SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 7 MARCH 2017
Page 40 of 55
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 7 MARCH 2017
Works BRI % of Annual
Project Original Carryover BR2 Current Year To Date Remaining Budget Spent
Code Finance Project Num ber - Description Budget Budget Budget Budget YID Actual Comm itments (Actuals )
Total Trans port and Infrastructure Management 3,460,000 3,780,846 1,964,044 294,524 131,124 61,764 3.79%
Waste Management
500640 500112 - Noosaville Landfil- Dosing & Monitoring Equipment 0 120,000 120,000 20,000 15,390 14,256 12.83%
500681 500681 - Noosaville Landfill Entrance Road to Briteside, Stage 2 165,000 165,000 165,000 41,250 0 0.00%
500682 500682 - Noosaville Landfill Gravity Sewer from Holding Tank at Clean 25,000 25,000 25,000 25,000 27,964 1,767 111.85%
500683 500683 - Noosaville Landfill Entrance Signage and Landscaping 26,000 26,000 26,000 0 0 0.00%
500709 500709 - Noosaville Eumundi Rd Landfill Expand Contractors Vehicle Pa 282,000 282,000 282,000 132,000 207,579 2.492 73.61%
Total Waste Management 498.000 618,000 618.000 218.250 250,932 18,515 50.39%
Other Capital 43 eT 4,491.2 ert oe oy
Asset Management
500684 500684 - Whole of Shire, Asset Condition Assessments 250,000 250,000 250,000 21,250 122 0.05%
500685 500685 - Whole of Shire, Pavement System and Analysis for Reseal Prog 100,000 100,000 104,790 41,000 20,252 10,275 19.33%
500686 500686 - Whole of Shire, Annual Level 3 Bridge Inspection Program 40,000 40,000 40,000 11,600 13,940 21,825 34.85%
500687 500687 - Whole of Shire, CCTV Drainage Program 125,000 125,000 125,000 55,000 63,045 16,335 50.44%
500688 500688 - Whole of Shire, Review of Standard Drawings 25,000 25,000 25,000 2,500 0 0.00%
500710 500710 - Whole of Shire, T1 Asset Systems Mobility Rollout & Hardware 250,000 250,000 250,000 120,000 92.311 4,755 36.92%
Total Asset Management 790.000 790,000 794.790 251,350 189.670 53,190 24.01%
Fleet - Plant Replacement
500518 500518 - Plantand Fleet Replacement Program 1,765,000 2,151,438 2,151,438 1,297,438 1,312,206 417,503 60.99%
Total Fleet -Plant Replacement 1,765,000 2,151,438 2,151,438 1,297,438 1,312,206 417,503 74.35%
Information Technology
500075 500075 - Whole of Shire - Tech One HR module 0 0 0 0 25 4,152 0.00%
500076 500076 - Whole of Shire - Mobile Mapping 0 0 0 0 329 0.00%
500078 500078 - Whole of Shire - replace failed UPS 0 0 0 0 375 0.00%
500542 500542 - Implementation of CIAnywhere Functionality for TechnologyOn 0 54,606 54,606 44,606 19,181 37,322 35.13%
500689 500689 - Whole of Shire, Meeting Room Projectors and Smart Television 17,580 17,580 17,580 17,580 7,007 633 39.86%
500711 500711 - Whole of Shire, CI Anywhere Functionality Implementation 200,000 200,000 200,000 68,525 45,000 4,283 22.50%
500712 500712 - Whole of Shire, mplement Eplan online Planning Scheme T1 140,000 140,000 140,000 48,750 13.687 0.00%
500713 500713 - Whole of Shire, Wireless enable Council Buildings 26,000 26,000 26,000 11,250 0.00%
500721 500721 - Black Mountain Repeater Replacement 0 0 6.923 6.923 6,923 100.00%
Total Information Technology 383,580 438,186 445,109 197,634 79,041 60.077 20.61%
Planning Scheme
500107 500107 - Noosa River Hydraulic Model 0 76,304 76,304 76.304 28,384 9,920 37.20%
500203 500203 - Business Distribution and Land Needs Project 0 0 0 0 1,515 0.00%
500543 500543 - Whole of Shire Plannng Scheme Development Projects 2016 0 176,618 176,618 176.618 145,306 9,122 82.27%
500714 500714 - Whole of Shire, Climate Change Adaptation Strategy 100,000 100,000 100,000 40,000 0 0.00%
500715 500715 - Whole of Shire, Consultant Costs for Planning Scheme Develop 100,000 100,000 100,000 50,000 0 0.00%
500716 500716 - Whole of Shire, Project Team Resources for New Planning Sche 546.963 546,963 546.963 239,150 222,203 40.62%
500717 500717 - Six Mile Creek Flood Study 100,000 100,000 100,000 61,000 18,020 80,025 18.02%
Total Planning Scheme 846,963 1,099,885 1,099,885 643,072 415,427 99,067 49.05%
Grand Total 23,101,168 26,989,587 25,449,321 8,143,833 6,425,844 6,158,494 27.82%
Oe
Page 40 of 55See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.