered to be limited given the
    Road is protected and                                             extent of mature vegetation which
    enhanced.                                                         exists    along the eastern lot
                                                                      boundary of the property. At 40 m
                                                                      in height, the majority of the
                                                                      proposed facility will be screened
                                                                      from view by this vegetation.
                                                                      Additionally, views from passing
                                                                      motorists           will     be     of      limited
                                                                      duration.           The     facility       is   well
                                                                      removed         from        other      significant
                                                                      transport routes.

                                                                      Therefore the proposal                 complies
                                                                      with 02.

    4.10 Built Form


    Density                         53.1 For the Village Mix          03 Not applicable.
                                                                             -




    03The density of                Zone-residential density does The       proposed facility is not a
    development within the site     not exceed a rate of 1 dwelling   residential development and is
    area-                           unit per non-residential use.     also not located within the Village
    a) is compatible with                                             Mix Zone.
    surrounding development;
    b) has a low site impact to                                       However,              the
                                                                                             development
    enhance the opportunity to                                        footprint comprising an area of 70
    maintain natural site                                             m2     is   relatively minor     and
    characteristics, i ncl udi ng                                     consistent with the scale of existing
    native vegetation and natural                                     infrastructure in the surrounding
.
    landforms.                                                        area (eg. power stanchions and

                                                                      light poles).

                                                                      The slimline monopole   design (as
                                                                      opposed to a lattice type structure)
                                                                      will reduce the visual dominance
                                                                      the structure when viewed from a
                                                                      distance             including             adjacent
                                                                      properties,           roads         and
                                                                      surrounding areas. Additionally, the
                                                                      facility .may be colour matched to
                                                                      its surroundings (at the request
                                                                      council) to further reduce its visual
                                                                      appearance.


                                                                      Existing vegetation on site will be
                                                                      retained and used to help screen

Page 71

                                                                 the proposed facility.

Height                            S4.1 Buildings and other       04    -
                                                                           Complies.
04 Bu dings and other             structures have a maximum      The        proposed development            is
structures-                       building height of-            located within the Rural Zone and
a) are low rise and present a   a) if in the Rural or Rural      comprises a monopole structure of
building height consistent with Settlement                       40 m in height and therefore does
structures on adjoining and     Zone-8m, or 9m where the         not   comply with the maximum
surrounding premises;           pitched                          building height specified in S4.1
b) have a maximum building      roof but no other part of the    (a). However the use is considered
height of 2 storeys;            bu ding or structure exceeds     to    be   compatible    with  the
c) do not visually dominate the 8m; or                           surrounding area and          thus
street, surrounding spaces or   b) if in the Industry Zone-10m   complies with 04 for the following
the existing skyline;           c) in all other zones- 8m.       reasons:

d) preserve the amenity of                                        .        the   development         has been
surrounding premises                                                       located within an area which
including privacy, views and                                               generally comprises of low
access to sunlight;                                                        density        rural-residential
e) respect the scale of the                                                development and is well
surrounding vegetation; and                                                removed from neighbouring
f) respond to the topography                                               residential   dwellings     and
of the site and minimises                                                  Boreen Point Village;
                                                                  .
                                                                           existing infrastructure uses in
                                                                           the area (such as powerlines
                                                                           and poles) will ensure the
                                                                           facility is of a scale and
                                                                           height consistent with the
                                                                           surrounding environment;
                                                                  .
                                                                           existing vegetation within the
                                                                           property       and    the     wider
                                                                           surrounding area will screen
                                                                           the lower margins of the
                                                                           facility; and
                                                                  .        the proposed height is the
                                                                           minimum required to achieve
                                                                           the       required    coverage
                                                                           objectives and provide line of
                                                                           sight to the adjoining facilities
                                                                           in    the    area  (specifically
                                                                           Boreen Point, Coondoo West
                                                                           and       David       Cootharaba
                                                                       (Davis Road Cootharaba).
                                                                 (refer to Section 8.1 for additional
                                                                 visual assessment)


                                                                 For these reasons, the              height of
                                                                 the facility is considered to comply
                                                                 with 04.

Setbacks                          S5.1 Bu dings and structures   55.1   -
                                                                            Complies.
05 Buildings and other            comply with the setbacks       Table 1.1         of Schedule 1        of the
structures are appropriately      identified in Schedule 1-      Noosa        Plan    2009      specifies   a

designed and sited to-            Minimum Boundary Setbacks.     minimum           frontage      and      side
a) provide amenity for users of                                  setback in the Rural Zone of 10m.
the premises, as well as
preserve the visual and                                          The       proposed       facility    complies
acoustic privacy of adjoining                                    with       s5.1     as    it   is     setback
and nearby land uses;                                            approximately 250 m from the
b) preserve existing                                             western    lot  boundary and

Page 72

                                                           ..


                                                                "




vegetation that will buffer                                         approximately               1     km    from     the
the proposed building from                                          southern            lot
                                                                                     boundary.                       The

adjoining uses;                                                     propo~ed facility is also setback
c) allow for landscaping to be                                      approximately 40 m from the
provided between buildings;                                         northern          frontage        to    Lake     Flat
d) maintain the visual                                              Road          and      over      600    m   to   the
continuity and pattern of                                           eastern           frontage        to    Lake     Flat
buildings and landscape                                             Road.
elements within the street; and                                     The        location       of the
                                                                                           facility has
e) help protect the natural                                         been          selected      in
                                                                                            attempt toan

character and visual amenity                                        mlnlmlse    visual  and     amenity
of the Noosa River system.                                          impacts, whilst also avoiding the
                                                                    loss or fragmentation of productive
                                                                    rural         land. These         setbacks       are

                                                                    also       compliant        with       05   as   the
                                                                    location        will    maintain        the visual
                                                                    amenity for those travelling along
                                                                    the       Lake       Flat        Road    and     the
                                                                    residential         dwellings to the north
                                                                    east.


                                                                    05   Complies.
                                                                          -




                                                                    The   proposed facility is also
                                                                    compliant with 05 as it is:
                                                                    .   well removed from community
                                                                              sensitive locations, significant
                                                                              areas     of mature           vegetation
                                                                              exist    on     site and within the
                                                                              surrounding area which will
                                                                              help to mitigate potential
                                                                              visual impacts associated with
                                                                              the development,
                                                                    .         is consistent with the visual
                                                                              continuity, of the surrounding
                                                                              area as it has been co-located

                                                                            with        existing       infrastructure
                                                                              uses      in the       area    (such as
                                                                              power        stanchions       and   light
                                                                              p  les)
                                                                    .,no          landscaping or vegetation
                                                                              removal i,s proposed as part
                                                                              of this development and will
                                                                              not. impact on the NQosa
                                                                              River system

SitQ cover                         No solution provided.            06 Not applicable.
                                                                          -




06 The site cover of buildings                                      The    proposed facility is not a
and other roofed structures-                                        building     or    roofed    structure.
a) is of a scale that is                                            However,         the     development
compatible with surrounding
                     ,
                                                                    footprint comprising an area of 70
development;                                                        m2     is    relatively   minor    and
b)for a class 1 or class 10a                                        consistent with the scale of existing
structure with the Detached                                         infrastructure in the surrounding
HoUsing Zone, does not                                              area     specifically the energex
exceed-                                                             electricity corridor which contains
   i.   for a single storey                                         power poles and lines running from
        building 50%; or
                 -
                                                                    north to south through the subject
  ii.   for a building of 2 or                                      site (approximately 20 m east
        more storeys     -
                             50%                                    the proposed facility).

Page 73

            on the   ground floor                                  The slimline monopole design (as
            and 30% for the upper                                  opposed to a lattice type structure)
          storey(s), or 40% for                                    will reduce the visual dominance of
          all storeys for a                                        the structure when viewed from a
          building of 2 or more                                    distance      including     adjacent
          storeys;                                                 properties,    roads    and     other
c)for other classes within the                                     surrounding areas. Additionally, the
Detached Housing Zone         -

                                                                   facility may be colour matched to
40%;                                                               its surroundings (at the request of
d) does not present an                                             council) to further reduce its visual
appearance of bulk to                                              appearance.
adjacent properties, roads or
other areas in the vicinity of                                     Existing vegetation on site will be
the site;                                                          retained and used to help screen
e) maximises the retention of                                      the proposed facility (refer to
existing vegetation and allows                                     Section    8.1   for additional visual
for additional soft landscaping                                    assessment).
between buildings;
f) allows for adequate area at                                     Therefore        the      proposal      is
ground level for outdoor                                           consistent with 06.
recreation, entertainment,
clothes drying and other site
facilities; and
g)facilitates onsite stormwater
management and vehicular
access.


Flooding and drainage           S7.1 For new buildings or          57.1 Not Applicable.
07Buildings and other works     structures or additions of more    The      development        is   not
are designed and sited to-      than 50m2gross floor area to       habitable use
a) provide flood free access to an existing building or

premises  and flood free        structure, floor levels for        57.2 Not Applicable.
habitable areas;                    habitable rooms are-           No       Council       Infrastructure
b) allow only minor, short term a)for areas where minimum         available for use.
and infrequent flooding of non- floor levels are available-not
habitable areas;                less than the specified level;    57.3 Not Applicable.
c) ensure carparking areas      b) for areas where flood          No car parking is proposed as
can be adequately drained;      modelling is                      of this development.
d) ensure drainage does not     available-a minimum of
adversely impact upon    other  500mm                             57.4 Not Applicable.
premises;  and                  above   the modelled flood level; No basements are proposed as
e) ensure filling or excavation and                               part of this development.
does not adversely impact       c)for areas where flood
upon other premises by-         modelling is not available, a     57.5 Not Applicable.
    i.   causing ponding of     minimum of 500mm above the No basements are proposed as
        water on the site or    highest known flood level;        part of this development.
         nearby land;
   ii.   increasing flooding,   AND                               07 Complies.
                                                                        -




        which adversely                                           The proposed facility has been
         affects the safety or  S7.2 Where Council                located outside of areas identified
            use of any land         infrastructure is              on   the Natural Hazard: Landslide
            upstream and            available-                     &     Flooding    Overlay        as

            downstream; and         a) any drainage (from buildings containing a ’Flood Hazard Area’
  Hi.       adversely affecting     and land)flows to that          and land ’Subject to minimum floor
            the flow of water in    infrastructure; and             Additionally     the     proposed
            any overland flow       b) the infrastructure has the   telecommunications facility is not
            path.                   capacity to accept any          for a habitable use and has been
                                    additional loading;             sited and designed to minimise the
                                                                    hazards associated with flooding.

Page 74

                                  AND                               For example the foundations and
                                                                    earthworks          are     to     follow
                                  57.3 Car parking and              engineering design standards and
                                  maneuvering areas are             stormwater dissipation is provided
                                  constructed at a level that       through the proposed          gravel
                                  permits the parking area to       compound finish. Any discharge
                                  drain from the site by gravity    points will not affect downstream,
                                  means, without the need for       upstream or underground streams
                                  mechanical                        on any adjoining properties as the

                                  pumping; or                       proposed facility is not a generator
                                                                    of effluent run off.
                                  57.4 Basements for residential
                                  uses have flood   immunity
                                  above the Q1 00 where
                                  alternative means to
                                  mechanical pumping are used
                                  to achieve such immunity; or


                                  57.5 Basements for non-
                                  residential uses have flood
                                  immunity above the Q1 00 that
                                  may be achieved by means of
                                  mechanical pumping where the
                                  mechanical feature is
                                  installed with adequate holding
                                  tanks and an alternative back
                                  up power source.


5ense of arrival to Kin Kin       No solution provided.             08   -   Not applicable.
08 Uses, buildings, structures                                      The proposed facility is not located
and other works do not have                                         within the township of Kin Kin.
an adverse effect on the visual

amenity of the entry points to
Kin Kin village, including the
sense of arrival to the village

provided by-
a) the rural landscape
immediately prior to the
township;
b) the avenue of pine trees
along Pomona-Kin Kin Road;
c) the Main Street/Pomona-
Kin Kin Road junction; and
d) Sister Tree Creek Road.
Visual amenity in Soreen          No solution provided.             09   -
                                                                             Complies.
Point village
                                                                    The       subject    site   is   located
09 Uses, buildings, structures
                                                                    outside of open space corridors
and other works do not have
                                                                    and the specific location of the
an adverse  impact .pon-
   views    Lake Cootharaba
                                                                    facility is not within existing native
a)       to
and beyond from roads and
                                                                    vegetation as outlined on Map 4
                                                                    Open Space Networks. The
public open spaces;.and
                                                                    proposed facility has also been
b) the visual amenity from                                          setback from public open spaces
Louis Bazzo Drive, including
                                                                    within the wider area, specifically
the sense of arrival in the
                                                                    900 m from Lake Cootharaba and
village provided by-                                                              from the Boreen Field
                                                                    over 2 km
the rural landscape
                                                                    Park and Boreen Point Foreshore
immediately prior to the

Page 75

village; and the vegetation on   Par and will not impact on views
lots at the western end of       to   Lake Cootharaba and beyond
Laguna Street;                   from     roads      and           public    open
                                 spaces.

                                 Additionally the subject site is not
                                 located on the Heritage Overlay as
                                 being located within proximity to
                                 any heritage sites or character
                                 areas. The proposed facility will

                                 not adversely impact upon the
                                 visual amenity or sense of arrival
                                 in the Soreen Point village as it
                                 has been located over 2 km from
                                 Louis       Sazzo      Drive       and Laguna
                                 Street identified         as      key areas of
                                 09b.


                                 The   proposed facility has been
                                 appropriately located to minimise
                                 visual and amenity impacts to
                                 residential dwellings, Soreen Point
                                 Village and scenic vistas within the
                                 wider area by:
                                 .      The       corridor          of      mature
                                        vegetation which separates
                                        the facility from the edge of
                                        the lake in conjunction with
                                        the    900        m        setback      will
                                        mitigate          potential         visual
                                        impacts         from        recreational
                                        users of Lake Cootharaba.

                                 .
                                        Although          the
                                                         facility has
                                        been sited adjacent to Lake
                                        Flat Road (not identified as a
                                        Major Road Network on the
                                        Noosa Plan Strategy Map) a
                                        sense      of     arrival        into   the
                                        Soreen Point village will be
                                        maintained as the facility will
                                        only      become           intermittently
                                        visible      at       a     few      minor
                                        clearings in the vegetation
                                        aligning the road. These
                                        views are not anticipated to
                                        be visually obtrusive as Lake
                                        Flat Road is travelled by
                                        motor vehicles only at a
                                        constant speed and does not
                                        provide any opportunities for
                                        vehicles              to          become
                                        stationary.
                                 .      At    40 m      in height, the
                                        majority of the proposed
                                        facility will be screened from
                                        view by this vegetation, of
                                        which the tallest tree is 25 m.
                                 .      Visual impacts will be further
                                        mitigated         by       the    slimline

Page 76

                                      monopole        design        and     be
                                      colour        matched         to     the
                                  surroundings (if requested
                                  by Council).
                                . The   proposed facility has
                                  been appropriately sited on
                                  the    periphery   of   the
                                      concentrated                residential
                                      dwellings (aligning Kildeys
                                      Road) and over 2 km from
                                      the Soreen Point township
                                      which will essentially help
                                      mitigate any views from
                                       Louis Sazzo Drive.
                                .      It     is    also      located        an

                                      appropriate           setback        from
                                      community            sensitive       land
                                       uses and     residential dwellings
                                      where there are only three (3)
                                       residential    dwellings within a
                                      500 m radius of the facility.


                                (refer to Section 8.1 for additional
                                visual assessment)

010 Uses, buildings,            010     Complies.
                                        -




structures and other works      The    proposed facility will be
are   designed and sited to     approximately 15 m above the
maintain the visual             existing tree canopy where the
dominance of the tree canopy    tallest tree is approximately 25 m
and other natural features      high.     The    proposed    height
along the water’s edge of       however is essential to allow the
Lake Cootharaba;                panel antennas to have clear line
                                of sight above the tree canopy to
                                the surrounding premises (radio
                                coverage), and also ensure that
                                the radio transmission              dish    has
                                clear line of sight to the adjoining
                                network        facilities    at     Coondoo
                                West, Soreen          Point and           David
                                Cootharaba             (Davis              Road
                                Cootharaba) in         order to link the
                                sites       back    into     the      broader
               ..




          ..
                                network.


                                Notwithstanding this the facility
                                has  been appropriately setback
                                over 900 m from the water’s edge

                                of Lake Cootharaba. Therefore the
                                proposal is considered to be
                                appropriately   sited   a   large
                                seperation distance from the lake
                                in    order to      maintain      the visual
                                dominance of the tree canopy and
                                other natural features             along    the
                                water’s edge of Lake Cootharaba.

011 Uses, buildings,            011     -   Not applicable.
structures and other works on   The proposed facility is not located
Soreen Parade and Urunga        adjacent       to   Soreen        Parade

Page 77

Parade maintain or improve                                          Urunga Parade.
the visual amenity of this
esplanade.
Materials and finishes           512.1 Buildings and structures     012   -
                                                                               Complies.
012 Buildings and other          incorporate  a mix of textured     NBN Co proposes to construct a
structures use materials and     external building materials,       new    telecommunication  facility
finishes that complement the     such as timber cladding and        consisting of a 40 m slim line
rural heritage character and     corrugated iron roofs.             monopole with three (3) panel
integrate with the surrounding                                      antennas (1180 mm x 300 mm x
natural landscape.                                                  115 mm) which will be mounted to
                                                                    a     circular     headframe      at   a

                                                                    centreline       elevation   of   40   m.

                                                                    Additionally      three   (3) parabolic
                                                                    dish antennas are proposed. Two
                                                                    (2)outdoor cabinets founded on a
                                                                    concrete slab at the base of the
                                                                    monopole are also proposed.

                                                                    The    monopole was selected for
                                                                    the   proposal due to its slim line
                                                                    appearance and minimal visual
                                                                    obtrusiveness when viewed from a
                                                                    distance.


                                                                    The   monopole design is deemed
                                                                    to    be more appropriate than a

                                                                    lattice tower as it can be painted

                                                                    a colour (At Council’s request) that

                                                                    will provide for visual integration
                                                                    and camouflage the facility with
                                                                    the surrounding landscape and
                                                                    vegetation
Roof form                        513.1 With the exception of        013 Not applicable.
                                                                          -




013 Roof forms-                  industrial                         The    proposed development does
a)contribute positively to the   buildings the main roof of the     not involve a building.
local skyline;                   building has a roof pitch no
b) complement the low rise       less than 12 degrees and has
character of the locality;       minimum 600mm eaves to at
c) use simple traditional roof   least 75% of
designs, such as hipped,         the perimeter of the building;
gabled and skillion; and
d) do not create opportunities   AND
for residents to overlook the
private open space areas of      513.2 Building and structures
neighbouring properties.         do not include rooftop terraces.

Page 78

Sloping sites                     S14.1 Buildings are of split                 014 Not applicable.
                                                                                      -




014 On sloping sites,             level design that step down the The                 proposed facility will be
buildings and structures are      slope        or have   suspended floor       developed on flat land for which
designed to maxi mise the use     construction; (See Figure 4-1                minimal earthworks are required
of natural slope and minimise     below)                                       (refer    to   compliance     with
the need for cut and fill.                                                     Earthworks Code at Section 7.2.3).
                                  AND


                                  S14.2 Cut or fill is less than 2m
                                  in depth relative to natural
                                  ground surface;

                                  AND


                                  S14.3 The distance between
                                  the ground and the lowest part
                                  of the floor of the building does
                                  not exceed 3m to avoid large
                                  under building areas.


                                  Figure 8.1-Design for
                                  sloping sites (suspended
                                  floor)
                                  :;\J~
                                  ,
                                          ~.


                                          ~1IIf.:




4.11 Environment, Conservation and Recreation


Environment & cultural            No solution provided.                        015    -
                                                                                          Complies.
heritage values                                                                The        proposal is        appropriately
015 There are no significant                                                   located within        a   low density rural
adverse effects on                                                             area       used for
                                                                                              farming purposes
the biodiversity, natural                                                      and     will  require vegetation
                                                                                              not
vegetation, native wildlife,                                                   removal. The proposed facility has
habitats, landscape quality,                                                   been       located    outside      of   areas

water quality or cultural                                                      mapped as ’Riparian Buffer Area’,
heritage values, including                                                     ’Koala         Habitat       Area’        and
those related to-                                                              ’Environmental               Enhancement
a)changes to natural                                                           Area’ on the Biodiversity Overlay.
drainage;
b) disturbance to any of the                                                   Although the proposed facility is
wetland systems;                                                               located approximately 60 m from
                                                                           .




c) management of landslide                                                     the border of the Great Sandy
and fire risk;                                                                 National       Park, the       location    is
d) erosion and the transport of                                                considered     appropriate as the
sediments off site;                                                            facility will be separated from the
e) unmanaged public access;                                                    National Park by a bitumen road
f) effluent disposal                                                           and located       over     350 m from the
g) changes to fauna habitat                                                    closest portion of mapped remnant
and behaviour; and                                                             vegetation        within     the    National
h) disturbance of buildings                                                    Park.       The
                                                                                            proposed facility is
and features, including natural                                                otherwise appropriately setback
features, of cultural heritage                                                 from   environmentally sensitive
significance.                                                                  areas (eg more than 900 m from

The text continues on page 79.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.